Item Descripción Und. Metrado
1.00 OBRAS PROVICIONALES
1.01 CASETA DE GUARDIANIA Y ALMACEN GLB 1.00
1.02 CERCO PERIMETRICO CON ARPILLERA ML 50.24
2.00 TRABAJOS PRELIMINARES
2.01 LIMPIEZA DEL TERRENO M2 119.87
2.02 TRAZO NIVEL Y REPLANTEO M2 119.87
3.00 MOVIMIENTO DE TIERRAS
3.01 EXCAVACION DE CIMIENTOS CORRIDOS Fc= 100 Kg/cm2 M3 86.23
3.02 EXCAV MANUAL ZAPATAS M3 12.61
3.03 RELLENO COMPACTADO M/PROPIO (zanjas y zapatas) M3 9.55
3.04 ELIMINACION MATERIAL EXCEDENTE M3 107.16
4.00 OBRAS CONCRETO SIMPLE
4.01 CIMIENTOS CORRIDOS Y SUB ZAPATAS F'c = 100 Kg / cm2 M3 80.17
4.02 SOBRECIMIENTOS F'c = 175 Kg / cm2 M3 2.79
4.03 ENCOFRADO Y DESENCOFRADO DE SOBRECIMIENTO M2 37.49
5.00 OBRAS DE CONCRETO ARMADO
ZAPATAS
5.01 ZAPATAS F'c = 210 Kg / cm2 M3 4.42
5.02 ENCOFRADO ZAPATAS M2 4.06
5.03 ACERO ZAPATAS F'y 4200 Kg/cm2 Kg 91.58
VIGAS DE CIMENTACION
5.04 VIGAS DE CIMENTACION f'c=210kg/cm" M3 1.34
5.05 ENCOFRADO DE VIGAS DE AMARRE M2 17.87
5.06 ACERO VIGAS DE CIMENTACION F'y =4200 Kg/cm2 Kg 199.83
COLUMNAS
5.07 COLUMNAS CONCRETO F'c =210kg/cm" M3 17.39
5.08 ENCOFRADO Y DESENCOF. EN COLUMNAS M2 225.98
5.09 ACERO EN COLUMNAS F'y 4200 Kg/cm2 Kg 2898.16
VIGAS
5.10 VIGAS CONCRETO F'c =210kg/cm" M3 11.53
5.11 ENCOFRADO Y DESENCOF. EN VIGAS M2 75.13
5.12 ACERO EN VIGAS F'y 4200 Kg/cm2 Kg 1404.16
LOSAS ALIGERADAS
5.13 LOSAS ALIGERADAS CONCRETO f'C=210kg/cm" M3 10.98
5.14 ENCOFRADO - DESENCOF. EN LOSAS ALIGERADAS M2 127.98
5.15 LADRILLO HUECO 15X30X30 CM P/TECHO ALIGERADO M2 1087.83
5.16 ACERO EN LOSAS ALIGERADAS F'y 4200 Kg/cm2 Kg 943.84
ESCALERAS
5.17 ESCALERAS f'C=175kg/cm" M3 5.66
5.17 ESCALERAS ENCOFRADO Y DESENCOFRADO M2 40.55
5.18 ACERO EN ESCALERAS F'y 4200 Kg/cm2 Kg 336.75
6.00 MUROS Y TABIQUES DE ALBAÑILERIA
6.01 MURO DE LADRILLO KK DE ARCILLA SOGA M2 223.98

COSTO DIRECTO
GASTOS GENERALES Y UTILIDADES 8%
TOTAL PRESUPUESTO
PRESUPUESTO 01 PRIMER NIVEL HASTA CASCO GRIS INSUMOS
1.00 MANO DE OBRA 33,142.17 35%
2.00 MATERIALES 57,762.08 61%
3.00 HERRAMIENTAS Y EQUIPOS 3,787.68 4%
COSTO DIRECTO S/. 94,691.93 100%

Precio S/. Parcial S/.
1,614.85 0.00 0.00
600.00 600.00
20.20 1014.85 NOTENGO COSTO SIQUIERAS LO DEJAS
327.24
1.05 125.86
1.68 201.38
4,829.33
28.00 2414.53
28.00 353.22
13.9 132.75
18 1928.83
13,838.25
156.90 12578.04
222.98 622.92
17.00 637.30
2,083.35
351.48 1551.87
17.00 69.02
5.05 462.46
1,719.31
303.15 406.34
CHEQUEA17 303.82
5.05 1009.14
25,493.38
351.48 6112.18
21 4745.50
5.05 14635.70
12,722.68
351.48 4054.04
21.00 1577.63
5.05 7091.01
15,234.87
351.48 3859.57
24.27 3106.07
3.22 3502.81
5.05 4766.42
4,541.00
351.48 1988.81
21.00 851.62
5.05 1700.58
12287.67
54.86 12287.67

94,691.93
8,522.27
S/. 103,214.20
PRESUPUESTO 01 PRIMER NIVEL HASTA CASCO GRIS INSUMOS

H O J A D E M E T R A D O S OBRA VIVIENDA UNIFAMILIARPROPIETARIO : Familia Balabarca Muñoz
DISTRITO :Mz H Lote 08 Urb, La Catedral - Dist. de Sachaca
FECHA : ABRIL 2011 HECHO POR : ESL
NRO TITULO DE PARTIDA NRO MEDIDAS SUB
PARTIDA VECES LARGO ANCHO ALTO PARCIAL PARCIAL
1.00 OBRAS PROVICIONALES1.01 CASETA DE GUARDIANIA Y ALMACEN 1 1.001.02 CERCO PERIMETRICO CON ARPILLERA mas 1 m X lado
(considerar 50 cm en cada lado)FACHADA 1 7.850 1.000 8.85LADO DERECHO 1 15.270 1.000 16.27LADO IZQUIERDO 1 15.270 1.000 16.27FONDO 1 7.850 1.000 8.85
2.00 TRABAJOS PRELIMINARES2.01 LIMPIEZA DEL TERRENO
AREA AREA TOTAL TERRENO 119.87
2.02 TRAZO NIVEL Y REPLANTEOAREA AREA TOTAL TERRENO 119.87
3.00 MOVIMIENTO DE TIERRAS
3.01 EXCAVACION DE CIMIENTOS CORRIDOS Fc= 100 Kg/cm2
CC-2 EJE A ( 1 - 2 ) 1 0.700 0.700 1.900 0.93
CC-3 EJE A' (4 - 5 ) 1 2.850 0.500 1.400 1.99
CC-2 EJE B (1 - 2 ) 1 0.660 0.700 1.900 0.88
CC-3 EJE B ( 2 - 5) 1 4.480 0.500 1.400 3.14
CC-4 EJE B' ( 3 - 5) 1 3.430 0.500 1.400 2.40
CC-3 EJE C ( 1- 2) 1 2.000 0.500 1.400 1.40
CC-2 EJE C ( 4- 5 ) 1 2.070 0.700 1.900 2.75
CC-4 EJE C' ( 4- 5 ) 1 1.300 0.500 1.400 0.91
CC-3 EJE D ( 1- 2 ) 1 2.000 0.500 1.400 1.40
CC-2 EJE D ( 4- 5 ) 1 2.290 0.700 1.900 3.05
CC-3 EJE E (1- 5 ) 1 4.760 0.500 1.400 3.33
CC-5 EJE F (1- 5 ) 1 7.050 0.400 1.000 2.82
CC-1 EJE 1 ( A- E ) 1 13.320 0.700 1.900 17.72
CC-1 EJE 1 ( B ) 1 1.200 0.250 1.900 0.57
CC-1 EJE 1 ( E) 1 1.000 0.500 1.900 0.95
CC-5 EJE 1 ( F) 1 1.950 0.400 1.000 0.78
CC-2 EJE 2 (A - B) 1 4.700 0.700 1.900 6.25
CC-2 EJE 2 (A) 1 1.000 0.580 1.900 1.10
CC-2 EJE 2 (B) 1 1.200 0.370 1.900 0.84
CC-3 EJE 3 ( B- C) 1 0.800 0.500 1.400 0.56
CC-2 EJE 4 (B-E) 1 6.680 0.700 1.900 8.88
CC-2 EJE 4 (C) 1 1.000 0.450 1.900 0.86
CC-2 EJE 4 (C') 1 1.100 0.570 1.900 1.19

