CRONOGRAMA DE EJECUCION DEL PROYECTO DESCRIPCION MES 1 MES 2 MES 3 MES 4 MES 5 MES 6 MES 7 MES 8 MES 9 MES 10 MES 11 MES 12 01 OBRAS PROVISIONALES ### 7,075.52 02 OBRAS PRELIMINARES ### 29,901.36 03 REPOSICION DE INSTALACIONES DE AGUA Y DESAGUE 04 INSTALACIONES DE AGUA ### 47,005.86 05 INSTALACIONES DE DESAGUE ### 89,132.32 06 BUZONES DE CONCRETO ### 19,018.38 07 MUROS DE CONTENCION ### 491,043.76 491,043.76 491,043.76 08 MUROS CON SISTEMA TERRAMESH ### 498,714.28 498,714.28 09 VIAS VEHICULARES 10 MOVIMIENTO DE TIERRAS ### 252,971.82 11 PAVIMENTO 12 MEJORAMIENTO DE LA SUBRASANTE 50 CM ### 306,543.71 13 BASE DE 20 CM DE ESPESOR ### 210,601.32 14 LOSA DE RODADURA ### 239,996.56 239,996.56 239,996.56 239,996.56 15 DRENAJE PLUVIAL 16 CANAL DE EVACUACION DE AGUAS PLUVIALES ### 22,867.11 17 SUMIDERO TRANSVERSAL ### 21,563.79 18 TUBERIA PARA AGUAS PLUVIALES ### 22,837.42 19 VIAS PEATONALES 20 SARDINELES ### 12,064.89 12,064.89 21 VEREDAS ### 34,864.05 34,864.05 22 TRABAJOS COMPLEMENTARIOS 23 SEÑALIZACION HORIZONTAL ### 2,834.95 24 PRUEBAS DE CONTROL DE CALIDAD ### 2,150.00 2,150.00 25 SEGURIDAD Y SALUD EN LA OBRA ### 4,029.00 26 LIMPIEZA DE OBRA ### 7,112.40 COSTO DIRECTO 41,005.88 155,156.56 491,043.76 491,043.76 1,242,729.86 805,257.99 277,869.64 252,061.45 254,211.45 277,010.60 274,860.60 9,947.35 GASTOS GENERALES 4.93% 2,022.49 7,652.64 24,219.30 24,219.30 61,294.01 39,716.99 13,705.11 12,432.19 12,538.24 13,662.74 13,556.69 490.62 GASTOS DE SUPERVISION 1.36% 556.38 2,105.19 6,662.57 6,662.57 16,861.58 10,925.88 3,770.18 3,420.01 3,449.19 3,758.53 3,729.36 134.97 GASTOS DE LIQUIDACION 0.36% 16,626.32 EXPEDIENTE TECNICO 0.52% 23,900.00 PROGRAMACION PORCENTUAL 1.38% 3.37% 10.65% 10.65% 26.96% 17.47% 6.03% 5.47% 5.51% 6.01% 5.96% 0.56% TOTAL PRESUPUESTADO 67,484.75 164,914.39 521,925.62 521,925.62 ### 855,900.86 295,344.93 267,913.65 270,198.87 294,431.87 292,146.65 27,199.26 PROYECTO: “MEJORAMIENTO DE LA TRANSITABILIDAD VEHICULAR Y PEATONAL DE LA VIA PRINCIPAL, CALLE C, CALLE ENTRE LAS MANZANAS K y L, y CALLE E MANZANAS M, N y O DEL ASENTAMIENTO HUMANO LA ESTRELLA 2DA ETAPA DEL DISTRITO DE SANTIAGO – CUSCO - CUSCO”

description

ds

Transcript of CRONOGRAMA DE GASTOS.xls

Page 1: CRONOGRAMA DE GASTOS.xls

CRONOGRAMA DE EJECUCION DEL PROYECTO

DESCRIPCION MES 1 MES 2 MES 3 MES 4 MES 5 MES 6 MES 7 MES 8 MES 9 MES 10 MES 11 MES 12 TOTAL01 OBRAS PROVISIONALES 7,075.52 7,075.52 7,075.52

