LISTA DE PRECIO DE MATERIALES
DESCRIPCION UN PZAS P.U. PZAS P.U. TOTAL
1 ACEROS Y MALLAS
ALAMBRE RECOCIDO KG 1000 $ 15.00 $ 6.00 $ 15,000.00
ALAMBRON KG 1000 $ 14.20 $ 5.60 $ 14,000.00
ARCOS $ -
ARMEX 15-15-3 6 $ 88.00 $ 35.20
ARMEX 15-15-4 6 $ 91.00 $ 36.00
ARMEX 15-20-4 6 $ 99.00 $ 39.60
ARMEX 15-25-4 6 $ 104.00 $ 41.60
ARMEX 15-30-4 6 $ 107.80 $ 3.13
ARMEX 15-15-4 9MM 6 $ 127.50 $ 39.20
ARMEX 15-20-4 9MM 6 $ 133.63 $ 41.20
ARMEX 15-25-4 9MM 6 $ 140.40 $ 44.00
ARMEX 15-30-4 9MM 6 $ 141.50 $ 48.00
CLAVOS 2 1/2 A 4" KG $ 20.50 $ 8.20
CLAVOS 1 1/2 A 2" KG $ 22.00 $ 17.00
ESCALERILLA 12-2 $ -
ESCALERILLA 15-2 $ -
ESTRIBOS KG 1000 $ 14.90 $ 6.00 $ 15,000.00
MALLA 66-10-10 ROLLO 100 $ 1,225.00 $ 2.80 $ 1,180.00
MALLA 66-66 ROLLO 100 $ 2,450.00 $ 4.40 $ 2,430.00
MALLA 66-44 ROLLO 100 $ 3,100.00 $ 5.74 $ 3,230.00
MALLA 66-88 ROLLO 100 $ 2,213.00 $ 3.60
METAL DESPLEGADO 9.15 * 22 ML 100 $ 391.00 $ - $ 352.60
TELA CRIVA 5*5 ML 100 $ 67.00 $ 26.00
VARILLA ACERO SAN LUIS R-42 # 2 333 $ -
VARILLA ACERO SAN LUIS R-42 # 2.5 217 $ -
VARILLA ACERO SAN LUIS R-42 # 3 150 $ 92.33 $ 30.40 $ 13,850.00
VARILLA ACERO SAN LUIS R-42 # 4 84 $ 164.88 $ 66.40 $ 13,850.00
VARILLA ACERO SAN LUIS R-42 # 5 53 $ 261.32 $ - $ 13,850.00
VARILLA ACERO SAN LUIS R-42 # 6 37 $ 374.32 $ - $ 13,850.00
VARILLA ACERO SAN LUIS R-42 # 7 27 $ 512.96 $ - $ 13,850.00
VARILLA ACERO SAN LUIS R-42 # 8 21 $ 659.52 $ - $ 13,850.00
VARILLA ACERO SAN LUIS R-42 # 10 13 $ 1,065.38 $ - $ 13,850.00
VARILLA ACERO SAN LUIS R-42 # 12 9 $ 1,538.89 $ - $ 13,850.00
DESCRIPCION UN PZAS P.U. PZAS P.U. TOTAL
5 ADITIVOS E IMPERMEABILIZANTES
ADITECH 1 LTS $ 85.00
ADITECH 4 LTS $ 256.00
ADITECH 19 LTS $ 1,094.00
EMULTECH ASF 19 LTS $ 780.00
FRAGUARAPID 4 LTS $ 335.00
SOBRE VOLUMEN
40%
SOBRE VOLUMEN
40%
FRAGUARAPID 19 LTS
IMPERNIASA ACRILICO 4 LTS $ 325.00
IMPERNIASA ACRILICO 19 LTS $ 1,346.00
MEMBRACURE 19 LTS $ 536.00
NIASA BOND 1 LTS $ 136.00
NIASA BOND 4 LTS $ 336.00
NIASA BOND 19 LTS $ 1,674.00
NIASA LASTIC 19 LTS $ 2,015.00
RESINA B-18 1 LTS $ 35.00
RESINA B-18 20 LTS $ 648.00
DESCRIPCION UN PZAS P.U. PZAS P.U. TOTAL
6 PANEL ELECTRICOS Y SONOTUBO
CARTON ASFALTICO $ 358.00
COLADERA D/ ALUMINIO 15*15 $ 51.00
COLADERA D/ ALUMINIO 20*20 $ -
MANGUERA PARA JARDIN 1/2 *20 MTS $ 174.00
PANEL ESTRU. CONVITEC 2" $ 282.00
PANEL ESTRU. CONVITEC 3" $ 307.00 308
PECHOS DE PALOMA 1.22 $ 38.00
POLIDUCTO NARANJA 1/2 100 ML $ 209.50
POLIDUCTO NARANJA 1/2 CORRUGADO 100 $ 333.00 $ 350.00
POLIDUCTO NARANJA 3/4 100 ML 50 $ 398.00 $ 300.00
POLIDUCTO NEGRO CEDULA 40 100 M $ 297.00
LAVADERO DE GRANITO S/PILA $ 216.00
LAVADERO C/PILA MEDIANO $ 342.00
LAVADERO C/PILA GRANDE $ 445.00
SONOTUBO 3MTS 15 CMS $ 61.00
SONOTUBO 3MTS 20 CMS $ 81.50
SONOTUBO 3MTS 25 CMS $ 116.50
SONOTUBO 3MTS 30 CMS $ 164.50
SONOTUBO 3MTS 35 CMS $ 182.00
SONOTUBO 3MTS 40 CMS $ 207.00
SONOTUBO 3MTS 45 CMS $ 258.00
SONOTUBO 3MTS 50 CMS $ 336.50
SONOTUBO 3MTS 55 CMS $ 432.00
SONOTUBO CUADRADO 20 x 20 $ 93.00
SONOTUBO CUADRADO 25 x 25 $ 127.50
SONOTUBO CUADRADO 30 x 30 $ 187.00
DESCRIPCION UN PZAS P.U. PZAS P.U. TOTAL
9 CISTERNA Y TINACOS
CISTERNA EUREKA 2800 LTS
CISTERNA EUREKA 5000 LTS
CISTERNA ROTOPLAS 2800 LTS $ 5,108.00
SOBRE VOLUMEN
40%
SOBRE VOLUMEN
40%
CISTERNA ROTOPLAS 5000 LTS
CISTERNA ROTOPLAS 10000 LTS
TINACO EUREKA 450 LTS
TINACO EUREKA 750 LTS
TINACO EUREKA 1100 LTS
TINACO EUREKA 2500 LTS
TINACO ROTOPLAS 450 LTS $ 964.50
TINACO ROTOPLAS 750 LTS $ 1,223.50
TINACO ROTOPLAS 1100 LTS $ 1,537.00
TAMBO VACIO 200 LTS
BOTE VACIO 200 LTS
DESCRIPCION UN PZAS P.U. PZA.
10 CIMBRA
VIGA 3 1/2" -7" - 8" M $ 2.44
VIGA 3 1/2" -7" - 10" M $ 3.05
VIGA 3 1/2" -7" - 12" M $ 3.66
VIGA 3 1/2" -7" - 14" M $ 4.30
VIGA 3 1/2" -7" - 16" M $ 4.90
VIGA 3 1/2" -7" - 18" M $ 5.50
VIGA 3 1/2" -7" - 20" M $ 6.10
TABLA DE 2DA 30 CM
TABLA DE 3ERA DE 30 CM
POLIN 3 1/2 - 3 1/2 $ 28.91
BARROTE 1/2 DE POLIN
TARIMA $ 21.00
DUELA 3/4" X 4" $ 10.21
TABLON 1.5" - 12" - 8" DE 2DA
TABLON 1.5" - 12" - 8" DE 3ERA
ESTACAS 2" - 4" -20"
12 CLAVOS
Clavo de 2" KG 185 $ 20.50
1|11|1||11 Clavo de 2 1/2" KG 148 $ 20.50
Clavo de 3" KG 124 $ 20.50
Clavo de 4" KG 92 $ 20.50
LISTA DE PRECIO DE MATERIALES
DESCRIPCION UN PZAS P.U. PZAS P.U. TOTAL
2 CEMENTOS Y POLVOS
CAL TON 40 $ 30.00 $ 1,160.00
CEMENTO GRIS TON 20 $ 102.50 $ 2,050.00
CEMENTO BLANCO 25 KG 40 $ 86.00 $ 3,350.00
CEMENTO MORTERO TON 20 $ 75.00 $ 1,500.00
CEMENTO BLANCO 50 KG 20 $ 4.50 $ 3,350.00
COLOR AMARILLO P/ CEMENTO KG $ 27.00
COLOR ROJO P/ CEMENTO KG $ 27.00
COLOR NEGRO P/ CEMENTO KG $ 34.00
MARMOLINA TON 6 $ 26.50 $ 520.00
PEGAZULEJO BLANCO NIASA PZA 50 $ 65.50 $ 2,700.00
YESO SUPREMO TON 40 $ 40.00 $ 1,600.00
DESCRIPCION UN PZAS P.U. PZAS P.U. TOTAL
3 MATERIAL DE ARRASTRE Y PREFABRICADO
ARENA D/ MINA P/6 M3 6 $ 95.80 $ 1,260.00
ARENILLA P/ VIAJE M3 6 $ 112.33 $ 620.00
GRAVA 3/4 M3 6 $ 71.80 $ 1,120.00
TABICON 10*14*28 PIEZA PZA 1000 $ 2.10 $ 1,100.00
TABICON 10*14-28 500 PZA PZA 1000 $ 2.50 $ 1,150.00
TABICON 10*14*28 750 PIEZA PZA 1000
TABICON 10*14*28 MILLAR PZA 1000 $ 2,100.00
TEPETATE P/VIAJE 6 M3 6 $ 500.00 $ 550.00
TUBO DE ALBAÑAL 6" PZA $ 26.00 $ 26.00
TUBO DE ALBAÑAL 8" PZA $ 41.00 $ 41.00
DESCRIPCION UN PZAS P.U. PZAS P.U. TOTAL
4 HERRAMIENTAS
CARRETILLA ESTANDAR $ 710.00
CARRETILLA HONDA $ 770.00
CARRETILLA SUPER HONDA $ 810.00
CABO P/PALA $ 60.00
CABO P/ ZAPAPICO $ 66.00
CAJA 3*3 $ 3.00
CAJA 4*4 3/4 $ 5.00
CHALUPAS $ 350.00
PALA CUADRADA C/CABO $ 107.50
TAPA PARA CISTERNA 40 x 60 $ 233.00
TAPA PARA CISTERNA 60 x 60 $ 264.50
REGISTROS 1 1/4 40*60*60 $ 112.00
SEGUETAS pza $ 11.00
ZAPAPICO CON CABO $ 167.00
ZAPAPICO SIN CABO $ 101.00
SOBRE VOLUMEN
40%
SOBRE VOLUMEN
40%
SOBRE VOLUMEN
40%
DESCRIPCION UN PZAS P.U. PZAS P.U. TOTAL
7 LAMINAS
LAMINA ACRILICA EST 1.83*1 $ 274.00
LAMINA ACRILICA EST 2.14*1 $ 311.70
LAMINA ACRILICA EST 2.44*1 $ 253.00
LAMINA ACRILICA EST 2.60*1 $ 380.00
LAMINA ACRILICA EST 3.15*1 $ 459.00
