TERMINOS PROBABILISTICOS ACTIVIDAD DEPENDE A B A C B D B E A F DE G CF H E I GH To= TIEMPO OBTIMISTA Tm= TIEMPO MEDIO Tp= TIEMPO PESIMISTA Te= TIEMPO ESPERADO FORMULAS: Te= (To+4Tm+Tp)/6 Ht= Lf-(Ei+D) Hl= Ef-(Ei+D) Hi= Ef-(Li+D) E = ACT TEMPRANA (valores acumulados) L = ACT TARDIA 1 0

description

DFGVDF

Transcript of Libro1

Hoja1TERMINOS PROBABILISTICOSACTIVIDADDEPENDE (To) (Tm)(Tp)(Te)(Ei)(Ef)(Li)(Lf)(Ht)(Hl)(Hi)(Rc)A13530303000VBA13533637100FCB456561171760-1FDB147461071110-1FEA7898311311000VFDE468611171117000VGCF456517221722000VHE7911911201122200FIGH135322252225000VTo= TIEMPO OBTIMISTATm= TIEMPO MEDIOTp= TIEMPO PESIMISTATe= TIEMPO ESPERADOFORMULAS:Te= (To+4Tm+Tp)/6

Ht= Lf-(Ei+D)

Hl= Ef-(Ei+D)

Hi= Ef-(Li+D)

E = ACT TEMPRANA (valores acumulados)

L = ACT TARDIA

1A2303B3C456113D4510E6118F7617G8522H9920I103251773111117222522