02 OBRAS PRELIMINARES 29,901.36 29,901.36 29,901.36

03 REPOSICION DE INSTALACIONES DE AGUA Y DESAGUE

04 INSTALACIONES DE AGUA 47,005.86 47,005.86 47,005.86

05 INSTALACIONES DE DESAGUE 89,132.32 89,132.32 89,132.32

06 BUZONES DE CONCRETO 19,018.38 19,018.38 19,018.38

07 MUROS DE CONTENCION ### 491,043.76 491,043.76 491,043.76 1,473,131.28

08 MUROS CON SISTEMA TERRAMESH ### 498,714.28 498,714.28 997,428.56

09 VIAS VEHICULARES

10 MOVIMIENTO DE TIERRAS ### 252,971.82 252,971.82

11 PAVIMENTO

12 MEJORAMIENTO DE LA SUBRASANTE 50 CM DE ES ### 306,543.71 306,543.71

13 BASE DE 20 CM DE ESPESOR ### 210,601.32 210,601.32

14 LOSA DE RODADURA ### 239,996.56 239,996.56 239,996.56 239,996.56 959,986.23

15 DRENAJE PLUVIAL

16 CANAL DE EVACUACION DE AGUAS PLUVIALES 22,867.11 22,867.11 22,867.11

17 SUMIDERO TRANSVERSAL 21,563.79 21,563.79 21,563.79

18 TUBERIA PARA AGUAS PLUVIALES 22,837.42 22,837.42 22,837.42

19 VIAS PEATONALES

20 SARDINELES 24,129.78 12,064.89 12,064.89 24,129.78

21 VEREDAS 69,728.09 34,864.05 34,864.05 69,728.09

22 TRABAJOS COMPLEMENTARIOS

23 SEÑALIZACION HORIZONTAL 2,834.95 2,834.95 2,834.95

24 PRUEBAS DE CONTROL DE CALIDAD 4,300.00 2,150.00 2,150.00 4,300.00

25 SEGURIDAD Y SALUD EN LA OBRA 4,029.00 4,029.00 4,029.00

26 LIMPIEZA DE OBRA 7,112.40 7,112.40 7,112.40

COSTO DIRECTO 41,005.88 155,156.56 491,043.76 491,043.76 1,242,729.86 805,257.99 277,869.64 252,061.45 254,211.45 277,010.60 274,860.60 9,947.35 4,572,198.90

GASTOS GENERALES 4.93% 2,022.49 7,652.64 24,219.30 24,219.30 61,294.01 39,716.99 13,705.11 12,432.19 12,538.24 13,662.74 13,556.69 490.62 225,510.32

GASTOS DE SUPERVISION 1.36% 556.38 2,105.19 6,662.57 6,662.57 16,861.58 10,925.88 3,770.18 3,420.01 3,449.19 3,758.53 3,729.36 134.97 62,036.40

GASTOS DE LIQUIDACION 0.36% 16,626.32 16,626.32

EXPEDIENTE TECNICO 0.52% 23,900.00 23,900.00

PROGRAMACION PORCENTUAL 1.38% 3.37% 10.65% 10.65% 26.96% 17.47% 6.03% 5.47% 5.51% 6.01% 5.96% 0.56%

TOTAL PRESUPUESTADO 67,484.75 164,914.39 521,925.62 521,925.62 1,320,885.45 855,900.86 295,344.93 267,913.65 270,198.87 294,431.87 292,146.65 27,199.26 4,900,271.94

PROYECTO: “MEJORAMIENTO DE LA TRANSITABILIDAD VEHICULAR Y PEATONAL DE LA VIA PRINCIPAL, CALLE C, CALLE ENTRE LAS MANZANAS K y L, y CALLE ENTRE LAS MANZANAS M, N y O DEL ASENTAMIENTO HUMANO LA ESTRELLA 2DA ETAPA DEL DISTRITO DE SANTIAGO – CUSCO - CUSCO”