LAMINA ACRILICA EST 3.66*1 $ 540.00
LAMINA ACRILICA RURAL 1.25*60 $ 120.00
LAMINA ACRILICA RURAL 1.25*1.20 $ 147.50
LAMINA CARTON DELGADA 1.20*55 $ 290.50
LAMINA CARTON GRUESA 6 1.23*55
LAMINA CARTON ROJA 1.23*55 $ 294.00
MULTITEJA COLOR ARCILLA 1.15*.85 $ 124.50
MULTITEJA CABALLETE ESTANDAR $ 119.80
TEJA SAN MIGUEL .97*1.26 $ 193.00
CABALLETE LIMATON S/MIGUEL $ 45.00
DESCRIPCION UN PZAS P.U. PZAS P.U. TOTAL
8 PLOMERIOA DE PVC
TUBO PVC DE NORMA 1 1/2 TRAMO $ 64.50
TUBO PVC DE NORMA 1 1/2 METRO $ 12.00
TUBO PVC DE NORMA 2" TRAMO $ 81.00
TUBO PVC DE NORMA 2" METRO $ 13.50
TUBO PVC DE NORMA 3" TRAMO $ 115.00
TUBO PVC DE NORMA 3" METRO $ 21.00
TUBO PVC DE NORMA 4" TRAMO $ 58.00
TUBO PVC DE NORMA 4" METRO $ -
TUBO PVC DE NORMA 6" TRAMO $ 403.00
TUBO PVC DE NORMA 6" METRO $ 73.00
CODO 45° CEMENTAL 1 1/2 $ 4.50
CODO 45° CEMENTAL 2" $ 4.00
CODO 45° CEMENTAL 3" $ 8.00
CODO 45° CEMENTAL 4" $ 15.00
CODO 45° CEMENTAL 6" $ 65.00
CODO 87° CEMETAL 3" $ 11.00
CODO 87° CEMENTAL 4" $ 12.00
CODO 87° CEMENTAL 6" $ 62.00
TEE SENCILLA CEMENTAL 1 1/2*1 1/2 $ 4.60
TEE SENCILLA CEMENTAL 2*2" $ 6.00
TEE SENCILLA CEMENTAL 3*3" $ 10.00
TEE SENCILLA CEMENTAL 4*4" $ 22.00
TEE SENCILLA CEMENTAL 6*6" $ 71.00
YEE SENCILLA CEMENTAL 1 1/2*1 1/2 $ 4.50
SOBRE VOLUMEN
40%
SOBRE VOLUMEN
40%
YEE SENCILLA CEMENTAL 2*2" $ 7.00
YEE SENCILLA CEMENTAL 3*3" $ 16.50
YEE SENCILLA CEMENTAL 4*4" $ 28.50
YEE SENCILLA CEMENTAL 4*2" $ 23.50
YEE SENCILLA CEMENTAL 6*6" $ 109.00
COPLE CEMENTAL 1 1/2" $ 2.80
COPLE CEMENTAL 2" $ 3.20
COPLE CEMENTAL 3" $ 7.00
COPLE CEMENTAL 4" $ 7.50
COPLE CEMENTAL 6" $ 34.50
CEMENTO PVC 500 LTS $ 76.00
COLADERA PVC $ 35.50
CESPOL BOTE DE UNA SALIDA 1 1/2" $ 34.00
CESPOL BOTE DE UNA SALIDA 2" $ 36.50
REDUCCION EXCENTRICA 2"*1/2 $ 3.00
REDUCCION EXCENTRICA PVC 4"2" $ 12.50
REDUCCION EXCENTRICA PVC 6"4" $ 38.00
DESCRIPCION UN PZAS P.U. PZAS P.U. TOTAL
11 VARIOS
AGUA M3 10 1000 l $ 200.00
HILOS PZA 1 $ 18.00
DIESEL LTS 19 l $ 19.00
CHAFLANES PZA 1 $ 7.00
ALQUILER EQUIPO DE MEDICION DIA 1 $ 1,200.00
VIAJE DE PIEDRA BRAZA M3 6 $ 1,250.00
SOBRE VOLUMEN
40%
DESCRIPCIONUN PZAS P.U. PZAS SOBRE VOLU P.U. TOTAL11 VARIOS
AGUA M3 10HILOS PZA 1DIESEL LTS 19CHAFLANES PZA 1ALQUILER EQDIA 1VIAJE DE PIE M3 6
ANALISIS DE COSTO TIPOCONCEPTO LECHADA CEMENTO BLANCO Un.
1.300T.de cemento +3%desp. Ton. 0.900 M3de agua +30% desp M3
TOTAL $ /M3=
ANALISIS DE COSTO TIPOCONCEPTO LECHADA CEMENTO GRIS Un.1.300T.de cemento +3%desp. Ton. 0.900 M3de agua +30% desp M3
TOTAL $ /M3=
ANALISIS DE COSTO TIPOCONCEPTO PASTA CEMENTO BLANCO Un.1.500T.de cemento blanco +3%desp. Ton. 0.700 M3 de agua +30% desp M3
TOTAL $ /M3=
ANALISIS DE COSTO TIPOCONCEPTO PASTA CEMENTO GRIS Un.1.500T.de cemento gris +3%desp. Ton. 0.700 M3 de agua +30% desp M3
TOTAL $ /M3=
ANALISIS DE COSTO TIPOCONCEPTO PASTA DE YESO Un.0.810T.de yeso +3%desp. Ton. 0.900 M3 de agua +30% desp M3
TOTAL $ /M3=
ANALISIS DE COSTO TIPOCONCEPTO PASTA CEMENTO BLANCO POLVO DE MARMOL 1:3 Un.0.540T. Cemento blanco +3% desp. Ton. 2.100 T.polvo marmol + 5% desp. Ton.0.280 M3 de agua +30% desp. M3
TOTAL $ /M3=
ANALISIS DE COSTO TIPO
CONCEPTO PASTA CEMENTO BLANCO POLVO DE MARMOL 1:4 Un.0.440T. Cemento blanco +3% desp. Ton. 2.200 T.polvo marmol + 5% desp. Ton.0.275 M3 de agua +30% desp. M3
TOTAL $ /M3=
ANALISIS DE COSTO TIPOCONCEPTO PASTA CEMENTO BLANCO POLVO DE MARMOL 1:5 Un.0.380T. Cemento blanco +3% desp. Ton. 2.300 T.polvo marmol + 5% desp. Ton.0.272 M3 de agua +30% desp. M3
TOTAL $ /M3=
ANALISIS DE COSTO TIPOCONCEPTO PASTA CEMENTO BLANCO CAL-POLVO DE MARMOL 1:1:6 Un.0.270T. Cemento blanco +3% desp. Ton. 0.125 T. calhidra + 3% desp. Ton. 2.100 T.polvo marmol + 5% desp. Ton.0.280 M3 de agua +30% desp. M3
TOTAL $ /M3=
ANALISIS DE COSTO TIPOCONCEPTO PASTA CEMENTO BLANCO CAL-POLVO DE MARMOL 1:1:8 Un.0.220T. Cemento blanco +3% desp. Ton. 0.100 T. calhidra + 3% desp. Ton. 2.200 T.polvo marmol + 5% desp. Ton.0.278 M3 de agua +30% desp. M3
TOTAL $ /M3=
ANALISIS DE COSTO TIPOCONCEPTO PASTA CEMENTO BLANCO CAL-POLVO DE MARMOL 1:1:10 Un.0.190T. Cemento blanco +3% desp. Ton. 0.085 T. calhidra + 3% desp. Ton. 2.300 T.polvo marmol + 5% desp. Ton.0.276 M3 de agua +30% desp. M3
TOTAL $ /M3=
ANALISIS DE COSTO TIPOCONCEPTO PASTA CEMENTO BLANCO CAL-POLVO DE MARMOL 1:1:12 Un.0.135T. Cemento blanco +3% desp. Ton. 0.075 T. calhidra + 3% desp. Ton. 2.400 T.polvo marmol + 5% desp. Ton.0.274 M3 de agua +30% desp. M3
TOTAL $ /M3=
ANALISIS DE COSTO TIPOCant. P.U Importe
1.339 $ 86.00 $ 115.15 1.17 $ 200.00 $ 234.00
TOTAL $ /M3= ∑= $ 349.15
ANALISIS DE COSTO TIPOCant. P.U Importe
1.339 $ 102.50 $ 137.25 1.17 $ 200.00 $ 234.00
TOTAL $ /M3= ∑= $ 371.25
ANALISIS DE COSTO TIPOCant. P.U Importe
1.545 $ 86.00 $ 132.87 0.91 $ 200.00 $ 182.00
TOTAL $ /M3= ∑= $ 314.87
ANALISIS DE COSTO TIPOCant. P.U Importe
1.545 $ 102.50 $ 158.36 0.91 $ 200.00 $ 182.00
TOTAL $ /M3= ∑= $ 340.36
ANALISIS DE COSTO TIPOCant. P.U Importe
0.8343 $ 40.00 $ 33.37 1.17 $ 200.00 $ 234.00
TOTAL $ /M3= ∑= $ 267.37
ANALISIS DE COSTO TIPO PASTA CEMENTO BLANCO -POLVO MARMOLCant. P.U Importe CLASIFICACION. Cemento T Polvo marmol T
0.5562 $ 86.00 47.8332 Proporcion 1:3 0.54 2.12.205 $ 26.50 58.4325 Proporcion 1:4 0.44 2.20.364 $ 200.00 72.8 Proporcion 1:5 0.38 2.3
TOTAL $ /M3= ∑= 179.0657TOTAL $=
ANALISIS DE COSTO TIPO
Cant. P.U Importe0.4532 $ 86.00 38.9752
2.31 $ 26.50 61.2150.3575 $ 200.00 71.5
TOTAL $ /M3= ∑= 171.6902
ANALISIS DE COSTO TIPOCant. P.U Importe
0.3914 $ 86.00 33.66042.415 $ 26.50 63.9975
0.3536 $ 200.00 70.72TOTAL $ /M3= ∑= 168.3779
ANALISIS DE COSTO TIPO PASTA CEMENTO BLANCO -CAL-POLVO MARMOLCant. P.U Importe CLASIFICACION. Cemento blanco T calhidra T
0.2781 $ 86.00 23.9166 Proporcion 1:1:6 0.27 0.1250.12875 $ 30.00 3.8625 Proporcion 1:1:8 0.22 0.1
2.205 $ 26.50 58.4325 Proporcion 1:1:10 0.19 0.085
0.364 $ 200.00 72.8 Proporcion 1:1:12 0.135 0.075
TOTAL $ /M3= ∑= 159.0116
ANALISIS DE COSTO TIPOCant. P.U Importe