H O J A D E M E T R A D O S OBRA VIVIENDA UNIFAMILIARPROPIETARIO : Familia Balabarca Muñoz
DISTRITO :Mz H Lote 08 Urb, La Catedral - Dist. de Sachaca
FECHA : ABRIL 2011 HECHO POR : ESL
NRO TITULO DE PARTIDA NRO MEDIDAS SUB
PARTIDA VECES LARGO ANCHO ALTO PARCIAL PARCIAL
CC-1 EJE 5 (A-E) 1 13.320 0.700 1.900 17.72
CC-1 EJE 5 (A) 1 1.600 0.150 1.900 0.46
CC-1 EJE 5 (C`) 1 1.100 0.300 1.900 0.63
CC-1 EJE 5 (E 1 1.000 0.500 1.900 0.95
CC-5 EJE 5( F) 1 1.950 0.400 1.000 0.78
85.23
EXCAVACION DE CIMIENTO PARA ESCALERA
ESCALERA 1 (A - B) 1 1.000 0.500 1.000 0.50
ESCALERA 1 (C) 1 1.000 0.500 1.000 0.50
1.00
3.02 EXCAV MANUAL ZAPATAS
ZAPATA 01 3 1.450 1.450 2.000 12.61
3.03 RELLENO COMPACTADO M/PROPIO (zanjas)
CC-2 EJE A ( 1 - 2 ) 1 0.700 0.550 0.100 0.04
CC-3 EJE A' (4 - 5 ) 1 2.850 0.150 0.300 0.13
CC-2 EJE B (1 - 2 ) 1 0.660 0.550 0.100 0.04
CC-3 EJE B ( 2 - 5) 1 4.480 0.350 0.300 0.47
CC-4 EJE B' ( 3 - 5) 1 3.430 0.350 0.100 0.12
CC-3 EJE C ( 1- 2) 1 2.000 0.350 0.300 0.21
CC-2 EJE C ( 4- 5 ) 1 2.070 0.550 0.100 0.11
CC-4 EJE C' ( 4- 5 ) 1 1.300 0.350 0.100 0.05
CC-3 EJE D ( 1- 2 ) 1 2.000 0.350 0.300 0.21
CC-2 EJE D ( 4- 5 ) 1 2.290 0.550 0.100 0.13
CC-3 EJE E (1- 5 ) 1 4.760 0.350 0.300 0.50
CC-5 EJE F (1- 5 ) 1 7.050 0.250 0.100 0.18
CC-1 EJE 1 ( A- E ) 1 13.320 0.550 0.100 0.73
CC-1 EJE 1 ( B ) 1 1.200 0.250 0.100 0.03
CC-1 EJE 1 ( E) 1 1.000 0.500 0.100 0.05
CC-5 EJE 1 ( F) 1 1.950 0.250 0.100 0.05
CC-2 EJE 2 (A - B) 1 4.700 0.550 0.100 0.26
CC-2 EJE 2 (A) 1 1.000 0.580 0.100 0.06
CC-2 EJE 2 (B) 1 1.200 0.370 0.100 0.04
CC-4 EJE 3 ( B- C) 1 0.800 0.350 0.100 0.03
CC-2 EJE 4 (B-E) 1 6.680 0.550 0.100 0.37
CC-2 EJE 4 (C) 1 1.000 0.450 0.100 0.05
CC-2 EJE 4 (C') 1 1.100 0.570 0.100 0.06
CC-1 EJE 5 (A-E) 1 13.320 0.550 0.100 0.73
CC-1 EJE 5 (A) 1 1.600 0.150 0.100 0.02

H O J A D E M E T R A D O S OBRA VIVIENDA UNIFAMILIARPROPIETARIO : Familia Balabarca Muñoz
DISTRITO :Mz H Lote 08 Urb, La Catedral - Dist. de Sachaca
FECHA : ABRIL 2011 HECHO POR : ESL
NRO TITULO DE PARTIDA NRO MEDIDAS SUB
PARTIDA VECES LARGO ANCHO ALTO PARCIAL PARCIAL
CC-1 EJE 5 (C`) 1 1.100 0.300 0.100 0.03
CC-1 EJE 5 (E 1 1.000 0.500 0.100 0.05
CC-5 EJE 5( F) 1 1.950 0.250 0.100 0.05
4.79
3.04 ELIMINACION MATERIAL ZAPATAS Area relleno
ZAPATA (Columna Rec) 1 1.000 1.953 0.800 1.56
ZAPATA (Columna Cir) 2 1.000 2.000 0.800 3.20
3.05 ELIMINACION MATERIAL EXCEDENTE Excav. Rellen. 20% Expon
Excavacion total menos relleno+20% esponjam 1 98.848 9.551 89.30 107.16
4.00 OBRAS CONCRETO SIMPLE
4.01 CIMIENTOS CORRIDOS Y SUB ZAPATAS F'c = 100 Kg / cm2
CC-2 EJE A ( 1 - 2 ) 1 0.700 0.700 1.800 0.88
CC-3 EJE A' (4 - 5 ) 1 2.850 0.500 1.000 1.43
CC-2 EJE B (1 - 2 ) 1 0.660 0.700 1.800 0.83
CC-3 EJE B ( 2 - 5) 1 4.480 0.500 1.000 2.24
CC-4 EJE B' ( 3 - 5) 1 3.430 0.500 1.000 1.72
CC-3 EJE C ( 1- 2) 1 2.000 0.500 1.000 1.00
CC-2 EJE C ( 4- 5 ) 1 2.070 0.700 1.800 2.61
CC-4 EJE C' ( 4- 5 ) 1 1.300 0.500 1.000 0.65
CC-3 EJE D ( 1- 2 ) 1 2.000 0.500 1.000 1.00
CC-2 EJE D ( 4- 5 ) 1 2.290 0.700 1.800 2.89
CC-3 EJE E (1- 5 ) 1 4.760 0.500 1.000 2.38
CC-5 EJE F (1- 5 ) 1 7.050 0.400 0.900 2.54
CC-1 EJE 1 ( A- E ) 1 13.320 0.700 1.800 16.78
CC-1 EJE 1 ( B ) 1 1.200 0.250 1.800 0.54
CC-1 EJE 1 ( E) 1 1.000 0.500 1.800 0.90
CC-5 EJE 1 ( F) 1 1.950 0.400 0.900 0.70
CC-2 EJE 2 (A - B) 1 4.700 0.700 1.800 5.92
CC-2 EJE 2 (A) 1 1.000 0.580 1.800 1.04
CC-2 EJE 2 (B) 1 1.200 0.370 1.800 0.80
CC-4 EJE 3 ( B- C) 1 0.800 0.500 1.000 0.40
CC-2 EJE 4 (B-E) 1 6.680 0.700 1.800 8.42
CC-2 EJE 4 (C) 1 1.000 0.450 1.800 0.81

H O J A D E M E T R A D O S OBRA VIVIENDA UNIFAMILIARPROPIETARIO : Familia Balabarca Muñoz
DISTRITO :Mz H Lote 08 Urb, La Catedral - Dist. de Sachaca
FECHA : ABRIL 2011 HECHO POR : ESL
NRO TITULO DE PARTIDA NRO MEDIDAS SUB
PARTIDA VECES LARGO ANCHO ALTO PARCIAL PARCIAL
CC-2 EJE 4 (C') 1 1.100 0.570 1.800 1.13
CC-1 EJE 5 (A-E) 1 13.320 0.700 1.800 16.78
CC-1 EJE 5 (A) 1 1.600 0.150 1.800 0.43
CC-1 EJE 5 (C`) 1 1.100 0.300 1.800 0.59
CC-1 EJE 5 (E 1 1.000 0.500 1.800 0.90
CC-5 EJE 5( F) 1 1.950 0.400 0.900 0.70
77.01
ZAPATAS 3 1.450 1.450 0.500 3.15
3.15
4.02
CC-2 EJE A ( 1 - 2 ) 1 1.250 0.150 0.400 0.08
CC-2 EJE B (1 - 2 ) 1 0.810 0.150 0.400 0.05
CC-4 EJE B' ( 3 - 5) 1 4.150 0.150 0.400 0.25
CC-2 EJE C ( 4- 5 ) 1 1.300 0.150 0.400 0.08
CC-4 EJE C' ( 4- 5 ) 1 1.300 0.150 0.400 0.08
CC-2 EJE D ( 4- 5 ) 1 1.300 0.150 0.400 0.08
CC-5 EJE F (1- 5 ) 1 6.950 0.150 0.400 0.42
CC-1 EJE 1 ( A- F ) 1 11.620 0.150 0.400 0.70
CC-2 EJE 2 (A - B) 1 2.200 0.150 0.400 0.13
CC-4 EJE 3 ( B- C) 1 0.750 0.150 0.400 0.05
CC-2 EJE 4 (B-E) 1 3.400 0.150 0.400 0.20
CC-1 EJE 5 (A-E) 1 11.530 0.150 0.400 0.69
2.79
4.05 ENCOFRADO Y DESENCOFRADO DE SOBRECIMIENTO
CC-2 EJE A ( 1 - 2 ) 2 1.250 0.000 0.400 1.00
CC-2 EJE B (1 - 2 ) 2 0.810 0.000 0.400 0.65
CC-4 EJE B' ( 3 - 5) 2 4.150 0.000 0.400 3.32
CC-2 EJE C ( 4- 5 ) 2 1.300 0.000 0.400 1.04
CC-4 EJE C' ( 4- 5 ) 2 1.300 0.000 0.400 1.04
CC-2 EJE D ( 4- 5 ) 2 1.300 0.000 0.400 1.04
CC-5 EJE F (1- 5 ) 2 6.950 0.000 0.400 5.56
CC-1 EJE 1 ( A- F ) 2 11.620 0.000 0.400 9.30
CC-2 EJE 2 (A - B) 2 2.200 0.000 0.400 1.76
CC-4 EJE 3 ( B- C) 2 0.750 0.000 0.400 0.60
CC-2 EJE 4 (B-E) 2 3.400 0.000 0.400 2.72
CC-1 EJE 5 (A-E) 2 11.530 0.000 0.400 9.22
Tapas de sobrecimientos 1 0.600 0.000 0.400 0.24
37.49
SOBRECIMIENTOS F'c = 175 Kg / cm2