Page 2: CRONOGRAMA DE GASTOS.xls

¤ Item Descripción Und. Metrado Precio (S/.) Parcial (S/.)0 01 OBRAS PROVISIONALES 7,075.52

0 01.01 CARTEL DE IDENTIFICACION DE OBRA DE 3.60X2.40 M und 1.00 781.12 781.12

0 01.02 SEÑALES PREVENTIVAS DURANTE EL PROCESO DE EJECUCION und 10.00 73.12 731.20

0 01.03 CONSTRUCCION DE CAMPAMENTO DE OBRA m2 60.00 92.72 5,563.20

0 02 OBRAS PRELIMINARES 29,901.36

0 02.01 TRAZO, NIVELES Y REPLANTEO m2 6,934.21 0.45 3,120.39

0 02.02 TRAZO Y REPLANTEO DURANTE EL PROCESO CONSTRUCTIVO m2 6,934.21 0.45 3,120.39

0 02.03 MOVILIZACION Y DESMOVILIZACION DE EQUIPO GLB 1.00 3,925.30 3,925.30

0 02.04 TRANSPORTE DE MATERIALES CUSCO - OBRA ton 781.66 22.70 17,743.68

0 02.05 REUBICACION DE POSTES und 8.00 248.95 1,991.60

0 03 REPOSICION DE INSTALACIONES DE AGUA Y DESAGUE 155,156.56

0 03.01 INSTALACIONES DE AGUA 47,005.86

0 03.01.01 EXCAVACION DE ZANJA C/MAQUINARIA PARA TUBERIA HASTA 1.50 M DE PROFUNDIDAD m3 238.58 32.43 7,737.15

0 03.01.02 REFINE Y NIVELADO DE ZANJA P/TUBERIA m 596.46 3.21 1,914.64

0 03.01.03 CAMA DE ARENA PARA APOYO DE TUBERIA m 596.46 10.28 6,131.61

0 03.01.04 RELLENO Y COMPACTADO EN ZANJA CON MATERIAL PROPIO m3 223.67 52.00 11,630.84

0 03.01.05 TUBO PVC - U UF PARA AGUA POTABLE NTP-ISO 4422, DN 110 MM m 596.46 22.03 13,140.01

0 03.01.06 PRUEBAS A ZANJA TAPADA P/TUBERIA PVC- U m 596.46 1.71 1,019.95

0 03.01.07 CONEXIONES DOMICILIARIAS DE AGUA und 26.00 208.91 5,431.66

0 03.02 INSTALACIONES DE DESAGUE 89,132.32

0 03.02.01 EXCAVACION DE ZANJA C/MAQUINARIA PARA TUBERIA HASTA 1.50 M DE PROFUNDIDAD m3 442.37 32.43 14,346.06

0 03.02.02 REFINE Y NIVELADO DE ZANJA P/TUBERIA m 614.40 3.21 1,972.22

0 03.02.03 CAMA DE ARENA PARA APOYO DE TUBERIA m 614.40 10.28 6,316.03

0 03.02.04 RELLENO Y COMPACTADO EN ZANJA CON MATERIAL PROPIO m3 508.72 52.00 26,453.44

0 03.02.05 TUBO PVC - U UF PARA ALCANTARILLADO NTP-ISO 4435, DN 200 MM SERIE 20 m 614.40 48.73 29,939.71

0 03.02.06 PRUEBAS A ZANJA TAPADA P/TUBERIA PVC- U UF, DN 200 mm m 614.40 1.71 1,050.62

0 03.02.07 CONEXIONES DOMICILIARIAS DE DESAGUE und 26.00 348.24 9,054.24

0 03.03 BUZONES DE CONCRETO 19,018.38

0 03.03.01 DEMOLICION O RETIRO DE LOSA EXISTENTE m3 5.30 251.35 1,332.16

