Empresa Contratista Consorcio Caxamarca
Fecha de Firma de Contrato 3/13/2013
Aprobacin del Expediente Tecnico 1/29/2014
Fecha de Inicio de Obra 2/13/2014
Plazo de Elaboracin de Expediente Tcnico 120
Plazo de Ejecucin de Obra 420
Fecha de Culminacin de Obra Inicial 4/8/2015
Ampliacin de Plazo Total 450
Monto Declarado Viable S/. 76,230,916.00
Monto de Expediente Tcnico S/. 88,657,387.37
Monto de Contrato de Ejecucin S/. 84,483,566.60
Nuevo Monto Primera Vericatoria S/. 115,956,177.26
Monto Adicional Primera Verificatoria S/. 27,298,789.89
Nuevo Monto Segunda Verificatoria S/. 140,865,661.76
Monto Adicional Segunda Verificatoria S/. 24,909,484.50
-
das calendarios
dias calendarios
dias calendarios 33
Viablidad del 01/03/2010 18
Registrado el 29/01/2014
Contrato 01-2013-GR.CAJ/PROREGION
Verificado el 02/06/2015
Para equipamiento 7/2/2016
Nuevo monto a registrar
Para cubrir brecha de equipamiento
Elaboracin de Expediente Tcnico mas ejecucin de ObraResolucin Directoral Ejecutiva N 013-2014 - G.R.CAJ/PROREGION
-
990
540
120
870
-
Ao Pia. Pim. Acum. Dev. Acum.
2010 3,718,564 9,509,139 4,785,330.36
2011 4,978,511 17,385,645 12,108,278.10
2012 1,418,171 2,572,062 2,408,124.93
2013 0 1,123,305 366,583.68
2014 0 1,487,549 0
2015 0 330,000 0
19,668,317.07
-
Devengado Mensualizado
Ene Feb Mar Abr May Jun
0 0 18,062 16,500 0 0
37,965.42 2,609,964.08 1,440,360.29 30,240.48 1,232,577.05 933,140.63
0 540,681.40 72,934.74 705,270.52 10,347.41 115,680.54
0 0 0 0 38,620.45 0
0 0 0 0 0 0
0 0 0 0 0 0
-
Devengado Mensualizado
Jul Ago Set Oct Nov Dic
7,155.71 0 977,762.28 2,496,817.92 37,984.34 1,231,048.11
227,592.87 689,765.24 460,020.63 2,118,597.71 395,392.09 1,932,661.61
119,570.60 0 0 528,366.38 162,891.73 152,381.61
144,580.63 52,683.78 0 4,240.83 0 126,457.99
0 0 0 0 0 0
0 0 0 0 0 0
-
Certificacin
0 0
0 0
2,408,124.93 2,408,124.93
366,583.68 366,583.68
0 0
0 0
Compromiso Anual