H O J A D E M E T R A D O S OBRA VIVIENDA UNIFAMILIARPROPIETARIO : Familia Balabarca Muñoz
DISTRITO :Mz H Lote 08 Urb, La Catedral - Dist. de Sachaca
FECHA : ABRIL 2011 HECHO POR : ESL
NRO TITULO DE PARTIDA NRO MEDIDAS SUB
PARTIDA VECES LARGO ANCHO ALTO PARCIAL PARCIAL
5.00 OBRAS DE CONCRETO ARMADO
5.01 ZAPATAS f' c = 210 Kg / cm2Z-1 3 1.450 1.450 0.700 4.42
5.02 ENCOFRADO ZAPATASZ-1 1 5.800 0.700 4.06
5.04 VIGAS DE CIMENTACION f'c=210kg/cm"
CC-3 EJE A' (4 - 5 ) 1 4.150 0.150 0.400 0.25
CC-3 EJE B ( 2 - 5) 1 5.290 0.150 0.400 0.32
CC-3 EJE C ( 1- 2) 1 3.950 0.150 0.400 0.24
CC-3 EJE D ( 1- 2 ) 1 3.950 0.150 0.400 0.24
CC-3 EJE E (1- 5 ) 1 5.000 0.150 0.400 0.30
1.34
5.05 ENCOFRADO DE VIGAS DE AMARRE
CC-3 EJE A' (4 - 5 ) 2 4.150 0.000 0.400 3.32
CC-3 EJE B ( 2 - 5) 2 5.290 0.000 0.400 4.23
CC-3 EJE C ( 1- 2) 2 3.950 0.000 0.400 3.16
CC-3 EJE D ( 1- 2 ) 2 3.950 0.000 0.400 3.16
CC-3 EJE E (1- 5 ) 2 5.000 0.000 0.400 4.00
17.87
5.06 ACERO5.07 COLUMNAS CONCRETO f'C=210kg/cm"
PRIMER NIVEL
C1 Zapata 1 0.600 0.250 3.325 0.50C1 Columna 1 0.600 0.250 3.325 0.50C2 13 0.500 0.150 2.625 2.56C3 (Columna circular) 2 A= 0.098 3.325 0.65C4 2 0.400 0.150 2.625 0.32C5 2 0.250 0.250 2.625 0.33P1 2 0.850 0.150 2.625 0.67P2 1 0.850 0.200 2.625 0.45P3-P3-A 3 1.000 0.150 2.625 1.18P4-P5 2 0.850 0.150 2.625 0.67P6 2 0.800 0.200 2.625 0.84C-A MURO PERIMETRICO 5 0.150 0.300 3.000 0.67

H O J A D E M E T R A D O S OBRA VIVIENDA UNIFAMILIARPROPIETARIO : Familia Balabarca Muñoz
DISTRITO :Mz H Lote 08 Urb, La Catedral - Dist. de Sachaca
FECHA : ABRIL 2011 HECHO POR : ESL
NRO TITULO DE PARTIDA NRO MEDIDAS SUB
PARTIDA VECES LARGO ANCHO ALTO PARCIAL PARCIAL
C-A INTERIOR EJE 4 2 0.150 0.300 2.625 0.249.57
SEGUNDO NIVEL
C1 Zapata 2 0.600 0.250 2.425 0.73C2 13 0.500 0.150 2.425 2.36C4 4 0.400 0.150 2.425 0.58C5 2 0.250 0.250 2.425 0.30P1 2 0.850 0.150 2.425 0.62P2 1 0.850 0.200 2.425 0.41P3-P3-A 3 1.000 0.150 2.425 1.09P4-P5 2 0.850 0.150 2.425 0.62P6 2 0.800 0.200 2.425 0.78C-A 3 0.150 0.300 2.425 0.33
7.82
5.08 ENCOFRADO Y DESENCOF. EN COLUMNASPRIMER NIVEL
C1 Zapata 1 1.700 3.325 5.65C1 Columna 1 1.550 3.325 5.15C2 13 1.000 2.625 34.13C3 (Columna circular) 2 1.111 3.325 7.39C4 2 0.800 2.625 4.20C5 2 0.750 2.625 3.94P1 2 1.850 2.625 9.71P2 1 1.900 2.625 4.99P3-P3-A 3 2.150 2.625 16.93P4-P5 2 1.850 2.625 9.71P6 2 1.650 2.625 8.66C-A MURO PERIMETRICO 5 0.600 3.000 9.00C-A INTERIOR EJE 4 2 0.750 2.625 3.94
123.40
SEGUNDO NIVEL
C1 2 1.650 2.425 8.00C2 13 1.000 2.425 31.53C4 4 0.800 2.425 7.76C5 2 0.750 2.425 3.64P1 2 1.850 2.425 8.97P2 1 1.900 2.425 4.61P3-P3-A 3 2.150 2.425 15.64P4-P5 2 1.850 2.425 8.97P6 2 1.650 2.425 8.00C-A 3 0.750 2.425 5.46
102.58
5.07 VIGA

H O J A D E M E T R A D O S OBRA VIVIENDA UNIFAMILIARPROPIETARIO : Familia Balabarca Muñoz
DISTRITO :Mz H Lote 08 Urb, La Catedral - Dist. de Sachaca
FECHA : ABRIL 2011 HECHO POR : ESL
NRO TITULO DE PARTIDA NRO MEDIDAS SUB
PARTIDA VECES LARGO ANCHO ALTO PARCIAL PARCIAL
CONCRETO VIGAS f'C=210kg/cm"PRIMER NIVEL
VA-1 EJE A ( 1 - 5) 1 7.550 0.250 0.200 0.38VA-1 EJE B ( 1 - 5) 1 7.550 0.250 0.200 0.38VA-2 EJE C ( 1 - 5) 1 7.550 0.250 0.200 0.38VA-2 EJE C´ ( 1 - 5) 1 7.550 0.250 0.200 0.38VA-1 EJE D ( 1 - 5) 1 7.550 0.250 0.200 0.38VA-1 EJE E ( 1 - 5) 1 7.550 0.250 0.200 0.38VS-1 EJE 1 ( A - E) 1 13.320 0.400 0.150 0.80VS-1 EJE 2 ( A - B) 1 3.620 0.400 0.150 0.22VA-1 EJE 3 (A - E) 1 11.820 0.250 0.200 0.59VA-2 EJE 4 (B - E) 1 8.050 0.250 0.200 0.40VA-2 EJE 4' (C - D) 1 1.250 0.250 0.200 0.06VS-1 EJE 5 ( A - E) 1 13.320 0.400 0.150 0.80VB EJE A (2-5) 1 6.350 0.250 0.200 0.32VB EJE E (1-5) 1 4.800 0.300 0.200 0.29VB EJE C (2-5) 1 1.250 0.100 0.200 0.03
5.77
SEGUNDO NIVEL
VA-1 EJE A ( 1 - 5) 1 7.550 0.250 0.200 0.38VA-1 EJE B ( 1 - 5) 1 7.550 0.250 0.200 0.38VA-2 EJE C ( 1 - 5) 1 7.550 0.250 0.200 0.38VA-2 EJE C´ ( 1 - 5) 1 7.550 0.250 0.200 0.38VA-2 EJE D ( 1 - 5) 1 7.550 0.250 0.200 0.38VA-1 EJE E ( 1 - 5) 1 7.550 0.250 0.200 0.38VS-1 EJE 1 ( A - E) 1 13.320 0.400 0.150 0.80VS-1 EJE 2 ( A - B) 1 3.620 0.400 0.150 0.22VA-1 EJE 3 (A - E) 1 11.820 0.250 0.200 0.59VA-2 EJE 4 (B - E) 1 8.050 0.250 0.200 0.40VA-2 EJE 4' (C - D) 1 1.250 0.250 0.200 0.06VS-1 EJE 5 ( A - E) 1 13.320 0.400 0.150 0.80VB EJE A (2-5) 1 6.350 0.250 0.200 0.32VB EJE E (1-5) 1 4.800 0.300 0.200 0.29VB EJE C (2-5) 1 1.250 0.100 0.200 0.03
5.77
5.08 ENCOFRADO Y DESENCOF. EN VIGASPRIMER NIVEL
VA-1 EJE A ( 1 - 2) 1 2.100 0.100 0.21VA-1 EJE A ( 2- 5) 1 5.050 0.250 1.26VA-1 EJE B ( 1 - 2) 1 2.100 0.100 0.21VA-1 EJE B ( 2 - 5) 1 5.050 0.250 1.26VA-2 EJE C ( 1 - 4) 1 4.300 0.250 1.08VA-2 EJE C ( 4 - 5) 1 3.000 0.100 0.30VA-2 EJE C´ ( 1 - 5) 1 4.300 0.250 1.08

H O J A D E M E T R A D O S OBRA VIVIENDA UNIFAMILIARPROPIETARIO : Familia Balabarca Muñoz
DISTRITO :Mz H Lote 08 Urb, La Catedral - Dist. de Sachaca
FECHA : ABRIL 2011 HECHO POR : ESL
NRO TITULO DE PARTIDA NRO MEDIDAS SUB
PARTIDA VECES LARGO ANCHO ALTO PARCIAL PARCIAL
VA-2 EJE C´ ( 1 - 5) 1 3.000 0.100 0.30VA-1 EJE D ( 1 - 5) 1 4.300 0.250 1.08VA-1 EJE D ( 1 - 5) 1 3.000 0.100 0.30VA-1 EJE E ( 1 - 5) 1 7.050 0.100 0.71VS-1 EJE 1 ( A - E) 1 13.320 0.400 5.33VS-1 EJE 2 ( A - B) 1 2.600 0.400 1.04VS-1 EJE 2 ( A - B) 1 1.620 0.550 0.89VA-1 EJE 3 (A - E) 1 11.820 0.250 2.96VA-2 EJE 4 (B - E) 1 8.050 0.250 2.01VA-2 EJE 4' (C - D) 1 1.250 0.250 0.31VS-1 EJE 5 ( A - E) 1 13.320 0.400 5.33VB EJE A (2-5) 1 6.350 0.250 1.59VB EJE E (1-5) 1 4.800 0.300 1.44VB EJE C (2-5) 1 1.250 0.100 0.13TAPAS DE VIGAS 1 43.840 0.200 8.77
37.56
SEGUNDO NIVEL
VA-1 EJE A ( 1 - 2) 1 2.100 0.100 0.21VA-1 EJE A ( 2- 5) 1 5.050 0.250 1.26VA-1 EJE B ( 1 - 2) 1 2.100 0.100 0.21VA-1 EJE B ( 2 - 5) 1 5.050 0.250 1.26VA-2 EJE C ( 1 - 4) 1 4.300 0.250 1.08VA-2 EJE C ( 4 - 5) 1 3.000 0.100 0.30VA-2 EJE C´ ( 1 - 5) 1 4.300 0.250 1.08VA-2 EJE C´ ( 1 - 5) 1 3.000 0.100 0.30VA-1 EJE D ( 1 - 5) 1 4.300 0.250 1.08VA-1 EJE D ( 1 - 5) 1 3.000 0.100 0.30VA-1 EJE E ( 1 - 5) 1 7.050 0.100 0.71VS-1 EJE 1 ( A - E) 1 13.320 0.400 5.33VS-1 EJE 2 ( A - B) 1 2.600 0.400 1.04VS-1 EJE 2 ( A - B) 1 1.620 0.550 0.89VA-1 EJE 3 (A - E) 1 11.820 0.250 2.96VA-2 EJE 4 (B - E) 1 8.050 0.250 2.01VA-2 EJE 4' (C - D) 1 1.250 0.250 0.31VS-1 EJE 5 ( A - E) 1 13.320 0.400 5.33VB EJE A (2-5) 1 6.350 0.250 1.59VB EJE E (1-5) 1 4.800 0.300 1.44VB EJE C (2-5) 1 1.250 0.100 0.13TAPAS DE VIGAS 1 43.840 0.200 8.77
37.56
5.10 LOSAS ALIGERADASCONCRETO LOSAS ALIGERADAS f'C=210kg/cm"PRIMER NIVEL