0 03.03.02 RELLENO BRUTO m3 7.95 40.18 319.43

0 03.03.03 EXCAVACION DE ZANJA C/MAQUINARIA PARA TUBERIA HASTA 1.50 M DE PROFUNDIDAD m3 7.95 32.43 257.82

0 03.03.04 CONCRETO MEZCLA C:H 1:12, EN SOLADO m3 16.96 279.47 4,739.81

0 03.03.05 ENCOFRADO Y DESENCOFRADO EN BUZONES m2 67.01 50.63 3,392.72

0 03.03.06 ACERO DE REFUERZO F'y = 4200 Kg/cm2 kg 206.70 5.46 1,128.58

0 03.03.07 CONCRETO f'c = 175 kg/cm2, en paredes de buzones m3 4.77 429.66 2,049.48

0 03.03.08 CONCRETO f'c = 210 kg/cm2, en losa de buzones m3 5.30 463.10 2,454.43

0 03.03.09 COLOCADO DE TAPA DE BUZONES und 15.00 222.93 3,343.95

0 04 MUROS DE CONTENCION 2,470,559.84

0 04.01 EXCAVACION MANUAL DE ZANJAS PARA MUROS m3 6,721.51 27.86 187,261.27

0 04.02 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA D=5 KM m3 7,729.74 13.62 105,279.06

0 04.03 ENTIBADO DE TALUD PARA MURO DE CONTENCION m2 2,564.72 56.56 145,060.56

0 04.04 PERFILADO DE ZANJAS PARA MUROS m2 1,626.39 4.51 7,335.02

0 04.05 CONCRETO MEZCLA C:H 1:12, EN SOLADO m3 126.29 279.47 35,294.27

0 04.06 ENCOFRADO Y DESENCOFRADO PARA MURO DE CONTENCION m2 2,573.48 46.47 119,589.62

0 04.07 CONCRETO f'c = 210 kg/cm2, EN MURO DE CONTENCION m3 696.73 581.45 405,113.66

0 04.08 ACERO DE REFUERZO F'y = 4200 Kg/cm2 kg 17,701.69 5.46 96,651.23

0 04.09 CONCRETO CICLOPEO f´c = 140 Kg/cm2 + 30 % PG. m3 866.96 317.65 275,389.84

0 04.10 SUMINISTRO Y COLOCACION DE TUBERIA PVC SAL D = 2" (LLorones) m 359.10 7.25 2,603.48

0 04.11 CURADO DE CONCRETO EN MURO m2 2,573.48 1.77 4,555.06

0 04.12 BARANDA METALICA CON TUBERIA FºGº Ø=2" m 294.00 150.00 44,100.00

0 04.13 TARRAJEO EN MUROS EXTERIORES m2 1,984.89 22.62 44,898.21

0 04.14 MUROS CON SISTEMA TERRAMESH 997,428.56

0 04.14.01 GEOTEXTIL NO TEJIDO PARA GAVIONES m2 7,269.48 14.26 103,662.78

0 04.14.02 ELEMENTO TERRAMESH 0.50X1.00X4.0m.MALLA 10X12,DIAM.3.7mm. und 1,615.44 463.80 749,241.07

0 04.14.03 RELLENO Y COMPACTADO CON MATERIAL DE PRESTAMO m3 3,271.27 44.18 144,524.71

0 05 VIAS VEHICULARES 1,730,103.08

0 05.01 MOVIMIENTO DE TIERRAS 252,971.82

0 05.01.01 CORTE EN MATERIAL COMPACTO CON MAQUINARIA m3 6,841.98 5.74 39,272.97

0 05.01.02 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA D=10 KM m3 7,868.27 18.89 148,631.62