0.2266 $ 86.00 19.48760.103 $ 30.00 3.09
2.31 $ 26.50 61.2150.3614 $ 200.00 72.28
TOTAL $ /M3= ∑= 156.0726
ANALISIS DE COSTO TIPOCant. P.U Importe
0.1957 $ 86.00 16.83020.08755 $ 30.00 2.6265
2.415 $ 26.50 63.99750.3588 $ 200.00 71.76
TOTAL $ /M3= ∑= 155.2142
ANALISIS DE COSTO TIPOCant. P.U Importe
0.13905 $ 86.00 11.95830.07725 $ 30.00 2.3175
2.52 $ 26.50 66.780.3562 $ 200.00 71.24
TOTAL $ /M3= ∑= 152.2958
PASTA CEMENTO BLANCO -POLVO MARMOLAgua m3 Costo $/m3
0.28 179.06570.275 171.69020.272 168.3779
519.1338
PASTA CEMENTO BLANCO -CAL-POLVO MARMOLPolvo marmol T Agua m3 Costo $/m3
2.1 0.28 159.01162.2 0.278 156.07262.3 0.276 155.21422.4 0.274 152.2958
622.5942
ANALISIS DE COSTO TIPOCONCEPTO MESCLA CALHIDRA-ARENA1:3 Un. Cant. P.U Importe0.250 T.de calhidra +3%desp. Ton. 0.2575 $ 30.00 7.725 1.000 M3 de arena + 8% desp M3 1.08 $ 95.80 103.464 0.270 M3 de agua +30% desp M4 0.351 $ 200.00 70.2
TOTAL $ /M3= ∑= 181.389
ANALISIS DE COSTO TIPOCONCEPTO MESCLA CALHIDRA-ARENA1:4 Un. Cant. P.U Importe0.200 T.de calhidra +3%desp. Ton. 0.206 $ 30.00 6.18 1.070 M3 de arena + 8% desp M3 1.1556 $ 95.80 110.7065 0.260 M3 de agua +30% desp M4 0.338 $ 200.00 67.6
TOTAL $ /M3= ∑= 184.4865
ANALISIS DE COSTO TIPOCONCEPTO MESCLA CALHIDRA-ARENA1:5 Un. Cant. P.U Importe0.170 T.de calhidra +3%desp. Ton. 0.1751 $ 30.00 5.253 0.130 M3 de arena + 8% desp M3 0.1404 $ 95.80 13.45032 0.255 M3 de agua +30% desp M4 0.3315 $ 200.00 66.3
TOTAL $ /M3= ∑= 85.00332
ANALISIS DE COSTO TIPOCONCEPTO MESCLA CALHIDRA-ARENA1:6 Un. Cant. P.U Importe0.145 T.de calhidra +3%desp. Ton. 0.14935 $ 30.00 4.4805 1.180 M3 de arena + 8% desp M3 1.2744 $ 95.80 122.0875 0.250 M3 de agua +30% desp M4 0.325 $ 200.00 65
TOTAL $ /M3= ∑= 191.568
ANALISIS DE COSTO TIPOCONCEPTO MESCLA CALHIDRA-ARENA1:7 Un. Cant. P.U Importe0.125 T.de calhidra +3%desp. Ton. 0.12875 $ 30.00 3.8625 1.220 M3 de arena + 8% desp M3 1.3176 $ 95.80 126.2261 0.245 M3 de agua +30% desp M4 0.3185 $ 200.00 63.7
TOTAL $ /M3= ∑= 193.7886
ANALISIS DE COSTO TIPOCONCEPTO MESCLA CALHIDRA-ARENA1:8 Un. Cant. P.U Importe0.110 T.de calhidra +3%desp. Ton. 0.1133 $ 30.00 3.399 1.250 M3 de arena + 8% desp M3 1.35 $ 95.80 129.33 0.240 M3 de agua +30% desp M4 0.312 $ 200.00 62.4
TOTAL $ /M3= ∑= 195.129
ANALISIS DE COSTO TIPOCONCEPTO MESCLA CALHIDRA-ARENA1:9 Un. Cant. P.U Importe0.100 T.de calhidra +3%desp. Ton. 0.103 $ 30.00 3.09 1.270 M3 de arena + 8% desp M3 1.3716 $ 95.80 131.3993 0.235 M3 de agua +30% desp M4 0.3055 $ 200.00 61.1
TOTAL $ /M3= ∑= 195.5893
ANALISIS DE COSTO TIPOCONCEPTO MESCLA CALHIDRA-ARENA1:10 Un. Cant. P.U Importe0.090 T.de calhidra +3%desp. Ton. 0.0927 $ 30.00 2.781 1.285 M3 de arena + 8% desp M3 1.3878 $ 95.80 132.9512 0.230 M3 de agua +30% desp M4 0.299 $ 200.00 59.8
TOTAL $ /M3= ∑= 195.5322
ANALISIS DE COSTO TIPOCONCEPTO MESCLA-ARENA 1:4 Un. Cant. P.U Importe0.300 T. de mortero +3% desp. Ton. 0.309 $ 75.00 23.175 1.150 m3 de arena + 8% desp. m3 1.242 $ 95.80 118.98360.290 M3 de agua +30% desp. M3 0.377 $ 200.00 75.4
TOTAL $ /M3= ∑= 217.5586
ANALISIS DE COSTO TIPOCONCEPTO MESCLA-ARENA 1:5 Un. Cant. P.U Importe0.260 T. de mortero +3% desp. Ton. 0.2678 $ 75.00 20.085 1.260 m3 de arena + 8% desp. m3 1.3608 $ 95.80 130.36460.285 M3 de agua +30% desp. M3 0.3705 $ 200.00 74.1
TOTAL $ /M3= ∑= 224.5496
ANALISIS DE COSTO TIPOCONCEPTO MESCLA-ARENA 1:6 Un. Cant. P.U Importe0.225 T. de mortero +3% desp. Ton. 0.23175 $ 75.00 17.38125 1.240 m3 de arena + 8% desp. m3 1.3392 $ 95.80 128.29540.280 M3 de agua +30% desp. M3 0.364 $ 200.00 72.8
TOTAL $ /M3= ∑= 218.4766
ANALISIS DE COSTO TIPOCONCEPTO MESCLA-ARENA 1:7 Un. Cant. P.U Importe0.195 T. de mortero +3% desp. Ton. 0.20085 $ 75.00 15.06375 1.270 m3 de arena + 8% desp. m3 1.3716 $ 95.80 131.39930.275 M3 de agua +30% desp. M3 0.3575 $ 200.00 71.5
TOTAL $ /M3= ∑= 217.963
ANALISIS DE COSTO TIPOCONCEPTO MESCLA-ARENA 1:8 Un. Cant. P.U Importe0.170 T. de mortero +3% desp. Ton. 0.1751 $ 75.00 13.1325 1.290 m3 de arena + 8% desp. m3 1.3932 $ 95.80 133.46860.270 M3 de agua +30% desp. M3 0.351 $ 200.00 70.2
TOTAL $ /M3= ∑= 216.8011
ANALISIS DE COSTO TIPO
CONCEPTO MESCLA CEMENTO-ARENA 1:2 Un. Cant. P.U Importe0.600 T. de CEMENTO +3% desp. Ton. 0.618 0 1.000 m3 de arena + 8% desp. m3 1.08 $ 95.80 103.4640.275 M3 de agua +30% desp. M3 0.3575 $ 200.00 71.5
TOTAL $ /M3= ∑= 174.964
ANALISIS DE COSTO TIPOCONCEPTO MESCLA CEMENTO-ARENA 1:3 Un. Cant. P.U Importe0.510 T. de CEMENTO +3% desp. Ton. 0.5253 0 0 1.100 m3 de arena + 8% desp. m3 1.188 $ 95.80 113.81040.272 M3 de agua +30% desp. M3 0.3536 $ 200.00 70.72
TOTAL $ /M3= ∑= 184.5304
ANALISIS DE COSTO TIPOCONCEPTO MESCLA CEMENTO-ARENA 1:4 Un. Cant. P.U Importe0.430 T. de CEMENTO +3% desp. Ton. 0.4429 0 0 1.120 m3 de arena + 8% desp. m3 1.2096 $ 95.80 115.87970.266 M3 de agua +30% desp. M3 0.3458 $ 200.00 69.16
TOTAL $ /M3= ∑= 185.0397
ANALISIS DE COSTO TIPOCONCEPTO MESCLA CEMENTO-ARENA 1:5 Un. Cant. P.U Importe0.360 T. de CEMENTO +3% desp. Ton. 0.3708 0 0 1.150 m3 de arena + 8% desp. m3 1.242 $ 95.80 118.98360.261 M3 de agua +30% desp. M3 0.3393 $ 200.00 67.86
TOTAL $ /M3= ∑= 186.8436
ANALISIS DE COSTO TIPOCONCEPTO MESCLA CEMENTO-ARENA 1:6 Un. Cant. P.U Importe0.300 T. de CEMENTO +3% desp. Ton. 0.309 0 0 1.190 m3 de arena + 8% desp. m3 1.2852 $ 95.80 123.12220.257 M3 de agua +30% desp. M3 0.3341 $ 200.00 66.82
TOTAL $ /M3= ∑= 189.9422
ANALISIS DE COSTO TIPOCONCEPTO MESCLA CEMENTO-ARENA 1:7 Un. Cant. P.U Importe0.250 T. de CEMENTO +3% desp. Ton. 0.2575 0 0 1.240 m3 de arena + 8% desp. m3 1.3392 $ 95.80 128.29540.252 M3 de agua +30% desp. M3 0.3276 $ 200.00 65.52
TOTAL $ /M3= ∑= 193.8154
ANALISIS DE COSTO TIPOCONCEPTO MESCLA CEMENTO-ARENA 1:8 Un. Cant. P.U Importe0.210 T. de CEMENTO +3% desp. Ton. 0.2163 0 0 1.300 m3 de arena + 8% desp. m3 1.404 $ 95.80 134.50320.246 M3 de agua +30% desp. M3 0.3198 $ 200.00 63.96
TOTAL $ /M3= ∑= 198.4632
