Maintenance Management And Rehabilitation
ofReinforced Concrete Structures
Technical Presentation
to ORC
By
Tony Carpenter, B.Eng, C.Eng, MIStructE.
Regional Manager
7/29/2019 ORC Gereal Presentation - Conc Main.ppt
2/39
All Elements and Materials Deteriorate
For structures it is important to define at the outset
the required useful life expectancy.
We term life expectancy
Service Life
Introduction
7/29/2019 ORC Gereal Presentation - Conc Main.ppt
3/39
7/29/2019 ORC Gereal Presentation - Conc Main.ppt
4/39
7/29/2019 ORC Gereal Presentation - Conc Main.ppt
5/39
Physical Deterioration
Fire Damage
Over Loading by tenants/occupier
Thermal Expansion and Contraction
Impact Damage and Abuse
7/29/2019 ORC Gereal Presentation - Conc Main.ppt
6/39
Chemical Deterioration
Sulphate Attack
Alkali-Aggregate Reactions
Chemical Spillage
7/29/2019 ORC Gereal Presentation - Conc Main.ppt
7/39
Electro-Chemical Deterioration
Corrosion or rusting of steel reinforcement,
having been depassivated either by
Carbonation or Chloride contamination ofsurrounding concrete, or a combination of
the two.
Chloride Induced Electro-chemical
deterioration is generally the most common
form of reinforced concrete deterioration
experienced in the Gulf.
7/29/2019 ORC Gereal Presentation - Conc Main.ppt
8/39
Electro-Chemical Deterioration
Internal Cracking and Spalling
7/29/2019 ORC Gereal Presentation - Conc Main.ppt
9/39
Electro-Chemical Deterioration
External Cracking and Spalling
7/29/2019 ORC Gereal Presentation - Conc Main.ppt
10/39
Electro-Chemical Deterioration
Deterioration of Bridge Structure
7/29/2019 ORC Gereal Presentation - Conc Main.ppt
11/39
Attack of gasses Attack of non-electrolytes
e.g. oils
Chemical corrosion
Atmospherically
exposed steel
structures
(air and water)
Anodic and Cathodic
areas wich cannot
be separated
Micro-electrolytic
corrosion
Submerged og
cast in items
in water, soil or
concrete
Separate
Anodic and Cathodic
areas
Macro-electrolytic
corrosion
Electrochemical corrosion
Corrosion
7/29/2019 ORC Gereal Presentation - Conc Main.ppt
12/39
Micro-electrolytic Corrosion
7/29/2019 ORC Gereal Presentation - Conc Main.ppt
13/39
Macro-electrolytic Corrosion
7/29/2019 ORC Gereal Presentation - Conc Main.ppt
14/39
7/29/2019 ORC Gereal Presentation - Conc Main.ppt
15/39
7/29/2019 ORC Gereal Presentation - Conc Main.ppt
16/39
CO2
Cl-
Cl-
Cl-
Cl-
Cl-
Cl-
Cl-CO2CO2
CO2CO2
CO2CO2
7/29/2019 ORC Gereal Presentation - Conc Main.ppt
17/39
CO2
Cl-
Cl-Cl-
Cl-
Cl-
Cl-
Cl-CO2CO2
CO2CO2
CO2CO2
7/29/2019 ORC Gereal Presentation - Conc Main.ppt
18/39
CO2
Cl-
Cl-
Cl-
Cl-
Cl-
Cl-
Cl-CO2CO2
CO2CO2
CO2CO2
7/29/2019 ORC Gereal Presentation - Conc Main.ppt
19/39
Fe++
2e-
7/29/2019 ORC Gereal Presentation - Conc Main.ppt
20/39
2Fe 2Fe++ + 4e-
Anode Cathode
4e- + O2 + 2H2O 4(OH)-
2Fe + O2 + 2H2O 2Fe++ + 4(OH)-
O2
O2
O2
H2O H2O
7/29/2019 ORC Gereal Presentation - Conc Main.ppt
21/39
0 1 2 3 4 5 6 7
Fe
FeO
Fe3O4
Fe2O3
Fe(OH)2
Fe(OH)3
Fe(OH)3, 3H2O
Volume
7/29/2019 ORC Gereal Presentation - Conc Main.ppt
22/39
Transport Mechanisms
Concrete contaminated during construction
Capillary Action
Permeation
Diffusion
Osmosis (coatings)
7/29/2019 ORC Gereal Presentation - Conc Main.ppt
23/39
Transport Mechanisms
MOISTURE ONLY