H O J A D E M E T R A D O S OBRA VIVIENDA UNIFAMILIARPROPIETARIO : Familia Balabarca Muñoz
DISTRITO :Mz H Lote 08 Urb, La Catedral - Dist. de Sachaca
FECHA : ABRIL 2011 HECHO POR : ESL
NRO TITULO DE PARTIDA NRO MEDIDAS SUB
PARTIDA VECES LARGO ANCHO ALTO PARCIAL PARCIAL
LOSASCOMEDOR 1 A = 10.240 0.050 0.51BARRA 1 A = 2.930 0.050 0.15COCINA 1 A = 9.750 0.050 0.49DEPOSITO 1 A = 3.000 0.050 0.15ESTAR 1 A = 10.700 0.050 0.54PASADIZO 1 A = 2.880 0.050 0.14BAÑO 1 A = 6.240 0.050 0.31COCHERA 1 A = 15.020 0.050 0.75PASADIZO FRONTAL 1 A = 3.230 0.050 0.16VIGETASCOMEDOR 8 3.130 0.100 0.150 0.38BARRA 8 0.900 0.100 0.150 0.11COCINA 8 3.000 0.100 0.150 0.36DEPOSITO 3 2.410 0.100 0.150 0.11ESTAR 7 3.130 0.100 0.150 0.33PASADIZO 11 0.900 0.100 0.150 0.15BAÑO 4 3.000 0.100 0.150 0.18COCHERA 9 4.150 0.100 0.150 0.56PASADIZO FRONTAL 9 0.900 0.100 0.150 0.12
5.49
SEGUNDO NIVEL
LOSASCOMEDOR 1 A = 10.240 0.050 0.51BARRA 1 A = 2.930 0.050 0.15COCINA 1 A = 9.750 0.050 0.49DEPOSITO 1 A = 3.000 0.050 0.15ESTAR 1 A = 10.700 0.050 0.54PASADIZO 1 A = 2.880 0.050 0.14BAÑO 1 A = 6.240 0.050 0.31COCHERA 1 A = 15.020 0.050 0.75PASADIZO FRONTAL 1 A = 3.230 0.050 0.16VIGETASCOMEDOR 8 3.130 0.100 0.150 0.38BARRA 8 0.900 0.100 0.150 0.11COCINA 8 3.000 0.100 0.150 0.36DEPOSITO 3 2.410 0.100 0.150 0.11ESTAR 7 3.130 0.100 0.150 0.33PASADIZO 11 0.900 0.100 0.150 0.15BAÑO 4 3.000 0.100 0.150 0.18COCHERA 9 4.150 0.100 0.150 0.56PASADIZO FRONTAL 9 0.900 0.100 0.150 0.12
5.49

H O J A D E M E T R A D O S OBRA VIVIENDA UNIFAMILIARPROPIETARIO : Familia Balabarca Muñoz
DISTRITO :Mz H Lote 08 Urb, La Catedral - Dist. de Sachaca
FECHA : ABRIL 2011 HECHO POR : ESL
NRO TITULO DE PARTIDA NRO MEDIDAS SUB
PARTIDA VECES LARGO ANCHO ALTO PARCIAL PARCIAL
5.11 ENCOFRADO - DESENCOF. EN LOSAS ALIGERADASPRIMER NIVEL
COMEDOR 1 A = 10.240 10.24BARRA 1 A = 2.930 2.93COCINA 1 A = 9.750 9.75DEPOSITO 1 A = 3.000 3.00ESTAR 1 A = 10.700 10.70PASADIZO 1 A = 2.880 2.88BAÑO 1 A = 6.240 6.24COCHERA 1 A = 15.020 15.02PASADIZO FRONTAL 1 A = 3.230 3.23
63.99
SEGUNDO NIVEL
COMEDOR 1 A = 10.240 10.24BARRA 1 A = 2.930 2.93COCINA 1 A = 9.750 9.75DEPOSITO 1 A = 3.000 3.00ESTAR 1 A = 10.700 10.70PASADIZO 1 A = 2.880 2.88BAÑO 1 A = 6.240 6.24COCHERA 1 A = 15.020 15.02PASADIZO FRONTAL 1 A = 3.230 3.23
63.99
5.12 LADRILLO HUECO 15X30X30 CM P/TECHO ALIGERADOPRIMER NIVEL
COMEDOR 1 A = 10.240 8.500 87.04BARRA 1 A = 2.930 8.500 24.91COCINA 1 A = 9.750 8.500 82.88DEPOSITO 1 A = 3.000 8.500 25.50ESTAR 1 A = 10.700 8.500 90.95PASADIZO 1 A = 2.880 8.500 24.48BAÑO 1 A = 6.240 8.500 53.04COCHERA 1 A = 15.020 8.500 127.67PASADIZO FRONTAL 1 A = 3.230 8.500 27.46
543.92
SEGUNDO NIVEL
COMEDOR 1 A = 10.240 8.500 87.04BARRA 1 A = 2.930 8.500 24.91COCINA 1 A = 9.750 8.500 82.88DEPOSITO 1 A = 3.000 8.500 25.50

H O J A D E M E T R A D O S OBRA VIVIENDA UNIFAMILIARPROPIETARIO : Familia Balabarca Muñoz
DISTRITO :Mz H Lote 08 Urb, La Catedral - Dist. de Sachaca
FECHA : ABRIL 2011 HECHO POR : ESL
NRO TITULO DE PARTIDA NRO MEDIDAS SUB
PARTIDA VECES LARGO ANCHO ALTO PARCIAL PARCIAL
ESTAR 1 A = 10.700 8.500 90.95PASADIZO 1 A = 2.880 8.500 24.48BAÑO 1 A = 6.240 8.500 53.04COCHERA 1 A = 15.020 8.500 127.67PASADIZO FRONTAL 1 A = 3.230 8.500 27.46
543.92
5.14 ESCALERAS f'C=175kg/cm"PRIMER NIVEL
ESCALERAS 1 ( A- B)CIMIENTO 1 1.000 0.500 1.000 0.50TRAMO 1 1 A= 0.479 1.050 0.50TRAMO 2 1 A= 0.574 1.050 0.60ESCALERAS 1 ( C)CIMIENTO 1 1.000 0.500 1.000 0.50TRAMO 1 1 A= 0.479 1.025 0.49TRAMO 2 1 A= 0.574 1.025 0.59
SEGUNDO NIVEL
ESCALERAS 1 ( A- B)TRAMO 3 1 A= 0.596 1.050 0.63TRAMO 4 1 A= 0.596 1.050 0.63ESCALERAS 1 ( C)TRAMO 3 1 A= 0.596 1.025 0.61TRAMO 4 1 A= 0.596 1.025 0.61
5.15 ESCALERAS ENCOFRADO Y DESENCOFRADOPRIMER NIVEL
ESCALERAS 1 ( A- B)CONTRAPASOS 14 0.175 1.050 2.57TRAMO 1 ( COSTADO) 1 A= 0.479 0.48TRAMO 2 (COSTADO) 1 A= 0.574 0.57TRAMO 1 (FONFO) 1 A= 2.430 1.050 2.55TRAMO 2 (FONDO) 1 A= 3.160 1.050 3.32ESCALERAS 1 ( C)CONTRAPASOS 14 0.175 1.025 2.51TRAMO 1 ( COSTADO) 1 A= 0.479 0.48TRAMO 2 ( COSTADO) 1 A= 0.574 0.57TRAMO 1 (FONFO) 1 A= 2.430 1.025 2.49TRAMO 2 (FONDO) 1 A= 3.160 1.025 3.24
SEGUNDO NIVEL
ESCALERAS 1 ( A- B)CONTRAPASOS 16 0.175 1.050 2.94TRAMO 3 ( COSTADO) 1 A= 0.596 0.60

