SITUACION ACTUAL DE LA ACTIVIDAD: MANTENIMIENTO DE CANAL SECTOR KILKA DISTRITO DE COPORAQUE-ESPINAR-CUSCO SUB GERENCIA DE INFRAESTRUCTURA PUBLICA DEPARTAMENTO DE OBRAS PUBLICAS AREA DE MANTENIMIENTO

Transcript of Exposicion mantenimiento 2

SITUACION ACTUAL DE LA ACTIVIDAD: MANTENIMIENTO DE CANAL SECTOR KILKA DISTRITO DE COPORAQUE-ESPINAR-CUSCO

SUB GERENCIA DE INFRAESTRUCTURA PUBLICA

DEPARTAMENTO DE OBRAS PUBLICAS

AREA DE MANTENIMIENTO

• Ingeniero Inspector: Ing. Elías Oliver Diaz Cahuana

• Ingeniero Residente: Ing. David R. Paredes Luque

• Asistente Técnico: • Asistente Administrativo: Sr. Agustín Thea Zamabrano

• Maestro de Obra: Sr. Serapio Qquehue Qquehue

PERSONAL TECNICO:

PRESUPUESTO DE OBRA

PROYECTO:

UBICACIÓN:Departamento : CUSCOProvincia : ESPINARDistrito : COPORAQUE

TIEMPO DE EJECUCION 90 Dias Calendario ( 3 Meses )

ITEM DESCRIPCION COSTO TOTAL S/.

CD COSTO DIRECTO DE OBRA 234,213.18

GG GASTOS GENERALES 20.77% 48,646.08

P_O PRESUPUESTO DE OBRA 282,859.26

GS GASTOS DE SUPERVISIÓN 3.90% 9,134.31

GL GASTOS DE LIQUIDACIÓN 1.28% 2,997.93

GE GASTOS DE ELABORACION DEL EXP. TECNICO 2.73% 6,394.02

GE GASTOS DE EVALUACION DE EXPEDIENTE 1.34% 3,138.46

CF COSTO TOTAL FINANCIAMIENTO MUNICIPAL 304,523.98

GG = CD x 20.77%CF = CD + GG + GS + GL + GE GS = P_O x 3.90%

GL = P_O x 1.28%GE = P_O x 2.73%GE = P_O x 1.34%

RESUMEN

PRESUPUESTO DE INVERSION

: "MANTENIMIENTO DE CANAL SECTOR KILKA COMUNIDAD URINSAYA DISTRITO COPORAQUE - ESPINAR - CUSCO"

METAS DEL PROYECTO

Descripción Und. Cantidad

Captación tipo Bocatoma und 1

Desarenador Und. 1

Canal trapezoidal Mtl. 1,420.00

Toma parcelario Und. 12

Pase vehicular Und. 1

Pase peatonal Und. 1

RESUMEN DE AVANCE

FISICO

S/. % S/. % S/. % S/. %

INICIO 1,667,480.97 0.00% 0.00%

MES 1 AGOSTO 61,647.80 3.70% 61,647.80 3.70% 26,299.43 1.58% 26,299.43 1.58% -2.12%

MES 2 SETIEMBRE 193,675.65 11.61% 255,323.45 15.31% 37,829.07 2.27% 64,128.50 3.85% -11.47%

MES 3 OCTUBRE 412,293.31 24.73% 667,616.76 40.04% 58,783.99 3.53% 122,912.49 7.37% -32.67%

MES 4 NOVIEMBRE 531,604.89 31.88% 1,199,221.66 71.92% 59,505.64 3.57% 182,418.13 10.94% -60.98%

MES 5 DICIEMBRE 303,018.39 18.17% 1,502,240.04 90.09% 0.00% 182,418.13 10.94% -79.15%

MES 6 ENERO 165,240.92 9.91% 1,667,480.97 100.00% 0.00% 182,418.13 10.94% -89.06%

TOTAL C.D.1,667,480.97 1,667,480.97 100.00% 182,418.13 10.94%

VALORIZACION FISICO PROGRAMADO VALORIZACION FISICO EJECUTADAPROG. DEL MES ACUMULADO VAL. DEL MES ACUMULADO VAR. %MES

PTO APROBAD.

RESUMEN DE AVANCE FINANCIERO

S/. % S/. % S/. % S/. %

INICIO 1,917,689.29 0.00% 0.00%

MES 1 AGOSTO 145,944.97 7.61% 145,944.97 7.61% 124,617.63 6.50% 124,617.63 6.50% -1.11%

MES 2 SETIEMBRE 223,882.83 11.67% 369,827.80 19.29% 98,784.42 5.15% 223,402.05 11.65% -7.64%

MES 3 OCTUBRE 442,500.49 23.07% 812,328.29 42.36% 149,543.75 7.80% 372,945.80 19.45% -22.91%

MES 4 NOVIEMBRE 561,812.07 29.30% 1,374,140.36 71.66% 489,315.69 25.52% 862,261.49 44.96% -26.69%

MES 5 DICIEMBRE 333,225.56 17.38% 1,707,365.92 89.03% 0.00% 862,261.49 44.96% -44.07%

MES 6 ENERO 210,323.37 10.97% 1,917,689.29 100.00% 0.00% 862,261.49 44.96% -55.04%

TOTAL C.D.1,917,689.29 1,917,689.29 100.00% 862,261.49 44.96%

PTO APROBAD.

VALORIZ. FINANCIERO PROGRAMADO VALORIZACION FINANCIERO EJECUTADAVAR. %PROG. DEL MES ACUMULADO VAL. DEL MES ACUMULADOMES

PANEL FOTOGRAFICO DEL PROCESO CONSTRUCTIVO

Se Observa la charla de InducciónAntes del Inicio de los trabajos

Se Observa los Trabajos de Excavación de zanja para canal de Rectangular.