VR1VALOR REFERENCIAL VR1PROYECTO: CONSTRUCCIN CANAL DE RIEGO SAN JOSE DE SUCREUBICACIN: AYACUCHO - FAJARDO- SAN JOSE DE SUCREFECHA: AGOSTO -2005PRESUPUESTO BASEMATERIALESS/.701,522.62MATERIALES701,522.62MANO DE OBRAS/.159,290.75MANO DE OBRA159,290.75EQUIPOS Y HERRAMIENTASS/.43,371.29EQUIPOS Y HERRAMIENTAS43,371.52904,184.89TOTAL COSTO DIRECTOS/.904,184.66GASTOS GENERALES (10%)S/.90,418.47UTILIDAD (10%)S/.90,418.47SUB TOTALS/.1,085,021.591085021.590.00I.G.V. (19%)206,154.10TOTALS/.1,291,175.69SON: UN MILLON DOSCIENTOS NOVENTIUN MIL CIENTO SETENTICINCO Y 69/100 NUEVOS SOLES