ANALISIS DE COSTO TIPOCONCEPTO MESCLA CEMENTO-ARENA CERNIDA1:2 Un. Cant. P.U Importe0.630 T. de CEMENTO +3% desp. Ton. 0.6489 0 0 1.000 m3 de arena + 35% desp. m3 1.35 $ 95.80 129.330.285 M3 de agua +30% desp. M3 0.3705 $ 200.00 74.1
TOTAL $ /M3= ∑= 203.43
ANALISIS DE COSTO TIPOCONCEPTO MESCLA CEMENTO-ARENA CERNIDA1:3 Un. Cant. P.U Importe0.540 T. de CEMENTO +3% desp. Ton. 0.5562 0 0 1.050 m3 de arena + 35% desp. m3 1.4175 $ 95.80 135.79650.280 M3 de agua +30% desp. M3 0.364 $ 200.00 72.8
TOTAL $ /M3= ∑= 208.5965
ANALISIS DE COSTO TIPOCONCEPTO MESCLA CEMENTO-ARENA CERNIDA1:4 Un. Cant. P.U Importe0.440 T. de CEMENTO +3% desp. Ton. 0.4532 0 0 1.100 m3 de arena + 35% desp. m3 1.485 $ 95.80 142.2630.278 M3 de agua +30% desp. M3 0.3614 $ 200.00 72.28
TOTAL $ /M3= ∑= 214.543
ANALISIS DE COSTO TIPOCONCEPTO MESCLA CEMENTO-ARENA CERNIDA1:5 Un. Cant. P.U Importe0.380 T. de CEMENTO +3% desp. Ton. 0.3914 0 0 1.150 m3 de arena + 35% desp. m3 1.5525 $ 95.80 148.72950.275 M3 de agua +30% desp. M3 0.3575 $ 200.00 71.5
TOTAL $ /M3= ∑= 220.2295
ANALISIS DE COSTO TIPOCONCEPTO MESCLA CEMENTO-ARENA CERNIDA1:6 Un. Cant. P.U Importe0.310 T. de CEMENTO +3% desp. Ton. 0.3193 0 0 1.170 m3 de arena + 35% desp. m3 1.5795 $ 95.80 151.31610.273 M3 de agua +30% desp. M3 0.3549 $ 200.00 70.98
TOTAL $ /M3= ∑= 222.2961
ANALISIS DE COSTO TIPOCONCEPTO MESCLA CEMENTO CALHIDRA -ARENA 1:1:4 Un. Cant. P.U Importe0.300T. Cemento +3% desp. Ton. 0.309 0 0 0.150 T. calhidra + 3% desp. Ton. 0.1545 $ 30.00 4.635 1.000 M3 de arena + 8% desp. M3 1.08 $ 95.80 103.4640.280 M3 de agua +30% desp. M3 0.364 $ 200.00 72.8
TOTAL $ /M3= ∑= 180.899
ANALISIS DE COSTO TIPO
CONCEPTO MESCLA CEMENTO CALHIDRA -ARENA 1:1:6 Un. Cant. P.U Importe0.255T. Cemento +3% desp. Ton. 0.26265 0 0 0.125 T. calhidra + 3% desp. Ton. 0.12875 $ 30.00 3.8625 1.050 M3 de arena + 8% desp. M3 1.134 $ 95.80 108.63720.275 M3 de agua +30% desp. M3 0.3627 $ 200.00 72.54
TOTAL $ /M3= ∑= 185.0397
ANALISIS DE COSTO TIPOCONCEPTO MESCLA CEMENTO CALHIDRA -ARENA 1:1:8 Un. Cant. P.U Importe0.215T. Cemento +3% desp. Ton. 0.22145 0 0 0.100 T. calhidra + 3% desp. Ton. 0.103 $ 30.00 3.09 1.095 M3 de arena + 8% desp. M3 1.1826 $ 95.80 113.29310.278 M3 de agua +30% desp. M3 0.3614 $ 200.00 72.28
TOTAL $ /M3= ∑= 188.6631
ANALISIS DE COSTO TIPOCONCEPTO MESCLA CEMENTO CALHIDRA -ARENA 1:1:10 Un. Cant. P.U Importe0.180T. Cemento +3% desp. Ton. 0.1854 0 0 0.085 T. calhidra + 3% desp. Ton. 0.08755 $ 30.00 2.6265 1.065 M3 de arena + 8% desp. M3 1.1502 $ 95.80 110.18920.275 M3 de agua +30% desp. M3 0.3575 $ 200.00 71.5
TOTAL $ /M3= ∑= 184.3157
ANALISIS DE COSTO TIPOCONCEPTO MESCLA CEMENTO CALHIDRA -ARENA 1:1:12 Un. Cant. P.U Importe0.150T. Cemento +3% desp. Ton. 0.1545 0 0 0.075 T. calhidra + 3% desp. Ton. 0.07725 $ 30.00 2.3175 1.185 M3 de arena + 8% desp. M3 1.2798 $ 95.80 122.60480.273 M3 de agua +30% desp. M3 0.3549 $ 200.00 70.98
TOTAL $ /M3= ∑= 195.9023
MESCLAS CALHIDRA ARENACLASIFICACION. calhidra T Arena m3 Agua m3 Costo $/m3Proporcion 1:3 0.25 1 0.27 181.389Proporcion 1:4 0.2 1.07 0.26 184.48648Proporcion 1:5 0.17 1.13 0.255 85.00332Proporcion 1:6 0.145 1.18 0.25 191.56802Proporcion 1:7 0.125 1.22 0.245 193.78858Proporcion 1:8 0.11 1.25 0.24 195.129Proporcion 1:9 0.1 1.27 0.235 195.58928Proporcion 1:10 0.09 1.285 0.23 195.53224
MESCLAS MORTERO ARENACLASIFICACION. Mortero T Arena m3 Agua m3 Costo $/m3Proporcion 1:4 0.3 1.15 0.29 217.5586Proporcion 1:5 0.26 1.2 0.285 224.54964Proporcion 1:6 0.225 1.24 0.28 218.47661Proporcion 1:7 0.195 1.27 0.275 217.96303Proporcion 1:8 0.17 1.29 0.27 216.80106
MESCLAS MORTERO ARENA
CLASIFICACION. Mortero T Arena m3 Agua m3 Costo $/m3Proporcion 1:2 0.6 1 0.275 174.964Proporcion 1:3 0.51 1.1 0.272 184.5304Proporcion 1:4 0.43 1.2 0.266 185.03968Proporcion 1:5 0.36 1.15 0.261 186.8436Proporcion 1:6 300 1.19 0.257 189.94216Proporcion 1:7 0.25 1.24 0.252 193.81536Proporcion 1:8 0.21 1.3 0.246 198.4632
MESCLAS MORTERO ARENACLASIFICACION. Mortero T Arena m3 Agua m3 Costo $/m3Proporcion 1:2 0.63 1 0.285 203.43Proporcion 1:3 0.54 1.05 0.28 208.5965Proporcion 1:4 0.44 1.1 0.278 214.543Proporcion 1:5 0.38 1.15 0.275 220.2295Proporcion 1:6 310 1.17 0.273 222.2961
MESCLA CEMENTO-CALHIDRA-ARENACLASIFICACION. Cemento T calhidra T Arena m3 Agua m3 Costo $/m3Proporcion 1:1:4 0.3 0.15 1 0.28 180.899Proporcion 1:1:6 0.255 0.125 1.05 0.79 185.0397Proporcion 1:1:8 0.215 0.1 1.095 0.278 188.66308Proporcion 1:1:10 0.18 0.085 1.065 0.275 184.31566Proporcion 1:1:12 0.15 0.075 1.185 0.273 195.90234
ANALISIS DE COSTO TIPO
CONCEPTO CONCRETADO 100 kg/cm2 AGREGADO 3/4"CEMENTO NORMAL REV 8 a 10 CM0.260 T. Cemento resistencia rapida +3% desp. 0.500 m3 arena + 8% desp. 0.680 M3 grava + 8% desp.0.195 M3 agua +30% desp.
TOTAL $ /M2=
ANALISIS DE COSTO TIPOCONCEPTO CONCRETADO 100 kg/cm2 AGREGADO 1 1/2"CEMENTO NORMAL REV 8 a 10 CM0.254 T. Cemento resistencia rapida +3% desp. 0.470 m3 arena + 8% desp. 0.700 M3 grava + 8% desp.0.190 M3 agua +30% desp.
TOTAL $ /M2=
ANALISIS DE COSTO TIPOCONCEPTO CONCRETADO 100 kg/cm2 AGREGADO 3/4"CEMENTO NORMAL REV 12 a 15 CM0.286 T. Cemento resistencia rapida +3% desp. 0.500 m3 arena + 8% desp. 0.680 M3 grava + 8% desp.0.215 M3 agua +30% desp.
TOTAL $ /M2=
ANALISIS DE COSTO TIPO
CONCEPTO CONCRETADO 100 kg/cm2 AGREGADO 1 1/2"CEMENTO NORMAL REV 12 a 15CM0.280 T. Cemento resistencia rapida +3% desp. 0.470 m3 arena + 8% desp. 0.700 M3 grava + 8% desp.0.210 M3 agua +30% desp.
TOTAL $ /M2=
ANALISIS DE COSTO TIPOCONCEPTO CONCRETADO 150 kg/cm2 AGREGADO 3/4"CEMENTO NORMAL REV 8 a 10 CM0.323 T. Cemento resistencia rapida +3% desp. 0.480 m3 arena + 8% desp. 0.670 M3 grava + 8% desp.0.210 M3 agua +30% desp.
TOTAL $ /M2=
ANALISIS DE COSTO TIPOCONCEPTO CONCRETADO 150 kg/cm2 AGREGADO 1 1/2"CEMENTO NORMAL REV 8 a 10 CM0.308 T. Cemento resistencia rapida +3% desp. 0.450 m3 arena + 8% desp. 0.700 M3 grava + 8% desp.0.200 M3 agua +30% desp.