H O J A D E M E T R A D O S OBRA VIVIENDA UNIFAMILIARPROPIETARIO : Familia Balabarca Muñoz
DISTRITO :Mz H Lote 08 Urb, La Catedral - Dist. de Sachaca
FECHA : ABRIL 2011 HECHO POR : ESL
NRO TITULO DE PARTIDA NRO MEDIDAS SUB
PARTIDA VECES LARGO ANCHO ALTO PARCIAL PARCIAL
TRAMO 4 ( COSTADO) 1 A= 0.596 0.60TRAMO 3 (FONFO) 1 A= 3.270 1.050 3.43TRAMO 4 (FONDO) 1 A= 3.270 1.050 3.43ESCALERAS 1 ( C)CONTRAPASOS 16 0.175 1.025 2.87TRAMO 3 ( COSTADO) 1 A= 0.596 0.60TRAMO 4 ( COSTADO) 1 A= 0.596 0.60TRAMO 3 (FONFO) 1 A= 3.270 1.025 3.35TRAMO 4 (FONDO) 1 A= 3.270 1.025 3.35
6.00 MUROS Y TABIQUES DE ALBAÑILERIA
6.01 MURO DE LADRILLO KK DE ARCILLA SOGAPRIMER NIVEL
EJE A ( 1 - 2 ) 1 1.250 2.225 2.78EJE B (1 - 2 ) 1 0.810 2.225 1.80EJE B' ( 3 - 5) 1 3.850 2.225 8.57EJE C ( 4- 5 ) 1 1.300 2.225 2.89EJE C' ( 4- 5 ) 1 1.300 2.225 2.89EJE D ( 4- 5 ) 1 1.300 2.225 2.89EJE F (1- 5 ) 1 6.950 2.800 19.46EJE 1 ( A- F ) 1 11.620 2.025 23.53EJE 2 (A - B) 1 2.200 2.225 4.90EJE 3 ( B- C) 1 0.750 2.225 1.67EJE 4 (B-E) 1 3.400 2.225 7.57EJE 5 (A-E) 1 11.530 2.025 23.35
102.29
DESCONTANDO VENTANAS0.8*1.60*0.8 ALF -2 0.800 1.600 -2.561.60*1.40*1.00 ALF -1 1.600 1.400 -2.24
-4.80
SEGUNDO NIVEL
EJE A ( 1 - 2 ) 1 1.250 2.425 3.03EJE B (1 - 2 ) 1 3.610 2.425 8.75EJE C ( 4- 5 ) 1 1.300 2.425 3.15EJE C' ( 4- 5 ) 1 1.300 2.425 3.15EJE D ( 1- 5 ) 1 5.300 2.425 12.85EJE 1 ( A- F ) 1 11.620 2.425 28.18EJE 2 (A - B) 1 3.120 2.425 7.57EJE 3 ( B- C) 1 3.950 2.425 9.58

H O J A D E M E T R A D O S OBRA VIVIENDA UNIFAMILIARPROPIETARIO : Familia Balabarca Muñoz
DISTRITO :Mz H Lote 08 Urb, La Catedral - Dist. de Sachaca
FECHA : ABRIL 2011 HECHO POR : ESL
NRO TITULO DE PARTIDA NRO MEDIDAS SUB
PARTIDA VECES LARGO ANCHO ALTO PARCIAL PARCIAL
EJE 4 (B-E) 1 4.470 2.425 10.84EJE 5 (A-E) 1 11.530 2.425 27.96VOLADO 2 2.700 2.425 13.10VAÑOS 1 1.850 2.425 4.49
132.65
DESCONTANDO VENTANAS0.8*1.60*0.8 ALF -2 0.800 1.600 -2.561.80*1.60*0.80 ALF -1 1.600 1.800 -2.880.6*0.60* 1.80 ALF -2 0.600 0.600 -0.72
-6.16

TOTAL UND
PARCIAL
1.00 GLB
50.24 ML
119.87 M2 1011.5
119.87 M2

TOTAL UND
PARCIAL
86.23
12.61 M3

TOTAL UND
PARCIAL
9.55 M3
20% Expon
107.16 M3

TOTAL UND
PARCIAL
80.17 M3
2.79 M3

TOTAL UND
PARCIAL
37.49 M2
4.42 M3
4.06 M2
1.34 M3
17.87 M3
2.653.125

TOTAL UND
PARCIAL
M3
M317.39
M2
M2225.98 M2

TOTAL UND
PARCIAL
M3
M311.5342 M3

TOTAL UND
PARCIAL
M2
M275.125

TOTAL UND
PARCIAL
M3
M310.9809 M3

TOTAL UND
PARCIAL
M2
M2127.98 M2
UND

TOTAL UND
PARCIAL
UND1087.83
5.66 M3

TOTAL UND
PARCIAL
40.55 M2
M2
M2

TOTAL UND
PARCIAL
223.98 M2

H O J A D E M E T R A D O S OBRA VIVIENDA UNIFAMILIARPROPIETARIO : SR. MIGUEL ANGEL HUAMAN Y SRA
DISTRITO : HUNTER, PROVINCIA : AREQUIPA, DEPARTAMENTO : AREQUIPA
FECHA : ABRIL 2011 HECHO POR : ESL
NRO TITULO DE PARTIDA NRO CADA ELEMENTO LONGITUD TOTAL POR DIAMETRO
PARTIDA VECES CANT, DIAM, LONGIT 3/8'' 1/2'' 5/8'' 3/4'' 1/4''
5.03 ACERO ZAPATAS
Z-1
As VERTICAL 3 7 5/8'' 1.38 28.98
As HORIZONTAL 3 7 5/8'' 1.38 28.98
TOTAL ZAPATAS 0.00 0.00 57.96 0.00 0.00
TOTAL VARILLAS 0.00 0.00 6.44 0.00 0.00
0.00 0.00 91.58 0.00 0.00
TOTAL 91.58
5.06 ACERO VIGAS DE CIMENTACION
CC-3 EJE A' (4 - 5 ) 1 6 1/2'' 4.75 28.50
CC-3 EJE B ( 2 - 5) 1 6 1/2'' 5.90 35.40
CC-3 EJE C ( 1- 2) 1 6 1/2'' 4.50 27.00
CC-3 EJE D ( 1- 2 ) 1 6 1/2'' 4.50 27.00
CC-3 EJE E (1- 5 ) 1 6 1/2'' 5.60 33.60
ESTRIBOS
CC-3 EJE A' (4 - 5 ) 1 28 1/4'' 1.20 33.60
CC-3 EJE B ( 2 - 5) 1 39 1/4'' 1.20 46.80
CC-3 EJE C ( 1- 2) 1 23 1/4'' 1.20 27.60
CC-3 EJE D ( 1- 2 ) 1 23 1/4'' 1.20 27.60
CC-3 EJE E (1- 5 ) 1 38 1/4'' 1.20 45.60
TOTAL ZAPATAS 0.00 151.50 0.00 0.00 181.20
TOTAL VARILLAS 0.00 16.83 0.00 0.00 45.30
0.00 154.53 0.00 0.00 45.30
TOTAL 199.83
5.06 COLUMNAS ACERO
PRIMER NIVEL
C1 Zapata 1 10 5/8'' 4.63 46.25
C1 Columna 1 10 5/8'' 4.43 44.25
C2 13 6 1/2'' 4.33 337.74
C3 2 4 5/8'' 4.33 34.64
2 4 1/2'' 4.33 34.64
C4 2 8 3/8'' 4.33 69.20
C5 2 4 1/2'' 4.33 34.64
2 4 3/8'' 4.33 34.64
P1 2 4 5/8'' 4.33 34.64
2 4 1/2'' 4.33 34.64
P2 1 4 5/8'' 4.33 17.32

NRO TITULO DE PARTIDA NRO CADA ELEMENTO LONGITUD TOTAL POR DIAMETRO
PARTIDA VECES CANT, DIAM, LONGIT 3/8'' 1/2'' 5/8'' 3/4'' 1/4''
1 4 1/2'' 4.33 17.32
P3-P3-A 3 8 1/2'' 4.33 103.92
3 3 3/8'' 4.33 38.97
P4-P5 2 8 1/2'' 4.33 69.28
P6 2 8 5/8'' 4.33 69.28
2 2 1/2'' 4.33 17.32
C-A MURO PERIMETRICO 5 4 3/8'' 3.30 66.00
C-A INTERIOR EJE 4 2 4 3/8'' 3.40 27.20
ESTRIBOS
C1 Zapata 1 34 3/8'' 2.30 78.20
C1 Columna 1 32 3/8'' 2.30 73.60
C2 13 33 1/4'' 1.45 622.05
C3 2 35 1/4'' 1.10 77.00
C4 2 33 1/4'' 1.06 69.96
C5 1 33 1/4'' 1.00 33.00
P1 2 23 3/8'' 1.05 48.30
2 33 1/4'' 0.76 50.16
P2 1 23 3/8'' 1.05 24.15
1 33 1/4'' 1.44 47.52
P3-P3-A 3 23 3/8'' 0.90 62.10
3 33 1/4'' 1.20 118.80
P4-P5 2 23 3/8'' 1.05 48.30
2 33 1/4'' 0.76 50.16
P6 2 23 3/8'' 0.65 29.90
2 33 1/4'' 1.72 113.52
C-A MURO PERIMETRICO 5 28 1/4'' 0.90 126.00
C-A INTERIOR EJE 4 1 28 1/4'' 0.90 25.20
TOTAL COLUMNAS 600.56 649.50 246.38 0.00 1333.37
TOTAL VARILLAS 66.73 72.17 27.38 0.00 148.15
336.31 662.49 389.28 0.00 333.34
TOTAL 1721.43
SEGUNDO NIVEL
C1 2 10 5/8'' 3.13 62.50
C2 13 6 1/2'' 3.13 243.75
C4 4 8 3/8'' 3.13 100.00
C5 2 4 1/2'' 3.13 25.00
2 4 3/8'' 3.13 25.00
P1 2 4 5/8'' 3.13 25.00
2 4 1/2'' 3.13 25.00
P2 1 4 5/8'' 3.13 12.50
1 4 1/2'' 3.13 12.50
P3-P3-A 3 8 1/2'' 3.13 75.00
3 3 3/8'' 3.13 28.13
P4-P5 2 8 1/2'' 3.13 50.00
P6 2 8 5/8'' 3.13 50.00
2 2 1/2'' 3.13 12.50
C-A 3 4 3/8'' 10.30 123.60

