_presupuesto Sistema General de Hidrantes 02 Circuitos

1
Subpresupuesto 007 SISTEMA GENERAL DE HIDRANTES (02 Circuitos; 02 Lagunas) 1° etapa Item Descripción Und. Metrado Precio S/. Parcial S/. OBRAS PRELIMINARES 892.56 LIMPIEZA DE TERRENO MANUAL m2 177.73 2.50 444.33 TRAZO Y REPLANTEO m2 177.73 2.52 448.24 MOVIMIENTO DE TIERRAS 54,348.79 EXCAVACION m3 772.00 39.19 30,257.77 0.00 RELLENO CON MATERIAL DE PRESTAMO MANUAL m3 100.00 31.95 3,195.00 0.00 ELIMINACION CON TRANSPORTE (CARGUIO A MANO) REN.=25 M3/DIA m3 20.00 65.20 1,304.00 0.00 RELLENO CON MATERIAL PROPIO m3 457.33 42.84 19,592.02 CONCRETO SIMPLE 1,567.01 DADOS DE CONCRETO .40x.40x.40 HIDRANTES und 25.39 26.64 676.29 0.00 DADOS DE CONCRETO .30x.20x.30 HIDRANTES und 44.67 19.94 890.72 BOMBA DE HIDRANTES 17,347.94 BOMBA DE IMPULSION 8.5 HP UND 2.00 8,673.97 17,347.94 HIDRANTES 14,432.90 HIDRANTES UND 16.04 899.81 14,432.90 TUBERIA 39,021.85 TUBERIA PVC D=3" m 2,848.31 13.70 39,021.85 ACCESORIOS VARIOS 3,743.96 ACCESORIOS Fº Fº und 0.67 5,588.00 3,743.96 COSTO DIRECTO 131,355.00

description

_presupuesto Sistema General de Hidrantes 02 Circuitos

Transcript of _presupuesto Sistema General de Hidrantes 02 Circuitos

Subpresupuesto 007 SISTEMA GENERAL DE HIDRANTES (02 Circuitos; 02 Lagunas) 1° etapa

Item Descripción Und. Metrado Precio S/. Parcial S/.

OBRAS PRELIMINARES 892.56

LIMPIEZA DE TERRENO MANUAL m2 177.73 2.50 444.33

TRAZO Y REPLANTEO m2 177.73 2.52 448.24

MOVIMIENTO DE TIERRAS 54,348.79

EXCAVACION m3 772.00 39.19 30,257.770.00 RELLENO CON MATERIAL DE PRESTAMO MANUAL m3 100.00 31.95 3,195.000.00 ELIMINACION CON TRANSPORTE (CARGUIO A MANO) REN.=25 M3/DIA m3 20.00 65.20 1,304.000.00 RELLENO CON MATERIAL PROPIO m3 457.33 42.84 19,592.02

CONCRETO SIMPLE 1,567.01

DADOS DE CONCRETO .40x.40x.40 HIDRANTES und 25.39 26.64 676.290.00 DADOS DE CONCRETO .30x.20x.30 HIDRANTES und 44.67 19.94 890.72

BOMBA DE HIDRANTES 17,347.94

BOMBA DE IMPULSION 8.5 HP UND 2.00 8,673.97 17,347.94

HIDRANTES 14,432.90

HIDRANTES UND 16.04 899.81 14,432.90

TUBERIA 39,021.85

TUBERIA PVC D=3" m 2,848.31 13.70 39,021.85

ACCESORIOS VARIOS 3,743.96

ACCESORIOS Fº Fº und 0.67 5,588.00 3,743.96

COSTO DIRECTO 131,355.00