TOTAL $ /M2=
ANALISIS DE COSTO TIPOCONCEPTO CONCRETADO 150 kg/cm2 AGREGADO 3/4"CEMENTO NORMAL REV 12a 15 CM
0.354 T. Cemento resistencia rapida +3% desp. 0.480 m3 arena + 8% desp. 0.670 M3 grava + 8% desp.0.210 M3 agua +30% desp.
TOTAL $ /M2=
ANALISIS DE COSTO TIPOCONCEPTO CONCRETADO 150 kg/cm2 AGREGADO 1 1/2"CEMENTO NORMAL REV 12 a 15 CM0.338 T. Cemento resistencia rapida +3% desp. 0.450 m3 arena + 8% desp. 0.700 M3 grava + 8% desp.0.220 M3 agua +30% desp.
TOTAL $ /M2=
ANALISIS DE COSTO TIPOCONCEPTO CONCRETADO 200 kg/cm2 AGREGADO 3/4"CEMENTO NORMAL REV 8 a 10 CM0.355 T. Cemento resistencia rapida +3% desp. 0.470 m3 arena + 8% desp. 0.650 M3 grava + 8% desp.0.195 M3 agua +30% desp.
TOTAL $ /M2=TOTAL $=
ANALISIS DE COSTO TIPOCONCEPTO CONCRETADO 200 kg/cm2 AGREGADO 1 1/2"CEMENTO NORMAL REV 8 a 10 CM0.337 T. Cemento resistencia rapida +3% desp.
0.440 m3 arena + 8% desp. 0.680 M3 grava + 8% desp.0.185 M3 agua +30% desp.
TOTAL $ /M2=
ANALISIS DE COSTO TIPOCONCEPTO CONCRETADO 200 kg/cm2 AGREGADO 3/4"CEMENTO NORMAL REV 12a 15 CM0.391 T. Cemento resistencia rapida +3% desp. 0.470 m3 arena + 8% desp. 0.650 M3 grava + 8% desp.0.215 M3 agua +30% desp.
TOTAL $ /M2=
ANALISIS DE COSTO TIPOCONCEPTO CONCRETADO 200 kg/cm2 AGREGADO 1 1/2"CEMENTO NORMAL REV 12 a 15 CM0.373 T. Cemento resistencia rapida +3% desp. 0.440 m3 arena + 8% desp. 0.680 M3 grava + 8% desp.0.205 M3 agua +30% desp.
TOTAL $ /M2=
ANALISIS DE COSTO TIPOCONCEPTO CONCRETADO 250kg/cm2 AGREGADO 3/4"CEMENTO NORMAL REV 8 a 10 CM0.423 T. Cemento resistencia rapida +3% desp. 0.465 m3 arena + 8% desp.
0.640 M3 grava + 8% desp.0.190 M3 agua +30% desp.
TOTAL $ /M2=
ANALISIS DE COSTO TIPOCONCEPTO CONCRETADO 250 kg/cm2 AGREGADO 1 1/2"CEMENTO NORMAL REV 8 a 10 CM0.400 T. Cemento resistencia rapida +3% desp. 0.435 m3 arena + 8% desp. 0.670 M3 grava + 8% desp.0.180 M3 agua +30% desp.
TOTAL $ /M2=
ANALISIS DE COSTO TIPOCONCEPTO CONCRETADO 250 kg/cm2 AGREGADO 3/4"CEMENTO NORMAL REV 12a 15 CM0.467 T. Cemento resistencia rapida +3% desp. 0.465 m3 arena + 8% desp. 0.640 M3 grava + 8% desp.0.210 M3 agua +30% desp.
TOTAL $ /M2=
ANALISIS DE COSTO TIPOCONCEPTO CONCRETADO 250 kg/cm2 AGREGADO 1 1/2"CEMENTO NORMAL REV 12 a 15 CM0.445 T. Cemento resistencia rapida +3% desp. 0.435 m3 arena + 8% desp. 0.670 M3 grava + 8% desp.0.200 M3 agua +30% desp.
TOTAL $ /M2=
ANALISIS DE COSTO TIPOCONCRETO HECHO EN OBRA
Un. Cant. P.U ImporteTon. 0.2678 0 0
100 kg/cm2Ton. 0.54 $ 95.80 51.732M3 0.7344 $ 71.80 52.72992M3 0.2535 $ 200.00 50.7
TOTAL $ /M2= ∑= 155.1619
150kg/cm2ANALISIS DE COSTO TIPOUn. Cant. P.U ImporteTon. 0.26162 0 0Ton. 0.5076 $ 95.80 48.62808M3 0.756 $ 71.80 54.2808
200kg/cm2M3 0.247 $ 200.00 49.4TOTAL $ /M2= ∑= 152.3089
ANALISIS DE COSTO TIPOUn. Cant. P.U Importe
250kg/cm2Ton. 0.29458 0 0Ton. 0.54 $ 95.80 51.732M3 0.7344 $ 71.80 52.72992M3 0.2795 $ 200.00 55.9
TOTAL $ /M2= ∑= 160.3619
ANALISIS DE COSTO TIPO
f"
Un. Cant. P.U ImporteTon. 0.2884 0 0Ton. 0.5076 $ 95.80 48.62808M3 0.756 $ 71.80 54.2808M3 0.273 $ 200.00 54.6
TOTAL $ /M2= ∑= 157.5089
ANALISIS DE COSTO TIPOUn. Cant. P.U ImporteTon. 0.33269 0 0Ton. 0.5184 $ 95.80 49.66272M3 0.7236 $ 71.80 51.95448M3 0.273 $ 200.00 54.6
TOTAL $ /M2= ∑= 156.2172
ANALISIS DE COSTO TIPOUn. Cant. P.U ImporteTon. 0.31724 0 0Ton. 0.486 $ 95.80 46.5588M3 0.756 $ 71.80 54.2808M3 0.26 $ 200.00 52
TOTAL $ /M2= ∑= 152.8396
ANALISIS DE COSTO TIPOUn. Cant. P.U Importe
Ton. 0.36462 0 0Ton. 0.5184 $ 95.80 49.66272M3 0.7236 $ 71.80 51.95448M3 0.273 $ 200.00 54.6
TOTAL $ /M2= ∑= 156.2172
ANALISIS DE COSTO TIPOUn. Cant. P.U ImporteTon. 0.34814 0 0Ton. 0.486 $ 95.80 46.5588M3 0.756 $ 71.80 54.2808M3 0.286 $ 200.00 57.2
TOTAL $ /M2= ∑= 158.0396
ANALISIS DE COSTO TIPOUn. Cant. P.U ImporteTon. 0.36565 0 0Ton. 0.5076 $ 95.80 48.62808M3 0.702 $ 71.80 50.4036M3 0.2535 $ 200.00 50.7
TOTAL $ /M2= ∑= 149.7317
ANALISIS DE COSTO TIPOUn. Cant. P.U ImporteTon. 0.34711 0 0
Ton. 0.4752 $ 95.80 45.52416M3 0.7344 $ 71.80 52.72992M3 0.2405 $ 200.00 48.1
TOTAL $ /M2= ∑= 146.3541
ANALISIS DE COSTO TIPOUn. Cant. P.U ImporteTon. 0.40273 0 0Ton. 0.5076 $ 95.80 48.62808M3 0.702 $ 71.80 50.4036M3 0.2795 $ 200.00 55.9
TOTAL $ /M2= ∑= 154.9317
ANALISIS DE COSTO TIPOUn. Cant. P.U ImporteTon. 0.38419 0 0Ton. 0.4752 $ 95.80 45.52416M3 0.7344 $ 71.80 52.72992M3 0.2665 $ 200.00 53.3
TOTAL $ /M2= ∑= 151.5541
ANALISIS DE COSTO TIPOUn. Cant. P.U ImporteTon. 0.43569 0 0Ton. 0.5022 $ 95.80 48.11076
M3 0.6912 $ 71.80 49.62816M3 0.247 $ 200.00 49.4
TOTAL $ /M2= ∑= 147.1389
ANALISIS DE COSTO TIPOUn. Cant. P.U ImporteTon. 0.412 0 0Ton. 0.4698 $ 95.80 45.00684M3 0.7236 $ 71.80 51.95448M3 0.234 $ 200.00 46.8
TOTAL $ /M2= ∑= 143.7613
ANALISIS DE COSTO TIPOUn. Cant. P.U ImporteTon. 0.48101 0 0Ton. 0.5022 $ 95.80 48.11076M3 0.6912 $ 71.80 49.62816M3 0.273 $ 200.00 54.6
TOTAL $ /M2= ∑= 152.3389
ANALISIS DE COSTO TIPOUn. Cant. P.U ImporteTon. 0.45835 0 0Ton. 0.4698 $ 95.80 45.00684M3 0.7236 $ 71.80 51.95448M3 0.26 $ 200.00 52
TOTAL $ /M2= ∑= 148.9613
CONCRETO HECHO EN OBRA
Arena m3 Grva m3
8 a 10 cm 3/4" 0.26 0.5 0.68
1 1/2" 0.254 0.47 0.7
12 a 15 cm3/4" 0.286 0.5 0.68
1 1/2" 0.28 0.47 0.7
8 a 10 cm 3/4" 0.323 0.48 0.67
1 1/2" 0.308 0.45 0.7
12 a 15 cm3/4" 0.354 0.48 0.67
1 1/2" 0.338 0.45 0.7
8 a 10 cm 3/4" 0.355 0.47 0.65
1 1/2" 0.337 0.44 0.68
12 a 15 cm3/4" 0.391 0.47 0.65
1 1/2" 0.373 0.44 0.68
8 a 10 cm 3/4" 0.423 0.465 0.64
1 1/2" 0.4 0.435 0.67
12 a 15 cm3/4" 0.467 0.465 0.64
1 1/2" 0.445 0.435 0.67
f" Agregado maximo
Cemento Ton.
CONCRETO HECHO EN OBRA
Agua m3 costo $/m3 costo $/m3
0.195 155.161920.19 152.30888
0.215 160.361920.21 157.50888
0.21 156.21720.2 152.8396
0.23 156.21720.22 158.0396
0.195 149.731680.185 146.354080.215 154.931680.205 151.55408
0.19 147.138920.18 143.761320.21 152.338920.2 148.96132
CEMENTO NORMAL
CEMENTO ALTA RESISTENCIA
257.97 269.92253.6 265.38
272.24 285.5267.94 280.92
289.48 304.45281.2 295.47
306.52 322.23297.7 313.23
303.95 320.41294.03 309.65323.69 341.81313.83 331.12
339.57 359.18326.93 345.47363.71 385.36351.65 372.28
CONCEPTO Un. Gpo.