0 05.01.03 PERFILADO RIEGO Y COMPACTADO DE SUB - RASANTE m2 6,841.98 9.51 65,067.23

0 05.02 PAVIMENTO 1,477,131.26

0 05.02.01 MEJORAMIENTO DE LA SUBRASANTE 50 CM DE ESPESOR 306,543.71

0 05.02.01 TRAZO Y REPLANTEO DURANTE EL PROCESO CONSTRUCTIVO m2 5,948.95 0.45 2,677.03

0 05.02.01 MATERIAL DE CANTERA BASE m3 3,420.65 70.12 239,855.98

0 05.02.01 EXTENDIDO BATIDO Y PERFILADO DE MATERIAL DE BASE m2 5,948.95 4.80 28,554.96

0 05.02.01 RIEGO Y COMPACTADO DE BASE m2 5,948.95 5.96 35,455.74

0 05.02.02 BASE DE 20 CM DE ESPESOR 210,601.32

0 05.02.02 TRAZO Y REPLANTEO DURANTE EL PROCESO CONSTRUCTIVO m2 5,948.95 0.45 2,677.03

0 05.02.02 MATERIAL DE CANTERA BASE m3 2,052.39 70.12 143,913.59

0 05.02.02 EXTENDIDO BATIDO Y PERFILADO DE MATERIAL DE BASE m2 5,948.95 4.80 28,554.96

0 05.02.02 RIEGO Y COMPACTADO DE BASE m2 5,948.95 5.96 35,455.74

0 05.02.03 LOSA DE RODADURA 959,986.23

0 05.02.03 TRAZO Y REPLANTEO DURANTE EL PROCESO CONSTRUCTIVO m2 5,948.95 0.45 2,677.03

0 05.02.03 ENCOFRADO Y DESENCOFRADO EN PAVIMENTO RIGIDO m2 533.15 42.04 22,413.63

0 05.02.03 CONCRETO f'c = 210 kg/cm², en pavimento rígido, e=20 cm m2 5,948.95 146.93 874,079.22

0 05.02.03 Acero grado 60 Ø 1/4", en malla de temperatura kg 3,702.02 5.12 18,954.34