NRO TITULO DE PARTIDA NRO CADA ELEMENTO LONGITUD TOTAL POR DIAMETRO
PARTIDA VECES CANT, DIAM, LONGIT 3/8'' 1/2'' 5/8'' 3/4'' 1/4''
ESTRIBOS
C1 2 21 3/8'' 2.30 96.60
C2 13 22 1/4'' 1.45 414.70
C4 4 22 1/4'' 1.06 93.28
C5 1 22 1/4'' 1.00 22.00
P1 2 13 3/8'' 1.05 27.30
2 22 1/4'' 0.76 33.44
P2 1 13 3/8'' 1.05 13.65
1 22 1/4'' 1.44 31.68
P3-P3-A 3 13 3/8'' 0.90 35.10
3 22 1/4'' 1.20 79.20
P4-P5 2 13 3/8'' 1.05 27.30
2 22 1/4'' 0.76 33.44
P6 2 13 3/8'' 0.65 16.90
2 22 1/4'' 1.72 75.68
C-A 3 22 1/4'' 0.90 59.40
TOTAL COLUMNAS 493.58 443.75 150.00 0.00 842.82
TOTAL VARILLAS 54.84 49.31 16.67 0.00 93.65
276.40 452.63 237.00 0.00 210.70
TOTAL 1176.73
5.09 VIGAS
PRIMER NIVEL
VA-1 EJE A ( 1 - 5) 1 6 1/2'' 7.9 47.40
VA-1 EJE B ( 1 - 5) 1 6 1/2'' 7.9 47.40
VA-2 EJE C ( 1 - 5) 1 4 1/2'' 7.9 31.60
1 2 3/8'' 7.9 15.80
VA-2 EJE C´ ( 1 - 5) 1 4 1/2'' 7.9 31.60
1 2 3/8'' 7.9 15.80
VA-1 EJE D ( 1 - 5) 1 6 1/2'' 7.9 47.40
VA-1 EJE E ( 1 - 5) 1 6 1/2'' 7.9 47.40
VS-1 EJE 1 ( A - E) 1 6 3/8'' 14.42 86.52
VS-1 EJE 2 ( A - B) 1 6 3/8'' 4.20 25.20
VA-1 EJE 3 (A - E) 1 6 3/8'' 12.00 72.00
VA-2 EJE 4 (B - E) 1 4 1/2'' 8.65 34.60
1 2 3/8'' 8.65 17.30
VA-2 EJE 4' (C - D) 1 4 1/2'' 1.75 7.00
1 2 3/8'' 1.75 3.50
VS-1 EJE 5 ( A - E) 1 6 1/2'' 14.42 86.52
VB EJE A (2-5) 1 2 1/2'' 6.85 13.70
VB EJE E (1-5) 1 2 3/8'' 5.30 10.60
VB EJE C (2-5) 1 2 1/2'' 1.60 3.20
ESTRIBOS
VA-1 EJE A ( 1 - 5) 1 47 1/4'' 0.90 42.30
VA-1 EJE B ( 1 - 5) 1 48 1/4'' 0.90 43.20
VA-2 EJE C ( 1 - 5) 1 47 1/4'' 0.90 42.30

NRO TITULO DE PARTIDA NRO CADA ELEMENTO LONGITUD TOTAL POR DIAMETRO
PARTIDA VECES CANT, DIAM, LONGIT 3/8'' 1/2'' 5/8'' 3/4'' 1/4''
VA-2 EJE C´ ( 1 - 5) 1 48 1/4'' 0.90 43.20
VA-1 EJE D ( 1 - 5) 1 47 1/4'' 0.90 42.30
VA-1 EJE E ( 1 - 5) 1 45 1/4'' 0.90 40.50
VS-1 EJE 1 ( A - E) 1 90 1/4'' 1.10 99.00
VS-1 EJE 2 ( A - B) 1 30 1/4'' 1.10 33.00
VA-1 EJE 3 (A - E) 1 82 1/4'' 0.90 73.80
VA-2 EJE 4 (B - E) 1 63 1/4'' 0.90 56.70
VA-2 EJE 4' (C - D) 1 11 1/4'' 0.90 9.90
VS-1 EJE 5 ( A - E) 1 90 1/4'' 1.10 99.00
VB EJE A (2-5) 1 33 1/4'' 0.30 9.90
VB EJE E (1-5) 1 30 1/4'' 0.30 9.00
VB EJE C (2-5) 1 10 1/4'' 0.30 3.00
TOTAL VIGAS 246.72 397.82 0.00 0.00 647.10
TOTAL VARILLAS 27.41 44.20 0.00 0.00 71.90
138.16 405.78 0.00 0.00 161.78
TOTAL 705.71
SEGUNDO NIVEL
VA-1 EJE A ( 1 - 5) 1 6 1/2'' 7.9 47.40
VA-1 EJE B ( 1 - 5) 1 6 1/2'' 7.9 47.40
VA-2 EJE C ( 1 - 5) 1 4 1/2'' 7.9 31.60
1 2 3/8'' 7.9 15.80
VA-2 EJE C´ ( 1 - 5) 1 4 1/2'' 7.9 31.60
1 2 3/8'' 7.9 15.80
VA-2 EJE D ( 1 - 5) 1 4 1/2'' 7.9 31.60
1 2 3/8'' 7.9 15.80
VA-1 EJE E ( 1 - 5) 1 6 1/2'' 7.9 47.40
VS-1 EJE 1 ( A - E) 1 6 3/8'' 14.42 86.52
VS-1 EJE 2 ( A - B) 1 6 3/8'' 4.20 25.20
VA-1 EJE 3 (A - E) 1 6 3/8'' 12.00 72.00
VA-2 EJE 4 (B - E) 1 4 1/2'' 8.65 34.60
1 2 3/8'' 8.65 17.30
VA-2 EJE 4' (C - D) 1 4 1/2'' 1.75 7.00
1 2 3/8'' 1.75 3.50
VS-1 EJE 5 ( A - E) 1 6 1/2'' 14.42 86.52
VB EJE A (2-5) 1 2 1/2'' 6.85 13.70
VB EJE E (1-5) 1 2 3/8'' 5.30 10.60
VB EJE C (2-5) 1 2 1/2'' 1.60 3.20
ESTRIBOS
VA-1 EJE A ( 1 - 5) 1 47 1/4'' 0.90 42.30
VA-1 EJE B ( 1 - 5) 1 48 1/4'' 0.90 43.20
VA-2 EJE C ( 1 - 5) 1 47 1/4'' 0.90 42.30
VA-2 EJE C´ ( 1 - 5) 1 48 1/4'' 0.90 43.20
VA-1 EJE D ( 1 - 5) 1 47 1/4'' 0.90 42.30
VA-1 EJE E ( 1 - 5) 1 45 1/4'' 0.90 40.50
VS-1 EJE 1 ( A - E) 1 90 1/4'' 1.10 99.00

NRO TITULO DE PARTIDA NRO CADA ELEMENTO LONGITUD TOTAL POR DIAMETRO
PARTIDA VECES CANT, DIAM, LONGIT 3/8'' 1/2'' 5/8'' 3/4'' 1/4''
VS-1 EJE 2 ( A - B) 1 30 1/4'' 1.10 33.00
VA-1 EJE 3 (A - E) 1 82 1/4'' 0.90 73.80
VA-2 EJE 4 (B - E) 1 63 1/4'' 0.90 56.70
VA-2 EJE 4' (C - D) 1 11 1/4'' 0.90 9.90
VS-1 EJE 5 ( A - E) 1 90 1/4'' 1.10 99.00
VB EJE A (2-5) 1 33 1/4'' 0.30 9.90
VB EJE E (1-5) 1 30 1/4'' 0.30 9.00
VB EJE C (2-5) 1 10 1/4'' 0.30 3.00
TOTAL VIGAS 262.52 382.02 0.00 0.00 647.10
TOTAL VARILLAS 29.17 42.45 0.00 0.00 71.90
147.01 389.66 0.00 0.00 161.78
TOTAL 698.45
5.13 LOSAS ALIGERADASPRIMER NIVELViguetas 1 15 1/2'' 10.8 162.00
1 15 3/8'' 1.15 17.25Viguetas 1 4 1/2'' 6.8 27.20
1 4 3/8'' 1.15 4.60Viguetas 1 9 1/2'' 8 72.00
1 9 3/8'' 5 45.00
FIERRO TEMPERATURAPRIMER NIVELPAÑO 1 1 31 1/4'' 7.45 230.95
1 30 1/4'' 7.30 219.00PAÑO 2 1 18 1/4'' 4.50 81.00
1 8 1/4'' 1.85 14.80PAÑO 3 1 23 1/4'' 5.50 126.50
1 17 1/4'' 4.00 68.00TOTAL LOSA ALIGERADA 66.85 261.20 0.00 0.00 672.25TOTAL VARILLAS 7.43 29.02 0.00 0.00 74.69
37.44 266.42 0.00 0.00 168.06
TOTAL 471.92
SEGUNDO NIVELPRIMER NIVELViguetas 1 15 1/2'' 10.8 162.00
1 15 3/8'' 1.15 17.25Viguetas 1 4 1/2'' 6.8 27.20
1 4 3/8'' 1.15 4.60Viguetas 1 9 1/2'' 8 72.00
1 9 3/8'' 5 45.00
FIERRO TEMPERATURAPRIMER NIVELPAÑO 1 1 31 1/4'' 7.45 230.95
1 30 1/4'' 7.30 219.00PAÑO 2 1 18 1/4'' 4.50 81.00