Preliminares y cimentacion. Limpiezay trazo m2 2Excavacion en tierra hasta de 2.0M de profundidad m3 1Excavacion en tepetate blando hasta de 2.0M de profundidad m3 1Traspaleo hasta2 m m3 1Acarreo concarretilla a 20.00 m. maximo m3 1rellenos por capas, compactadas con pison de mano m3 1compactacion de cepas con pison de mano m2 1Plantillas entre .07 y.10 m m2 2Cimientos de piedra braza m3 5Habilitado y armado de fierro e refuerzoa) en cimentacion Ton. 4b) en estructura Ton. 4
Ton. 4Cimbra y desimbrar , acabado no aparente.a)en cimientos m2 3b) en columnas rectangulares m2 3c)en columnas circulares m2 3d) en trabes m2 3e)en losas m2 3Hechura de cimbraa)en cimientos m2 3b) en columnas rectangulares m2 3c)en columnas circulares m2 3d) en trabes m2 3e)en losas m2 3f)cimbrar y desimbrar en sonotubo m 3losas reticuladascolocacion block hasta 20x40x40cm caja 2colocacion block hasta 35x60x60cm caja 2entrepiso reticular celulado linea menor caja 2entrepiso reticular celulado linea mayor caja 2
colados(no incluyendo la fabricacion del concreto)a)en cimientos m3 2b) en columnas y muros m3 2c)en trbes y muros m3 2d)en losas reticuladas m3 2e)curado de concreto con agua en superficies horizontales m3 1f)curado de concreto con agua m2 1g)curado de concreto con agua en superficies verticales m2 1
muros de tabique comun o ligero no aparentea) de 0.07m de espesor m2 5b) de 0.14m de espesor m2 5c) de 0.21m de espesor m2 5d)de 0.28m de espesor m2 5
Habilitando y armando de alambron de 1/4 y 5/16 "Ø
e) sobre precio por cara aparente m2 5muros de block tipo piramide
a)de 0.10 m de espesor m2 5b) de 0.12 m de espesor m2 5c) de 0.15 m de espesor m2 5d) de 0.20 m de espesor m2 5e) sobre precio por cara aparente m2 5
muro de block extruidoa) de 5x10x15 en 10 cm espesor m2 6b) de 6x10x20 en 10 cm espesor m2 6c) de 10x10x20 en 10 cm espesor m2 6d) de 10x15x20 en 15 cm espesor m2 6e) sobre precio por cara aparente m2 6
castillos y cadenascastillo centro de block 1Ø (3/8") 9.5mm m 5castillos y cadenas 15 x 15 con 4 Ø (3/8") 9.5mm m 5castillos y cadenas 15 x 20 con 4 Ø (3/8") 9.5mm m 5castillos y cadenas 15 x 30 con 4 Ø (3/8") 9.5mm m 5sobre cara aparente castillos y cadenas m 5
recubrimientosrepellados de mezcla m2 5aplanados de mezcla (rostreados) m2 5aplanados finos de mescla m2 5aplanados pulidos de cemento llana m2 5confitillo sobre aplanado m2 5recubrimiento de ceramica o mosaico veneciano incle repellado m2 6recubrimiento cintilla 5.5 x 22 x 1.0 a 6.0 x 24 x 1.0 cm m2 6recubrimiento fachaleta 10 x 20 x 1 a 11 x 22 x 1 cm m2 6recubrimiento azulejo m2 6recubrimiento tipo vitricota 6 x 20 x 18 cm m2 6recubrimiento tipo vitricota 10 x 20 x 1.8 cm m2 6recubrimiento mosaico 20 x 20 x 2.0 cm m2 5boquilla incluyendo cortes a 450 materiales vereficados m2 6sobreprecio por tendidos en fachadas m2 3
pisos firmes de concreto para pisos espesor de 8 a 10 cm m2 2acabado escobillado integral sobre firmes m2 5fino no integral acabado pulido m2 5armado con malla en pisos m2 4pisos ceramica sin firme m2 6pisos loseta 15 x 15 x 1.0 cm a 2 cm m2 6pisos loseta 10 x 20 x 1.0 cm a 2 cm m2 6pisos loseta 30 x 30 x 2.5 cm a 2.5 cm m2 6pisos mosaico 20 x 20 x 2 cm m2 5pisos mosaico terrazo sin junta metalica 50 x 50 x2.5 cm m 6zoclo mosaico 10 x 20 x 2.0 cm m 6zoclo loseta 10 x 15 x 30 a 40 cm m2 6
marterinados
marterinado fino sobre pisos m2 1marterinado fino sobre columnas m2 1marterinado fino sobre muros m2 1marterinado fino sobre trabes y losas m2 1
azoteasrelleno de tezontle en azoteas m3 1entortado sobre casco m2 5enladrillado y escobillado m2 5enladrillado aparente m2 5chaflanes de pedaceria 5
varioshechura de tarimas 50 x 100 cm Pza 3muro block vidrio 10 x 20 x 20 cm. Incluyendo refuerzo en juntas m2 6registro de 40 x 60 cm. Con profundidad promedio 1.25 m Pza 5tapa de registro de 40 x 60 cm Pza 5impermeabilizacion de cimientos m 2albañales 15 cm Ø tendido y junteo m 5colocacion de herreria m2 5impermeabilizacion azotea por capa m2 2
rendimiento aproximado por grupo. COSTOS UNITARIOS DEL TRABAJO PARA ANALISIS DE COSTOSTIPO A TIPO B GPO
150 m2 / Jor 3.87 2.68 24 m3 / Jor 39.96 27.53 342m3 / Jor 79.93 55.07 418 m3 / Jor 8.88 6.12 55 m3 / Jor 31.97 22.03 67 m3 / Jor 22.84 15.7335 m2 / Jor 4.57 3.1514 m2 / Jor 13.84 9.58 PARA PAGO DIRECTO DE AL OPERARIO3 m3 / Jor 115.29 80.58 GPO
10.17 Ton. / Jor 1509.18 1068 20.16 Ton. /Jor 1603.5 1134.75 30.13Ton./Jor 1973.54 1396.62 4
59.5 m2/Jor 36.59 25.89 67.5 m2/Jor 46.35 32.86 m2/Jor 57.94 418.5 m2/Jor 40.9 28.949m2/Jor 38.6 27.33
17m2/Jor 20.45 14.478.5m2/Jor 40.9 28.944m2/Jor 86.91 61.5410m2/Jor 34.76 24.610m2/Jor 34.76 24.615m/Jor 23.18 16.4
100 C/Jor 1.94 1.3440 C/Jor 4.84 3.3540 C/Jor 4.84 3.3530 C/Jor 6.46 4.47
1.50 m3 / Jor 129.18 89.420.85 m3 / Jor 227.96 157.80.95 m3 / Jor 203.97 141.19.080 m3 / Jor 242.21 167.6610 m3 / Jor 15.99 11.01300 m2 / Jor 0.53 0.37100 m2 / Jor 1.6 1.1
11 m2 / Jor 31.44 21.9810 m2 / Jor 34.59 24.188 m2 / Jor 43.23 30.226 m2 / Jor 57.64 40.29
40 m2 / Jor 8.65 6.04
10 m2 / Jor 34.59 24.189.5 m2 / Jor 36.41 25.459 m2 / Jor 38.43 26.868.5 m2 / Jor 40.69 28.4480 m2 / Jor 4.32 3.02
4.5 m2 / Jor 80.86 56.565.0 m2 / Jor 72.78 50.95.5 m2 / Jor 66.16 46.275.5 m2 / Jor 66.16 46.2755 m2 / Jor 6.62 4.63
30 m/Jor 11.53 8.0610 m/Jor 34.59 24.189.5 m/Jor 36.41 25.458 m/Jor 43.23 30.2225 m/Jor 13.83 6.97
19 m2 / Jor 18.2 12.7214 m2 / Jor 24.7 17.2711 m2 / Jor 31.44 21.9810 m2 / Jor 34.59 24.1823 m2 / Jor 15.04 10.514 m2 / Jor 90.47 63.634.5 m2 / Jor 80.86 56.565 m2 / Jor 72.78 50.95.5 m2 / Jor 66.16 46.274.5 m2 / Jor 80.86 56.565 m2 / Jor 72.78 50.99 m2 / Jor 38.43 26.8616 m2 / Jor 22.74 15.9143 m2 / Jor 8.08 5.72
10 m2 / Jor 19.38 13.4135 m2 / Jor 9.88 6.9118 m2 / Jor 19.21 13.4350 m2 / Jor 5.13 3.635 m2 / Jor 72.78 50.97 m2 / Jor 51.98 36.367 m2 / Jor 51.98 36.3613 m2 / Jor 27.99 19.5811 m2 / Jor 31.44 21.989.5 m2 / Jor 38.3 26.7918 m2 / Jor 20.22 14.1418 m2 / Jor 20.22 14.14
4 m2 / Jor 39.96 27.532 m2 / Jor 79.93 55.073 m2 / Jor 53.29 36.712 m2 / Jor 79.93 55.07
2 m3 / Jor 79.93 55.8520 m2 / Jor 17.29 12.0911m2 / Jor 31.44 21.987 m2 / Jor 49.41 34.5424 m2 / Jor 14.41 10.07
19 Pza/ Jor 18.3 12.953.5 m2 / Jor 103.97 72.712 Pza/ Jor 172.93 120.886 Pza/ Jor 57.64 40.2935 m/ Jor 5.54 3.8326 m/ Jor 13.3 9.37.5 m2 / Jor 46.12 32.2330 m2 / Jor 6.46 4.47
PARA ANALISIS DE COSTOSCOMPOSICION OPERACIONES 1er IMPORTE FSR 2do IMPORTE F.H.M F.M.0.10 cabo + 1.0 Peon 0.1 121.8 103.86 116.04 1.25 145.05 1.03 1.070.25 oficial + 1.0 Peon 0.25 147.2 103.86 140.66 1.25 175.825 1.03 1.071.0 Of.Carp. + 1.0 Ay.Carp. 136.95 115.4 252.35 1.25 315.4375 1.03 1.07.5 Of.Fierr. + 1.0 Ay.Fierr. 0.5 141.67 115.4 186.235 1.25 232.79375 1.03 1.071.0 oficial + 1.0 Peon 147.2 103.86 251.06 1.25 313.825 1.03 1.071.0 Of.Espec + 1.0 Peon 160.28 103.86 264.14 1.25 330.175 1.03 1.07
PARA PAGO DIRECTO DE AL OPERARIOCOMPOSICION OPERACIONES 1er IMPORTE FSR 2do IMPORTE F.H.M F.M.0.10 cabo + 1.0 Peon 0.1 95 78.6 88.1 1.25 110.125 1.03 1.070.25 oficial + 1.0 Peon 0.25 114.8 78.6 107.3 1.25 134.125 1.03 1.071.0 Of.Carp. + 1.0 Ay.Carp. 106.8 90 196.8 1.25 246 1.03 1.07.5 Of.Fierr. + 1.0 Ay.Fierr. 0.5 110.5 90 145.25 1.25 181.5625 1.03 1.071.0 oficial + 1.0 Peon 114.8 78.6 193.4 1.25 241.75 1.03 1.071.0 Of.Espec + 1.0 Peon 125 78.6 203.6 1.25 254.5 1.03 1.07
PARA ANALISIS DE COSTOSIMPORTE FINAL
149.40 159.86 181.10 193.78 324.90 347.64 239.78 256.56 323.24 345.87 340.08 363.89
PARA PAGO DIRECTO DE AL OPERARIOIMPORTE FINAL
113.43 121.37 138.15 147.82 253.38 271.12 187.01 200.10 249.00 266.43 262.14 280.48