EVAPORATION OF
DIFFUSION
GF SLAB
CAPILLARYGW L
MOVEMENT
MOISTURE
DIFFUSION
COLUMN
DIFFUSION
EVAPORATION OF
MOISTURE ONLY
FOOTING
BLINDING
CONCRETE
7/29/2019 ORC Gereal Presentation - Conc Main.ppt
24/39
Transport Mechanisms
S E E P A G E
D I F F U S I O N
G W L
G L
B L I N D I N G
C O N C R E T E
E V A P O R A T I O N O F
M O I S T U R E O N L Y
M O I S T U R E O N L Y
E V A P O R A T IO N O F
C A P I L L A R Y /
M O V E M E N T
M O I S T U R E
B A S E M E N T W A L L
7/29/2019 ORC Gereal Presentation - Conc Main.ppt
25/39
Service Life
Technical Service life
Age of Structure
Acceptable Limit
Initiation Phase Propagation Phase
Damage
7/29/2019 ORC Gereal Presentation - Conc Main.ppt
26/39
Achieving Service Life
Design
Materials
Workmanship
Preventive Maintenance
Repairs/Rehabilitation
Substantial Reconstruction
7/29/2019 ORC Gereal Presentation - Conc Main.ppt
27/39
Technical Service life
Age of Structure
Acceptable Limit
Damage
The Law of Fives (de Sitter)
A B C D
Service Life Curve
7/29/2019 ORC Gereal Presentation - Conc Main.ppt
28/39
7/29/2019 ORC Gereal Presentation - Conc Main.ppt
29/39
Existing Structures
Existing structures are principally
within:
Phase B
Phase C
Phase D
7/29/2019 ORC Gereal Presentation - Conc Main.ppt
30/39
Existing Structures
Age of many concrete structure means
owners becoming faced with rapidly
increasing maintenance/rehabilitation
costs as deterioration move to phase D.
Why?
Lack of trained civil maintenance staff
Low priority given to civil works
No real appreciation of condition and
consequences of not taking action
No medium term planning
7/29/2019 ORC Gereal Presentation - Conc Main.ppt
31/39
Actions to be Taken
Adopt same attitude to civil works as
applied to plant!
Develop maintenance programme for
reinforced concrete structures
7/29/2019 ORC Gereal Presentation - Conc Main.ppt
32/39
Advantages/Benefits
Budgets planned well in advance
Human resources efficiently managed
Operations planned to minimise disruption of users
Extends service life of structure
Maintains capital investment
7/29/2019 ORC Gereal Presentation - Conc Main.ppt
33/39
Maintenance Management
Start with Investigation of Structures
Archive search
Site investigation
- Visual inspection
- Sampling and testing
Assessment and RecommendationsPrioritise rehabilitation activities
7/29/2019 ORC Gereal Presentation - Conc Main.ppt
34/39
7/29/2019 ORC Gereal Presentation - Conc Main.ppt
35/39
7/29/2019 ORC Gereal Presentation - Conc Main.ppt
36/39
Time For Intervention
CRITICALITY CODE DAMAGE CODE DETERMINING FACTOR
1 2 3 4
1 A B C* D* Life/Welfare, Capital loss
2 A/B B/C C* D* Interruption of operation
3 B/C C* D* D* Maintenance inconvenience
4 E* E* E* E* Cost effectiveness
A Immediate Action D < 6 years
B < 1 year E at failure
C < 3 years
* Based on regular inspection and monitoring
7/29/2019 ORC Gereal Presentation - Conc Main.ppt
37/39
Recommendations
Strategies and Concepts For
Remedial Works
Other Important Factors
Operational Constraints
- Special Temporary supports required
for structure
- Plant and equipment cannot be
relocated, diverted or decommissioned
7/29/2019 ORC Gereal Presentation - Conc Main.ppt
38/39
7/29/2019 ORC Gereal Presentation - Conc Main.ppt
39/39