NRO TITULO DE PARTIDA NRO CADA ELEMENTO LONGITUD TOTAL POR DIAMETRO
PARTIDA VECES CANT, DIAM, LONGIT 3/8'' 1/2'' 5/8'' 3/4'' 1/4''1 8 1/4'' 1.85 14.80
PAÑO 3 1 23 1/4'' 5.50 126.501 17 1/4'' 4.00 68.00
TOTAL LOSA ALIGERADA 66.85 261.20 0.00 0.00 672.25TOTAL VARILLAS 7.43 29.02 0.00 0.00 74.69
37.44 266.42 0.00 0.00 168.06
TOTAL 471.92
5.16 ESCALERASPRIMER NIVEL
ESCALERAS 1 ( A- B)TRAMO 1As ARRIBA LARGO 1 4 3/8'' 2.10 8.40
1 7 3/8'' 3.80 26.601 4 3/8'' 1.50 6.00
As ABAJO LARGO 1 4 3/8'' 1.65 6.601 4 3/8'' 1.41 5.64
As TRANSVERSALES 1 29 3/8'' 1.05 30.45
TRAMO 2As ARRIBA LARGO 1 4 3/8'' 1.76 7.04
1 4 3/8'' 1.00 4.001 4 3/8'' 1.30 5.20
As ABAJO LARGO 1 7 3/8'' 3.52 24.64As TRANSVERSALES 1 31 3/8'' 1.05 32.55
ESCALERAS 1 ( C)TRAMO 1As ARRIBA LARGO 1 4 3/8'' 2.10 8.40
1 7 3/8'' 3.80 26.601 4 3/8'' 1.50 6.00
As ABAJO LARGO 1 4 3/8'' 1.65 6.601 4 3/8'' 1.41 5.64
As TRANSVERSALES 1 29 3/8'' 1.03 29.72
TRAMO 2As ARRIBA LARGO 1 4 3/8'' 1.76 7.04
1 4 3/8'' 1.00 4.001 4 3/8'' 1.30 5.20
As ABAJO LARGO 1 7 3/8'' 3.52 24.64As TRANSVERSALES 1 31 3/8'' 1.03 31.78
SEGUNDO NIVEL
TRAMO 3As ARRIBA LARGO 1 4 3/8'' 1.06 4.24
1 7 3/8'' 3.65 25.551 4 3/8'' 1.52 6.08
As ABAJO LARGO 1 4 3/8'' 1.41 5.64As TRANSVERSALES 1 29 3/8'' 1.05 30.45
TRAMO 4As ARRIBA LARGO 1 4 3/8'' 1.06 4.24
1 7 3/8'' 3.65 25.551 4 3/8'' 1.52 6.08

NRO TITULO DE PARTIDA NRO CADA ELEMENTO LONGITUD TOTAL POR DIAMETRO
PARTIDA VECES CANT, DIAM, LONGIT 3/8'' 1/2'' 5/8'' 3/4'' 1/4''As ABAJO LARGO 1 4 3/8'' 1.41 5.64As TRANSVERSALES 1 29 3/8'' 1.05 30.45
ESCALERAS 1 ( C)TRAMO 3As ARRIBA LARGO 1 4 3/8'' 1.06 4.24
1 7 3/8'' 3.65 25.551 4 3/8'' 1.52 6.08
As ABAJO LARGO 1 4 3/8'' 1.41 5.64As TRANSVERSALES 1 29 3/8'' 1.03 29.72
TRAMO 4As ARRIBA LARGO 1 4 3/8'' 1.06 4.24
1 7 3/8'' 3.65 25.551 4 3/8'' 1.52 6.08
As ABAJO LARGO 1 4 3/8'' 1.41 5.64As TRANSVERSALES 1 31 3/8'' 1.03 31.93TOTAL ESCALERAS 601.34 0.00 0.00 0.00 0.00TOTAL VARILLAS 66.82 0.00 0.00 0.00 0.00
336.75 0.00 0.00 0.00 0.00
TOTAL 336.75

UND.
ml.
Var CC-3 EJE A' 1 4.150
Kg. CC-3 EJE 1 5.290
Kg. CC-3 EJE 1 3.950
CC-3 EJE 1 3.950
CC-3 EJE E 1 5.000
28 11
ml.
Var
Kg.
Kg.
1

UND.
ml.
Var
Kg.
Kg.
con arranques para el tercer psiso
con anclaje del CA en losa

UND.
ml.
Var
Kg.
Kg.
13 34
9 10 29
24 10 13

UND.
35 13
24 10 13
18 9 18
6 21 15 14 11
9 21
9 21 13 26 13
15 14 11 23
11
6 21 15 14 11
33
30
10
ml.
Var
Kg.
Kg.
13 34
9 10 29
24 10 13
35 13
24 10 13
18 9 18
6 21 15 14 11

UND.
9 21
9 21 13 26 13
15 14 11 23
11
6 21 15 14 11
33
30
10
ml.
Var
Kg.
Kg.
ml.VarKg.Kg.

UND.
ml.VarKg.Kg.
29
29
29

UND.
29
ml.VarKg.Kg.

H O J A D E M E T R A D O S OBRA "VIVIENDA MULTIFAMILIAR"
PROPIETARIO : SR. JOSE ANTONIO MANRIQUE CORAZAO
y SRA YVONI CARRASCO CHACON
DISTRITO : CAYMA, PROVINCIA : AREQUIPA, DEPARTAMENTO : AREQUIPA
FECHA : FEBRERO 2013 HECHO POR : ESL
NRO TITULO DE PARTIDA TOTAL UND
PARTIDA
1.00 OBRAS PROVICIONALES
1.01 CASETA DE GUARDIANIA Y ALMACEN 1.00 GLB
1.02 CERCO PERIMETRICO CON ARPILLERA 50.24 ML
2.00 TRABAJOS PRELIMINARES
2.01 LIMPIEZA DEL TERRENO 119.87 M2
2.02 TRAZO NIVEL Y REPLANTEO 119.87 M2
3.00 MOVIMIENTO DE TIERRAS
3.01 EXCAVACION DE CIMIENTOS CORRIDOS Fc= 100 Kg/cm2 86.23 M3
3.02 EXCAV MANUAL ZAPATAS 12.61 M3
3.03 RELLENO COMPACTADO M/PROPIO (zanjas y zapatas) 9.55 M3
3.04 ELIMINACION MATERIAL EXCEDENTE 107.16 M3
4.00 OBRAS CONCRETO SIMPLE
4.01 CIMIENTOS CORRIDOS Y SUB ZAPATAS F'c = 100 Kg / cm2 80.17 M3
4.02 SOBRECIMIENTOS F'c = 175 Kg / cm2 2.79 M3
4.03 ENCOFRADO Y DESENCOFRADO DE SOBRECIMIENTO 37.49 M2
5.00 OBRAS DE CONCRETO ARMADO
5.01 ZAPATAS F'c = 210 Kg / cm2 4.42 M3
5.02 ENCOFRADO ZAPATAS 4.06 M2
5.03 ACERO ZAPATAS F'y 4200 Kg/cm2 91.58 Kg
5.04 VIGAS DE CIMENTACION f'c=210kg/cm" 1.34 M3
5.05 ENCOFRADO DE VIGAS DE AMARRE 17.87 M2
5.06 ACERO VIGAS DE CIMENTACION F'y =4200 Kg/cm2 199.83 Kg
5.07 COLUMNAS CONCRETO F'c =210kg/cm" 17.39 M3
5.08 ENCOFRADO Y DESENCOF. EN COLUMNAS 225.98 M2
5.09 ACERO EN COLUMNAS F'y 4200 Kg/cm2 2898.16 Kg
5.10 VIGAS CONCRETO F'c =210kg/cm" 11.53 M3
5.11 ENCOFRADO Y DESENCOF. EN VIGAS 75.13 M2
5.12 ACERO EN VIGAS F'y 4200 Kg/cm2 1404.16 Kg
5.13 LOSAS ALIGERADAS CONCRETO f'C=210kg/cm" 10.98 M3
5.14 ENCOFRADO - DESENCOF. EN LOSAS ALIGERADAS 127.98 M2
5.15 LADRILLO HUECO 15X30X30 CM P/TECHO ALIGERADO 1087.83 M2
5.16 ACERO EN LOSAS ALIGERADAS F'y 4200 Kg/cm2 943.84 Kg
5.17 ESCALERAS f'C=175kg/cm" 5.66 M3
5.17 ESCALERAS ENCOFRADO Y DESENCOFRADO 40.55 M2
5.18 ACERO EN ESCALERAS F'y 4200 Kg/cm2 336.75 Kg
6.00 MUROS Y TABIQUES DE ALBAÑILERIA
6.01 MURO DE LADRILLO KK DE ARCILLA SOGA 223.98 M2

H O J A D E M E T R A D O S OBRA "VIVIENDA MULTIFAMILIAR"
PROPIETARIO : SR. JOSE ANTONIO MANRIQUE CORAZAO
y SRA YVONI CARRASCO CHACON
DISTRITO : CAYMA, PROVINCIA : AREQUIPA, DEPARTAMENTO : AREQUIPA
FECHA : FEBRERO 2013 HECHO POR : ESL
NRO TITULO DE PARTIDA TOTAL UND
PARTIDA

H O J A D E M E T R A D O S OBRA "VIVIENDA MULTIFAMILIAR"
PROPIETARIO : SR. JOSE ANTONIO MANRIQUE CORAZAO
y SRA YVONI CARRASCO CHACON
DISTRITO : CAYMA, PROVINCIA : AREQUIPA, DEPARTAMENTO : AREQUIPA
FECHA : FEBRERO 2013 HECHO POR : ESL
NRO TITULO DE PARTIDA TOTAL UND
PARTIDA