Cuadro de analisis del factor de salario paecial de personal de campo(incluyen prestaciones, factor de salario real, factir de herramienta menor,factor maestro,PRE,FSR,FHM Y FM)
nivelaguinaldo
0.41% 4.11%peon 1000 6 166.666667 0.68333333 6.85ayudante de fierrero 1000 6 166.666667 0.68333333 6.85ayudante de carpintero 1000 6 166.666667 0.68333333 6.85cabo 1200 6 200 0.82 8.22velador 1000 6 166.666667 0.68333333 6.85bodegero 1000 6 166.666667 0.68333333 6.85oficial de carpimtero 1500 6 250 1.025 10.275oficial de fierrero 1500 6 250 1.025 10.275oficial de albañileria 1500 6 250 1.025 10.275oficial especializado 1800 6 300 1.23 12.33plomero 1500 6 250 1.025 10.275electrico 1500 6 250 1.025 10.275ayudante de electricista y plomero 1000 6 166.666667 0.68333333 6.85
pago semanal
jornada tiempo
semanal
SDB pago directo al
trabajador
prima vacacional
Cuadro de analisis del factor de salario paecial de personal de campo(incluyen prestaciones, factor de salario real, factir de herramienta menor,factor maestro,PRE,FSR,FHM Y FM) FSR ACTIVIDADES DEPENDIENTES
SUMAIMSS ISPR IMSS infonadit
FSR15.99% 1% 1% 5%
174.2 27.85458 1.742 1.66666667 8.33333333 39.59658 213.79658 1.25174.2 27.85458 1.742 1.66666667 8.33333333 39.59658 213.79658 1.25174.2 27.85458 1.742 1.66666667 8.33333333 39.59658 213.79658 1.25
209.04 33.425496 2.0904 2 10 47.515896 256.555896 1.25174.2 27.85458 1.742 1.66666667 8.33333333 39.59658 213.79658 1.25174.2 27.85458 1.742 1.66666667 8.33333333 39.59658 213.79658 1.25261.3 41.78187 2.613 2.5 12.5 59.39487 320.69487 1.25261.3 41.78187 2.613 2.5 12.5 59.39487 320.69487 1.25261.3 41.78187 2.613 2.5 12.5 59.39487 320.69487 1.25
313.56 50.138244 3.1356 3 15 71.273844 384.833844 1.25261.3 41.78187 2.613 2.5 12.5 59.39487 320.69487 1.25261.3 41.78187 2.613 2.5 12.5 59.39487 320.69487 1.25174.2 27.85458 1.742 1.66666667 8.33333333 39.59658 213.79658 1.25
suma de prestaciones
analisis de costo total
FSR ACTIVIDADES DEPENDIENTES
FHM FM
3% 7%267.245725 8.01737175 18.7072008 293.970298267.245725 8.01737175 18.7072008 293.970298267.245725 8.01737175 18.7072008 293.970298
320.69487 9.6208461 22.4486409 352.764357267.245725 8.01737175 18.7072008 293.970298267.245725 8.01737175 18.7072008 293.970298400.868588 12.0260576 28.0608011 440.955446400.868588 12.0260576 28.0608011 440.955446400.868588 12.0260576 28.0608011 440.955446481.042305 14.4312691 33.6729614 529.146536400.868588 12.0260576 28.0608011 440.955446400.868588 12.0260576 28.0608011 440.955446267.245725 8.01737175 18.7072008 293.970298
segundo total
importe total del
analisis de costo
dependiente
Cuadro de analisis del factor de salario paecial de personal de campo(incluyen prestaciones, factor de salario real, factir de herramienta menor,factor maestro,PRE,FSR,FHM Y FM)
nivel0.41%
peon 1000 6 166.6666666667 0.6833333333ayudante de fierrero 1000 6 166.6666666667 0.6833333333ayudante de carpintero 1000 6 166.6666666667 0.6833333333cabo 1200 6 200 0.82velador 1000 6 166.6666666667 0.6833333333bodegero 1000 6 166.6666666667 0.6833333333oficial de carpimtero 1500 6 250 1.025oficial de fierrero 1500 6 250 1.025oficial de albañileria 1500 6 250 1.025oficial especializado 1800 6 300 1.23plomero 1500 6 250 1.025electrico 1500 6 250 1.025ayudante de electricista y plomero 1000 6 166.6666666667 0.6833333333
pago semanal
jornada tiempo semanal
SDB pago directo al trabajador
prima vacacional
Cuadro de analisis del factor de salario paecial de personal de campo(incluyen prestaciones, factor de salario real, factir de herramienta menor,factor maestro,PRE,FSR,FHM Y FM) FHM, FM pago independiente
aguinaldo
SUMA
IMSS ISPR IMSS infonadit
FSR4.11% 15.99% 1% 1% 5%
6.85 174.2 27.8546 1.742 1.66666667 8.3333333333 39.59658 213.79658 1.256.85 174.2 27.8546 1.742 1.66666667 8.3333333333 39.59658 213.79658 1.256.85 174.2 27.8546 1.742 1.66666667 8.3333333333 39.59658 213.79658 1.258.22 209.04 33.4255 2.0904 2 10 47.515896 256.555896 1.256.85 174.2 27.8546 1.742 1.66666667 8.3333333333 39.59658 213.79658 1.256.85 174.2 27.8546 1.742 1.66666667 8.3333333333 39.59658 213.79658 1.25
10.275 261.3 41.7819 2.613 2.5 12.5 59.39487 320.69487 1.2510.275 261.3 41.7819 2.613 2.5 12.5 59.39487 320.69487 1.2510.275 261.3 41.7819 2.613 2.5 12.5 59.39487 320.69487 1.25
12.33 313.56 50.1382 3.1356 3 15 71.273844 384.833844 1.2510.275 261.3 41.7819 2.613 2.5 12.5 59.39487 320.69487 1.2510.275 261.3 41.7819 2.613 2.5 12.5 59.39487 320.69487 1.25
6.85 174.2 27.8546 1.742 1.66666667 8.3333333333 39.59658 213.79658 1.25
suma de prestaciones
analisis de costo total
FHM, FM pago independiente
FHM FM
3% 7%
267.2457 8.01737 18.7072 26.7245725267.2457 8.01737 18.7072 26.7245725267.2457 8.01737 18.7072 26.7245725320.6949 9.62085 22.4486 32.069487267.2457 8.01737 18.7072 26.7245725267.2457 8.01737 18.7072 26.7245725400.8686 12.0261 28.0608 40.08685875400.8686 12.0261 28.0608 40.08685875400.8686 12.0261 28.0608 40.08685875481.0423 14.4313 33.673 48.1042305400.8686 12.0261 28.0608 40.08685875400.8686 12.0261 28.0608 40.08685875267.2457 8.01737 18.7072 26.7245725
segundo total
importe total del analisis de costo
dependiente
tabla para analisis de costos ( incluye integrado por prestaciones,FSR,FHM,FM)
valor nombre total valores nombre sm total
0.1 cabo 256.56 25.66 1 peon 213.80 213.80 0.25 oficial albañileria 320.69 80.17 1 peon 213.80 213.80
1 oficial de carpinteria 320.69 320.69 1 ayudante de carpintero 213.80 213.80 0.5 oficial de fierrero 320.69 160.35 1 ayudante de fierrero 213.80 213.80
1 oficial albañileria 320.69 320.69 1 peon 213.80 213.80 1 oficial especializado 384.83 384.83 1 peon 213.80 213.80
tabla para analisis de costos ( incluye integrado por prestaciones,FSR,FHM,FM)
valor nombre total valores nombre sm total
0.1 cabo 200.00 20 1 peon 166.67 166.67 0.25 oficial albañileria 250.00 62.5 1 peon 166.67 166.67
1 oficial de carpinteria 250.00 250 1 ayudante de carpintero 166.67 166.67 0.5 oficial de fierrero 250.00 125 1 ayudante de fierrero 166.67 166.67
1 oficial albañileria 250.00 250 1 peon 166.67 166.67 1 oficial especializado 300.00 300 1 peon 166.67 166.67
valor descripcion valor descripcion1.1 cabo 1 peon
0.25 oficial albañileria 1 peon
1 oficial de carpinteria 1
0.5 oficial de fierrero 11 oficial albañileria 1 peon1 oficial especializado 1 peon
sm salario minimo
sm salario minimo
ayudante de carpintero
ayudante de fierrero
tabla para analisis de costos ( incluye integrado por prestaciones,FSR,FHM,FM)
1er sub total FSR 2do sub total FHM FM importe total3% 7%
5,485.08 1.25 6,856.35 205.69 479.94 7,541.98 17,140.87 1.25 21,426.08 642.78 1,499.83 23,568.69 68,563.47 1.25 85,704.33 2,571.13 5,999.30 94,274.77 34,281.73 1.25 42,852.17 1,285.56 2,999.65 47,137.38 68,563.47 1.25 85,704.33 2,571.13 5,999.30 94,274.77 82,276.16 1.25 102,845.20 3,085.36 7,199.16 113,129.72
tabla para analisis de costos ( incluye integrado por prestaciones,FSR,FHM,FM)
1er sub total FSR 2do sub total FHM FM importe total3% 7%
186.67 1.25 233.33 7.00 16.33 23.33 87.11 110.45 229.17 1.25 286.46 8.59 20.05 28.65 98.99 127.64 416.67 1.25 520.83 15.62 36.46 52.08 98.99 151.07 291.67 1.25 364.58 10.94 25.52 36.46 98.99 135.45 416.67 1.25 520.83 15.62 36.46 52.08 98.99 151.07 466.67 1.25 583.33 17.50 40.83 58.33 110.87 169.20
suma de prestaciones
pago total de separado
tabla para analisis de costos ( incluye integrado por prestaciones,FSR,FHM,FM)
prestamo 1 prestamo 247.52 39.6059.39 39.6059.39 39.6059.39 39.6059.39 39.6071.27 39.60
concepto m2 un cant pu importemadera de estacascalhidra en trazo 25 600 kg 0.04166667 $ 30.00 $ 1.25 alqiler de instruento
cimentacinesconcepto m2 un cant pu importedepreciacion de la pala
CONCEPTO Un. Gpo.
