PRECIO PARTICULAR DE INSUMOS
OBRA : HABILITACION DEL CONDOMINIO "LA ALBORADA DE SUBTANJALLA"
DISTRITO DE SUBTANJALLA - PROVINCIA DE ICA - REGION ICA
CLIENTE: MUNICIPALIDAD DISTRITAL DE SUBTANJALLA
LUGAR: SUBTANJALLA - ICA - ICA
I.U. RECURSO UNIDAD CANTIDAD
MANO DE OBRA
47 CAPATAZ hh47 OFICIAL hh47 OPERARIO hh47 PEON hh47 TOPOGRAFO hh
TOTAL S/. 5,192.00MATERIALES
01 ACEITE MOTOR SE-SAE-SE LOW 30 gal 127.9039 AGUA m³ 160.2402 FIERRO LISO kg 14920.0804 AGREGADO FINO m³ 225.9230 CAL HIDRAULICA ( BOLSA = 20 KGS) kg 843.0421 CEMENTO PORTLAND TIPO I bol 5466.3439 CORDEL ml 9861.0003 FIERRO CORRUGADO kg 26875.6834 GASOLINA 84 OCTANOS gal 203.9753 GRASA gal 1.6538 HORMIGON m³ 601.1017 BLOQUE Y LADRILLO und 39310.0043 MADERA PINO OREGON BRUTO ESC. p² 12196.1505 AGREGADO GRUESO m³ 419.1944 TRIPLAY DE 4' x 8' x 4 mm pln 63.00
EQUIPOS Y HERRAMIENTAS
37 HERRAMIENTAS MANUALES %mo48 MEZCLADORA 9-11 P³ 20 HP hm 862.6449 EQUIPO IMPORTADO hm 362.30
SUBCONTRATO
GIGANTOGRAFIA 3.60 x 4.20 m und 1.00INSTALACIONES SANITARIAS glb 1.00INST. DE PUNTO ELECTRICO glb 1.00
TOTAL PRESUPUESTO
SON: UN MILLON SETECIENTOS OCHENTA Y TRES MIL CIENTO CINCUENTA Y OCHO CON 32/100 NUEVOS SOLES
PRECIO PARTICULAR DE INSUMOS
HABILITACION DEL CONDOMINIO "LA ALBORADA DE SUBTANJALLA"
DISTRITO DE SUBTANJALLA - PROVINCIA DE ICA - REGION ICA
PRECIO PARCIAL
MANO DE OBRA
S/. 20.19S/. 18.36S/. 15.39S/. 13.89S/. 15.39S/. 83.22 S/. 432,120.74
MATERIALES
S/. 53.68 S/. 6,865.50S/. 8.00 S/. 1,281.93S/. 4.00 S/. 59,680.30
S/. 35.00 S/. 7,907.34S/. 9.90 S/. 8,346.06
S/. 20.50 S/. 112,059.95S/. 0.13 S/. 1,281.93S/. 2.81 S/. 75,520.67
S/. 10.15 S/. 2,070.28S/. 79.38 S/. 130.62S/. 25.00 S/. 15,027.44S/. 2.05 S/. 80,585.49
S/. 35.83 S/. 436,988.00S/. 45.00 S/. 18,863.64S/. 26.90 S/. 1,694.70
TOTAL S/. 828,303.85EQUIPOS Y HERRAMIENTAS
S/. 21,640.62S/. 7.50 S/. 6,469.79S/. 6.25 S/. 2,264.35TOTAL S/. 30,374.76
SUBCONTRATO
S/. 200.00 S/. 200.00S/. 500.00 S/. 500.00S/. 500.00 S/. 500.00
TOTAL S/. 1,200.00
TOTAL PRESUPUESTO S/. 1,783,158.32SON: UN MILLON SETECIENTOS OCHENTA Y TRES MIL CIENTO CINCUENTA Y OCHO CON 32/100 NUEVOS SOLES