0 05.02.03 JUNTA LONGITUDINAL DE ARTICULACION Ø 1/2" ACERO CORRUGADO kg 293.91 4.64 1,363.74

0 05.02.03 JUNTA TRANSVERSAL DE CONTRACCION Ø 3/4" ACERO LISO kg 2,237.76 9.80 21,930.05

0 05.02.03 JUNTA DE DILATACION Ø 1" ACERO LISO kg 83.37 9.94 828.70

Page 3: CRONOGRAMA DE GASTOS.xls

0 05.02.03 CURADO DE CONCRETO EN LOSA DE PAVIMENTO m2 5,948.95 0.67 3,985.80

0 05.02.03 SELLADO DE JUNTAS LONGITUDINALES m 846.00 4.97 4,204.62

0 05.02.03 SELLADO DE JUNTAS DE CONTRACCION m 1,819.75 4.97 9,044.16

0 05.02.03 SELLADO DE JUNTAS DE DILATACION m 80.92 6.24 504.94

0 06 DRENAJE PLUVIAL 67,268.32

0 06.01 CANAL DE EVACUACION DE AGUAS PLUVIALES 22,867.11

0 06.01.01 TRAZO Y REPLANTEO DURANTE EL PROCESO CONSTRUCTIVO m2 60.00 0.45 27.00

0 06.01.02 EXCAVACION MANUAL DE ZANJAS m3 37.44 27.03 1,012.00

0 06.01.03 ELIMINACION MANUAL DE MATERIAL EXCEDENTE D = 30 mt. m3 43.06 18.03 776.37

0 06.01.04 PERFILADO Y COMPACTADO PARA FONDO DE CANAL m2 30.00 10.40 312.00

0 06.01.05 ENCOFRADO Y DESENCOFRADO EN CANAL m2 100.80 38.56 3,886.85

0 06.01.06 ACERO GRADO 60 kg 1,000.00 5.30 5,300.00

0 06.01.07 CONCRETO f'c = 210 kg/cm2 m3 16.68 463.10 7,724.51

0 06.01.08 TARRAJEO IMPERMEABILIZADO C:A 1:3 + ADITIVO m2 100.80 37.98 3,828.38

0 06.02 SUMIDERO TRANSVERSAL 21,563.79

0 06.02.01 TRAZO Y REPLANTEO DURANTE EL PROCESO CONSTRUCTIVO m2 13.50 0.45 6.08

0 06.02.02 EXCAVACION DE ZANJA C/MAQUINARIA PARA TUBERIA HASTA 1.50 M DE PROFUNDIDAD m3 13.50 32.43 437.81

0 06.02.03 PERFILADO Y COMPACTADO PARA FONDO DE SUMIDERO m2 13.50 5.20 70.20

0 06.02.04 ELIMINACION MANUAL DE MATERIAL EXCEDENTE D = 40 M m3 15.53 13.51 209.81

0 06.02.05 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA D=10 KM m3 15.53 18.89 293.36

0 06.02.06 ENCOFRADO Y DESENCOFRADO EN SUMIDERO m2 32.63 37.05 1,208.94

0 06.02.07 CONCRETO MEZCLA C:H 1:12, EN SOLADO m3 1.01 279.47 282.26

0 06.02.08 CONCRETO f'c = 210 kg/cm2 m3 6.92 463.10 3,204.65

0 06.02.09 ACERO GRADO 60 kg 1,000.00 5.30 5,300.00

0 06.02.10 TARRAJEO IMPERMEABILIZADO C:A 1:3 + ADITIVO m2 32.63 37.98 1,239.29

0 06.02.11 CURADO DE CONCRETO EN SUMIDERO m2 32.63 0.67 21.86

0 06.02.12 REJILLA DE SUMIDERO PLAT 2 1/2" X 1/2" C/RIEL und 9.00 1,032.17 9,289.53

0 06.03 TUBERIA PARA AGUAS PLUVIALES 22,837.42

0 06.03.01 EXCAVACION DE ZANJA C/MAQUINARIA PARA TUBERIA HASTA 1.50 M DE PROFUNDIDAD m3 91.22 32.43 2,958.26

0 06.03.02 ELIMINACION MANUAL DE MATERIAL EXCEDENTE D = 40 M m3 91.22 13.51 1,232.38

0 06.03.03 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA D=10 KM m3 91.22 18.89 1,723.15

0 06.03.04 REFINE Y NIVELADO DE ZANJA P/TUBERIA DN 315 mm m 190.04 3.21 610.03

0 06.03.05 CAMA DE ARENA PARA APOYO DE TUBERIA m 190.04 10.28 1,953.61

0 06.03.06 RELLENO Y COMPACTADO EN ZANJA CON MATERIAL PROPIO m3 91.22 52.00 4,743.44

0 06.03.07 TUBO PVC - U UF PARA ALCANTARILLADO NTP-ISO 4435, DN 200 MM SERIE 20 m 190.04 48.73 9,260.65

0 06.03.08 TUBO PVC - U UF PARA ALCANTARILLADO NTP-ISO 4435, DN 160 MM SERIE 20 m 1.00 30.93 30.93

0 06.03.09 PRUEBAS A ZANJA TAPADA P/TUBERIA PVC- U UF, DN 200 mm m 190.04 1.71 324.97

0 07 VIAS PEATONALES 93,857.87

0 07.01 SARDINELES 24,129.78

0 07.01.01 EXCAVACION DE ZANJAS PARA SARDINELES m 254.50 1.62 412.29

0 07.01.02 ELIMINACION MANUAL DE MATERIAL EXCEDENTE D = 40 M m3 22.91 13.51 309.51

0 07.01.03 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA D=10 KM m3 22.91 18.89 432.77

0 07.01.04 ENCOFRADO Y DESENCOFRADO DE SARDINELES m2 305.40 38.34 11,709.04

0 07.01.05 CONCRETO f'c = 175 kg/cm2, PARA SARDINELES m3 22.91 429.66 9,843.51

0 07.01.06 CURADO DE CONCRETO EN SARDINELES m 254.50 0.35 89.08

0 07.01.07 SELLADO DE JUNTAS EN SARDINELES m 254.50 5.24 1,333.58

0 07.02 VEREDAS 69,728.09

0 07.02.01 CORTE DE TERRENO HASTA 0.15 M DE ESPESOR m3 135.45 32.43 4,392.64

0 07.02.02 PERFILADO Y COMPACTADO m2 902.98 5.20 4,695.50

0 07.02.03 ELIMINACION MANUAL DE MATERIAL EXCEDENTE D = 40 M m3 135.45 13.51 1,829.93

0 07.02.04 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA D=10 KM m3 135.45 18.89 2,558.65