Preliminares y cimentacion. Limpiezay trazo m2 1Excavacion en tierra hasta de 2.0M de profundidad m3 1Excavacion en tepetate blando hasta de 2.0M de profundidad m3 1Traspaleo hasta2 m m3 1Acarreo concarretilla a 20.00 m. maximo m3 1rellenos por capas, compactadas con pison de mano m3 1compactacion de cepas con pison de mano m2 1Plantillas entre .07 y.10 m m2 2Cimientos de piedra braza m3 5Habilitado y armado de fierro e refuerzoa) en cimentacion Ton. 4b) en estructura Ton. 4
Ton. 4Cimbra y desimbrar , acabado no aparente.a)en cimientos m2 3b) en columnas rectangulares m2 3c)en columnas circulares m2 3d) en trabes m2 3e)en losas m2 3Hechura de cimbraa)en cimientos m2 3b) en columnas rectangulares m2 3c)en columnas circulares m2 3d) en trabes m2 3e)en losas m2 3f)cimbrar y desimbrar en sonotubo m 3losas reticuladascolocacion block hasta 20x40x40cm caja 2colocacion block hasta 35x60x60cm caja 2entrepiso reticular celulado linea menor caja 2entrepiso reticular celulado linea mayor caja 2
colados(no incluyendo la fabricacion del concreto)a)en cimientos m3 2b) en columnas y muros m3 2c)en trbes y muros m3 2d)en losas reticuladas m3 2e)curado de concreto con agua en superficies horizontales m3 1f)curado de concreto con agua m2 1g)curado de concreto con agua en superficies verticales m2 1
muros de tabique comun o ligero no aparentea) de 0.07m de espesor m2 5b) de 0.14m de espesor m2 5c) de 0.21m de espesor m2 5d)de 0.28m de espesor m2 5
Habilitando y armando de alambron de 1/4 y 5/16 "Ø
e) sobre precio por cara aparente m2 5muros de block tipo piramide
a)de 0.10 m de espesor m2 5b) de 0.12 m de espesor m2 5c) de 0.15 m de espesor m2 5d) de 0.20 m de espesor m2 5e) sobre precio por cara aparente m2 5
muro de block extruidoa) de 5x10x15 en 10 cm espesor m2 6b) de 6x10x20 en 10 cm espesor m2 6c) de 10x10x20 en 10 cm espesor m2 6d) de 10x15x20 en 15 cm espesor m2 6e) sobre precio por cara aparente m2 6
castillos y cadenascastillo centro de block 1Ø (3/8") 9.5mm m 5castillos y cadenas 15 x 15 con 4 Ø (3/8") 9.5mm m 5castillos y cadenas 15 x 20 con 4 Ø (3/8") 9.5mm m 5castillos y cadenas 15 x 30 con 4 Ø (3/8") 9.5mm m 5sobre cara aparente castillos y cadenas m 5
recubrimientosrepellados de mezcla m2 5aplanados de mezcla (rostreados) m2 5aplanados finos de mescla m2 5aplanados pulidos de cemento llana m2 5confitillo sobre aplanado m2 5recubrimiento de ceramica o mosaico veneciano incle repellado m2 6recubrimiento cintilla 5.5 x 22 x 1.0 a 6.0 x 24 x 1.0 cm m2 6recubrimiento fachaleta 10 x 20 x 1 a 11 x 22 x 1 cm m2 6recubrimiento azulejo m2 6recubrimiento tipo vitricota 6 x 20 x 18 cm m2 6recubrimiento tipo vitricota 10 x 20 x 1.8 cm m2 6recubrimiento mosaico 20 x 20 x 2.0 cm m2 5boquilla incluyendo cortes a 450 materiales vereficados m2 6sobreprecio por tendidos en fachadas m2 3
pisos firmes de concreto para pisos espesor de 8 a 10 cm m2 2acabado escobillado integral sobre firmes m2 5fino no integral acabado pulido m2 5armado con malla en pisos m2 4pisos ceramica sin firme m2 6pisos loseta 15 x 15 x 1.0 cm a 2 cm m2 6pisos loseta 10 x 20 x 1.0 cm a 2 cm m2 6pisos loseta 30 x 30 x 2.5 cm a 2.5 cm m2 6pisos mosaico 20 x 20 x 2 cm m2 5pisos mosaico terrazo sin junta metalica 50 x 50 x2.5 cm m 6zoclo mosaico 10 x 20 x 2.0 cm m 6zoclo loseta 10 x 15 x 30 a 40 cm m2 6
marterinados
marterinado fino sobre pisos m2 1marterinado fino sobre columnas m2 1marterinado fino sobre muros m2 1marterinado fino sobre trabes y losas m2 1
azoteasrelleno de tezontle en azoteas m3 1entortado sobre casco m2 5enladrillado y escobillado m2 5enladrillado aparente m2 5chaflanes de pedaceria 5
varioshechura de tarimas 50 x 100 cm Pza 3muro block vidrio 10 x 20 x 20 cm. Incluyendo refuerzo en juntas m2 6registro de 40 x 60 cm. Con profundidad promedio 1.25 m Pza 5tapa de registro de 40 x 60 cm Pza 5impermeabilizacion de cimientos m 2albañales 15 cm Ø tendido y junteo m 5colocacion de herreria m2 5impermeabilizacion azotea por capa m2 2
TIPO A TIPO B
50 m2 / Jor 3.87 2.684 m3 / Jor 39.96 27.5342m3 / Jor 79.93 55.0718 m3 / Jor 8.88 6.125 m3 / Jor 31.97 22.037 m3 / Jor 22.84 15.7335 m2 / Jor 4.57 3.1514 m2 / Jor 13.84 9.583 m3 / Jor 115.29 80.58
0.17 Ton. / Jor 1509.18 10680.16 Ton. /Jor 1603.5 1134.750.13Ton./Jor 1973.54 1396.62
9.5 m2/Jor 36.59 25.897.5 m2/Jor 46.35 32.86 m2/Jor 57.94 418.5 m2/Jor 40.9 28.949m2/Jor 38.6 27.33
17m2/Jor 20.45 14.478.5m2/Jor 40.9 28.944m2/Jor 86.91 61.5410m2/Jor 34.76 24.610m2/Jor 34.76 24.615m/Jor 23.18 16.4
100 C/Jor 1.94 1.3440 C/Jor 4.84 3.3540 C/Jor 4.84 3.3530 C/Jor 6.46 4.47
1.50 m3 / Jor 129.18 89.420.85 m3 / Jor 227.96 157.80.95 m3 / Jor 203.97 141.19.080 m3 / Jor 242.21 167.6610 m3 / Jor 15.99 11.01300 m2 / Jor 0.53 0.37100 m2 / Jor 1.6 1.1
11 m2 / Jor 31.44 21.9810 m2 / Jor 34.59 24.188 m2 / Jor 43.23 30.226 m2 / Jor 57.64 40.29
rendimiento aproximado por grupo.
COSTOS UNITARIOS DEL TRABAJO
40 m2 / Jor 8.65 6.04
10 m2 / Jor 34.59 24.189.5 m2 / Jor 36.41 25.459 m2 / Jor 38.43 26.868.5 m2 / Jor 40.69 28.4480 m2 / Jor 4.32 3.02
4.5 m2 / Jor 80.86 56.565.0 m2 / Jor 72.78 50.95.5 m2 / Jor 66.16 46.275.5 m2 / Jor 66.16 46.2755 m2 / Jor 6.62 4.63
30 m/Jor 11.53 8.0610 m/Jor 34.59 24.189.5 m/Jor 36.41 25.458 m/Jor 43.23 30.2225 m/Jor 13.83 6.97
19 m2 / Jor 18.2 12.7214 m2 / Jor 24.7 17.2711 m2 / Jor 31.44 21.9810 m2 / Jor 34.59 24.1823 m2 / Jor 15.04 10.514 m2 / Jor 90.47 63.634.5 m2 / Jor 80.86 56.565 m2 / Jor 72.78 50.95.5 m2 / Jor 66.16 46.274.5 m2 / Jor 80.86 56.565 m2 / Jor 72.78 50.99 m2 / Jor 38.43 26.8616 m2 / Jor 22.74 15.9143 m2 / Jor 8.08 5.72
10 m2 / Jor 19.38 13.4135 m2 / Jor 9.88 6.9118 m2 / Jor 19.21 13.4350 m2 / Jor 5.13 3.635 m2 / Jor 72.78 50.97 m2 / Jor 51.98 36.367 m2 / Jor 51.98 36.3613 m2 / Jor 27.99 19.5811 m2 / Jor 31.44 21.989.5 m2 / Jor 38.3 26.7918 m2 / Jor 20.22 14.1418 m2 / Jor 20.22 14.14
4 m2 / Jor 39.96 27.532 m2 / Jor 79.93 55.073 m2 / Jor 53.29 36.712 m2 / Jor 79.93 55.07
2 m3 / Jor 79.93 55.8520 m2 / Jor 17.29 12.0911m2 / Jor 31.44 21.987 m2 / Jor 49.41 34.5424 m2 / Jor 14.41 10.07
19 Pza/ Jor 18.3 12.953.5 m2 / Jor 103.97 72.712 Pza/ Jor 172.93 120.886 Pza/ Jor 57.64 40.2935 m/ Jor 5.54 3.8326 m/ Jor 13.3 9.37.5 m2 / Jor 46.12 32.2330 m2 / Jor 6.46 4.47