H O J A D E M E T R A D O S OBRA "VIVIENDA MULTIFAMILIAR"
PROPIETARIO : SR. JOSE ANTONIO MANRIQUE CORAZAO
y SRA YVONI CARRASCO CHACON
DISTRITO : CAYMA, PROVINCIA : AREQUIPA, DEPARTAMENTO : AREQUIPA
FECHA : FEBRERO 2013 HECHO POR : ESL
NRO TITULO DE PARTIDA TOTAL UND
PARTIDA

Item Descripción Und. Metrado
01 OBRAS PROVISIONALES
1.01 CASETA DE GUARDIANIA Y DEPOSITO GLB 1.00
1.03 CORTE DE TERRENO CON EQUIPO m3 74.10
1.04 RELLENO DE TERRENO CON EQUIPO m3 63.48
1.05 ELIMINACION DE MATERIAL CON EQUIPO m3 10.62
02 TRABAJOS PRELIMINARES
02.01 LIMPIEZA DE TERRENO MANUAL m2 200.87
02.02 TRAZO NIVEL Y REPLANTEO m2 200.87
03 MOVIMIENTO DE TIERRAS
03.01 EXCAVACION CIMIENTOS EN TERRENO NORMAL m3 78.74
03.02 RELLENO COMPACTADO CON MAT. PROPIO m3 14.08
03.03 NIVELACION INTERIOR Y APISONADO MANUAL m2 200.87
03.04 ELIMINACION MATERIAL EXCEDENTE CARGIO A MANO C/VOLQUETE DE 10m3, m3 77.59
04 OBRAS DE CONCRETO SIMPLE
04.01 SOLADO PARA ZAPATA e=10cm,f'c=100kg/cm2 m2 3.00
04.03 CIMIENTOS CORRIDOS MEZCLA 1:10 CEMENTO-HORMIGON 30% PIEDRA m3 47.02
04.04 SOBRECIMIENTOS
04.04.01 CONCRETO 1:8+25% P.M. PARA SOBRECIMIENTOS m3 2.68
04.04.02 ENCOFRADO Y DESENCOFRADO PARA SOBRECIMIENTOS m2 35.71
04.05 SARDINELES
04.05.01 CONCRETO F'C=140 kg/cm2 PARA SARDINELES m3 1.87
04.05.02 ENCOFRADO Y DESENCOFRADO DE SARDINELES m2 7.05
05 OBRAS DE CONCRETO ARMADO
05.01 ZAPATAS
05.01.01 CONCRETO EN ZAPATAS F'C=210 KG/CM2 m3 0.58
05.01.02 ACERO CORRUGADO EN ZAPATAS f'y=4200 kg/cm2 GRADO 60 kg 26.93
05.02 COLUMNAS
05.02.01 CONCRETO EN COLUMNAS F'C=210 KG/CM2 m3 8.67
05.02.02 ENCOFRADO Y DESENCOFRADO PARA COLUMNAS m2 148.71
05.02.03 ACERO CORRUGADO EN COLUMNASf'y=4200 kg/cm2 GRADO 60 kg 1,264.11
05.03 VIGAS
05.03.01 CONCRETO EN VIGAS F'C=210 KG/CM2 m3 4.53
05.03.02 ENCOFRADO Y DESENCOFRADO NORMAL EN VIGAS m2 43.83
05.03.03 ACERO CORRUGADO EN VIGAS f'y=4200 kg/cm2 GRADO 60 kg 677.12
05.04 LOSA ALIGERADA
05.04.01 CONCRETO EN LOSA ALIGERADA F'C=210 KG/CM2 m3 6.62
05.04.02 ENCOFRADO Y DESENCOFRADO EN LOSAS ALIGERADAS m2 74.92
05.04.03 ACERO CORRUGADO EN LOSA ALIGERADA f'y=4200 kg/cm2 GRADO 60 kg 363.67

05.04.04 LOSA ALIGERADA LADRILLO HUECO DE 15x30x30 und 636.84
05.05 ESCALERA
05.05.01 CONCRETO ESCALERAS F'C=210 KG/CM2 m3 2.14
05.05.02 ENCOFRADO Y DESENCOFRADO DE ESCALERAS m2 16.18
05.05.03 ACERO CORRUGADO EN ESCALERAS f'y=4200 kg/cm2 GRADO 60 kg 49.06
5.06 MUROS DE CONTENCION
05.06.01 CONCRETO MURO DE CONTENCION F'C=210 KG/CM2 m3 18.35
05.06.02 ENCOFRADO Y DESENCOFRADO DE MURO DE CONTENCION m2 184.63
05.06.03 ACERO CORRUGADO MURO DE CONTENCION f'y=4200 kg/cm2 GRADO 60 kg 474.99
06 MUROS Y TABIQUES
06.01 MURO LADRILLO KK SOGA 9x14x24 m2 207.11
06.02 REFUERZO HORIZONTAL CON ALAMBRE Nº 8 kg 276.45
07 REVOQUES ENLUCIDOS Y MOLDURAS
07.01 TARRAJEO PRIMARIO O RAYADO m2 8.31
07.02 TARRAJEO INTERIOR m2 114.21
07.03 TARRAJEO EXTERIOR m2 69.75
07.03 TARRAJEO EXTERIOR CERCO PERIMETRICO MY MUROS DE CONTENCION m2 144.49
07.04 TARRAJEO EN COLUMNAS m2 55.28
07.05 TARRAJEO EN VIGAS m2 25.09
07.06 TARRAJEO EN CIELO RASO m2 74.66
07.07 VESTIDURA DE DERRAMES m 80.02
08 PISOS Y PAVIMENTOS
08.01 FALSO PISO, e=10 cm. m2 131.19
08.02 CONTRAPISO DE 25mm. m2 131.19
15 TRATAMIENTO AREAS VERDES
15.01 TRATAMIENTO AREAS VERDES m2 49.00
17 INSTALACION SANITARIA
17.01 SISTEMA DE DESAGUE
17.01.01 SALIDA DE DESAGUE Ø 4" pto 1.00
17.01.02 SALIDA DE DESAGUE Ø 2" pto 9.00
17.01.03 SALIDA DE VENTILACION Ø 2" pto 2.00
17.01.04 TRAMPA EN "P" Ø 2" CON SUMIDERO pto 12.00
17.01.05 REGISTRO ROSCADO DE BRONCE 4" pza 1.00
17.01.06 CAJA DE REGISTRO DE DESAGUE 40x60 und 3.00
17.01.07 TUBERIA PVC-SAL 4" m 38.85
17.01.08 TUBERIA PVC-SAL 2" m 25.70
17.01.09 ACCESORIOS DE DESAGUE PVC (promedio) pza 26.00
17.02 SISTEMA DE DESAGUE PLUVIAL
17.02.01 BAJADA DE LLUVIA Ø 2" pto 5.00
17.02.02 TUBERIA PVC-SAL 2" m 15.00
17.02.03 ACCESORIOS DE DESAGUE PVC (promedio) pza 10.00
17.03 SISTEMA DE AGUA FRIA
17.03.01 SALIDA DE AGUA FRIA PVC-SAP 1/2" pto 6.00
17.03.02 LLAVE DE COMPUERTA DE BRONCE Ø 3/4" und 1.00
17.03.03 LLAVE DE COMPUERTA DE BRONCE Ø 1/2" und 3.00
17.03.04 TUBERIA PVC-SAP 3/4" m 30.50
17.03.05 TUBERIA PVC-SAP 1/2" m 15.50
17.03.06 ACCESORIOS DE AGUA PVC (promedio) pza 13.00

17.03 SISTEMA DE INSTALACIONES ELECTRICAS
19 VARIOS
19.01 LIMPIEZA FINAL DE OBRA m2 200.87
COSTO DIRECTO
GASTOS GENERALES Y UTILIDADES 8%
TOTAL PRESUPUESTO
PRESUPUESTO 01 PRIMER NIVEL HASTA CASCO GRIS INSUMOS
1.00 MANO DE OBRA 31,699.04 35%
2.00 MATERIALES 55,246.89 61%
3.00 HERRAMIENTAS Y EQUIPOS 3,622.75 4%
COSTO DIRECTO S/. 90,568.67 100%

Precio S/. Parcial S/.
5,572.07
600.00 600.00
34.75 2574.98
34.75 2205.93
18.00 191.16
548.38
1.05 210.91
1.68 337.46
4,218.88
28.00 2204.72
13.90 195.71
2.10 421.83
18.00 1396.62
8,091.80
240.00 720.00
156.78 7371.80
1,204.52
222.93 597.45
17.00 607.07
565.66
238.40 445.81
17.00 119.85
339.85
351.48 203.86
5.05 136.00
12,554.00
351.48 3047.33
21.00 3122.91
5.05 6383.76
5,932.09
351.48 1592.20
21.00 920.43
5.05 3419.46
8,032.26
351.48 2326.80
24.27 1818.31
5.05 1836.53

3.22 2050.62
1,339.70
351.48 752.17
21.00 339.78
5.05 247.75
12,725.59
351.48 6449.66
21.00 3877.23
5.05 2398.70
12,758.13
54.86 11362.05
5.05 1396.07
10,659.19
12.56 104.37
17.83 2036.36
21.18 1477.31
21.18 3060.30
21.88 1209.53
21.41 537.18
19.56 1460.35
9.67 773.79
6,058.35
27.52 3610.35
18.66 2448.01
661.50
13.50 661.50
2,036.48
67.50 67.50
59.20 532.80
47.80 95.60
37.12 445.44
29.85 29.85
105.07 315.21
7.24 281.27
4.44 114.11
5.95 154.70
385.50
47.35 236.75
5.95 89.25
5.95 59.50
645.89
32.74 196.44
55.35 55.35
41.43 124.29
5.17 157.69
3.04 47.12
5.00 65.00

1,600.00
210.91
1.05 210.91
90,568.67
8,151.18
S/. 98,719.85
PRESUPUESTO 01 PRIMER NIVEL HASTA CASCO GRIS INSUMOS