0 07.02.05 EMPEDRADO, E=12.5 cm m2 902.98 18.90 17,066.32

0 07.02.06 ENCOFRADO Y DESENCOFRADO m2 164.27 38.14 6,265.26

0 07.02.07 CONCRETO f'c = 175 kg/cm², e=7.5 cm m3 67.72 431.33 29,209.67

0 07.02.08 SELLADO DE JUNTAS EN VEREDAS m 778.30 3.83 2,980.89

0 07.02.09 CURADO DE CONCRETO m2 1,088.40 0.67 729.23

0 08 TRABAJOS COMPLEMENTARIOS 18,276.35

0 08.01 SEÑALIZACION HORIZONTAL 2,834.95

0 08.01.01 DEMARCACION EN EL PAVIMENTO m2 253.80 11.17 2,834.95

0 08.02 PRUEBAS DE CONTROL DE CALIDAD 4,300.00

0 08.02.01 DISEÑO DE MEZCLAS DE CONCRETO PRU 5.00 350.00 1,750.00

0 08.02.02 PRUEBAS DE RESISTENCIA DEL CONCRETO PRU 50.00 25.00 1,250.00

0 08.02.03 PRUEBAS DE DENSIDAD DE CAMPO PRU 20.00 15.00 300.00

0 08.02.04 ENSAYO DE PROCTOR MODIFICADO PRU 20.00 50.00 1,000.00

0 08.03 SEGURIDAD Y SALUD EN LA OBRA 4,029.00

0 08.03.01 ELABORACIÓN, IMPLEMENTACIÓN Y ADMINISTRACIÓN DEL PLAN DE SEGURIDAD Y SALUD EN GLB 1.00 1,200.00 1,200.00

0 08.03.02 EQUIPO DE PROTECCIÓN INDIVIDUAL GLB 1.00 1,750.00 1,750.00

0 08.03.03 EQUIPO DE PROTECCIÓN COLECTIVA GLB 1.00 1,079.00 1,079.00

0 08.04 LIMPIEZA DE OBRA 7,112.40

0 08.04.01 LIMPIEZA FINAL DE OBRA m2 6,934.21 0.68 4,715.26

0 08.04.02 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA D=10 KM m3 126.90 18.89 2,397.14

Page 4: CRONOGRAMA DE GASTOS.xls

RESUMEN PRESUPUESTO TOTAL

OBRA:

REGION: CUSCO PROVINCIA: CUSCO DISTRITO: SANTIAGO

DURACION: 12.00 MESES

PRESUPUESTO BASE

SUB TOTAL TOTAL

001 MEJORAMIENTO DE LA TRANSITABILIDAD VEHICULAY Y PEATONAL 4,572,198.90

COSTO DIRECTO 4,572,198.90GASTOS GENERALES 4.93% 225,510.32SUPERVISION DE OBRA 1.36% 62,036.40LIQUIDACION DE OBRA Y EVALUADOR 0.36% 16,626.32EXPEDIENTE TECNICO 0.52% 23,900.00

TOTAL PRESUPUESTO (S/.) 4,900,271.94

“MEJORAMIENTO DE LA TRANSITABILIDAD VEHICULAR Y PEATONAL DE LA VIA PRINCIPAL, CALLE C, CALLE ENTRE LAS MANZANAS K y L, y CALLE ENTRE LAS MANZANAS M, N y O DEL ASENTAMIENTO HUMANO LA ESTRELLA 2DA

ETAPA DEL DISTRITO DE SANTIAGO – CUSCO - CUSCO”