CRONOGRAMA DE REQUERIMIENTO CONCRETO PREMEZCLADOJULIO AGOSTO
ITEM DESCRIPCION DE PARTIDA UNDCANT.SEMANA 1 SEMANA 2 SEMANA 3 SEMANA 4 SEMANA 5 SEMANA 6 SEMANA 7 SEMANA 8
D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S
m3 % m3 % m3 % m3 % m3 % m3 % m3 % m3 %
05.06 VIGAS 22.32 8.33 22.32 8.33 22.32 8.33 22.32 8.33
05.06.01 CONCRETO F'C= 210 KG/CM2. PARA VIGAS m3 267.84
05.07 LOSAS MACIZAS 2.61 8.33 2.61 8.33 2.61 8.33 2.61 8.33
05.07.01 CONCRETO F'C= 210 KG/CM2. PARA LOSAS MACIZAS m3 31.26
05.08 LOSAS ALIGERADAS 37.54 9.03 37.54 9.03 37.54 9.03 37.54 9.03
05.08.01 CONCRETO F'C= 210 KG/CM2. PARA LOSAS ALIGERADAS m3 415.90
m3 TOTAL62.46 62.46 62.46 62.46
124.92 124.92
SETIEMBRE OCTUBRE
ITEM DESCRIPCION DE PARTIDA UNDCANT.SEMANA 1 SEMANA 2 SEMANA 3 SEMANA 4 SEMANA 5 SEMANA 6 SEMANA 7 SEMANA 8
D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S
m3 % m3 % m3 % m3 % m3 % m3 % m3 % m3 %
05.06 VIGAS 22.32 8.33 22.32 8.33 22.32 8.33 22.32 8.33
05.06.01 CONCRETO F'C= 210 KG/CM2. PARA VIGAS m3 267.84
05.07 LOSAS MACIZAS 2.61 8.33 2.61 8.33 2.61 8.33 2.61 8.33
05.07.01 CONCRETO F'C= 210 KG/CM2. PARA LOSAS MACIZAS m3 31.26
05.08 LOSAS ALIGERADAS 37.54 9.03 37.54 9.03 37.54 9.03 37.54 9.03
05.08.01 CONCRETO F'C= 210 KG/CM2. PARA LOSAS ALIGERADAS m3 415.90
m3 TOTAL62.46 62.46 62.46 62.46
124.92 124.92
NOVIEMBRE DICIEMBRE
ITEM DESCRIPCION DE PARTIDA UNDCANT.SEMANA 1 SEMANA 2 SEMANA 3 SEMANA 4 SEMANA 5 SEMANA 6 SEMANA 7 SEMANA 8
D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S
m3 % m3 % m3 % m3 % m3 % m3 % m3 % m3 %
05.06 VIGAS 22.32 8.33 22.32 8.33 22.32 8.33 22.32 8.33
05.06.01 CONCRETO F'C= 210 KG/CM2. PARA VIGAS m3 267.84
05.07 LOSAS MACIZAS 2.61 8.33 2.61 8.33 2.61 8.33 2.61 8.33
05.07.01 CONCRETO F'C= 210 KG/CM2. PARA LOSAS MACIZAS m3 31.26
05.08 LOSAS ALIGERADAS 37.54 9.03 37.54 9.03 20.27 4.87 20.27 4.87
05.08.01 CONCRETO F'C= 210 KG/CM2. PARA LOSAS ALIGERADAS m3 415.90
m3 TOTAL62.46 62.46 45.20 45.20
124.92 90.40
NOTA : EL PRESENTE CRONOGRAMA ES REFERENCIAL YA QUE SE SUJETARA AL VERDADERO REQUERIMIENTO EN OBRA
CRONOGRAMA DE REQUERIMIENTO CONCRETO PREMEZCLADOSETIEMBRE OCTUBRE
ITEM DESCRIPCION DE PARTIDA UNDCANT.SEMANA 1 SEMANA 2 SEMANA 3 SEMANA 4 SEMANA 5 SEMANA 6 SEMANA 7 SEMANA 8
D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S
m3 % m3 % m3 % m3 % m3 % m3 % m3 % m3 %
05.06 VIGAS 22.32 8.33 22.32 8.33 22.32 8.33
05.06.01 CONCRETO F'C= 210 KG/CM2. PARA VIGAS m3 267.84
05.07 LOSAS MACIZAS 2.61 8.33 2.61 8.33 2.61 0.97
05.07.01 CONCRETO F'C= 210 KG/CM2. PARA LOSAS MACIZAS m3 31.26
05.08 LOSAS ALIGERADAS 37.54 9.03 37.54 9.03 37.54 14.01
05.08.01 CONCRETO F'C= 210 KG/CM2. PARA LOSAS ALIGERADAS m3 415.90
m3 TOTAL0.00 62.46 62.46 62.46
62.46 124.92
NOVIEMBRE DICIEMBRE
ITEM DESCRIPCION DE PARTIDA UNDCANT.SEMANA 1 SEMANA 2 SEMANA 3 SEMANA 4 SEMANA 5 SEMANA 6 SEMANA 7 SEMANA 8
D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S
m3 % m3 % m3 % m3 % m3 % m3 % m3 % m3 %
05.06 VIGAS 22.32 8.33 22.32 8.33 22.32 8.33 22.32 8.33
05.06.01 CONCRETO F'C= 210 KG/CM2. PARA VIGAS m3 267.84
05.07 LOSAS MACIZAS 2.61 0.97 2.61 8.33 2.61 8.33 2.61 0.97
05.07.01 CONCRETO F'C= 210 KG/CM2. PARA LOSAS MACIZAS m3 31.26
05.08 LOSAS ALIGERADAS 37.54 14.01 37.54 9.03 37.54 9.03 37.54 14.01
05.08.01 CONCRETO F'C= 210 KG/CM2. PARA LOSAS ALIGERADAS m3 415.90
m3 TOTAL62.46 62.46 62.46 62.46
124.92 124.92
ENERO FEBRERO
ITEM DESCRIPCION DE PARTIDA UNDCANT.SEMANA 1 SEMANA 2 SEMANA 3 SEMANA 4 SEMANA 5 SEMANA 6 SEMANA 7 SEMANA 8
D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S
m3 % m3 % m3 % m3 % m3 % m3 % m3 % m3 %
05.06 VIGAS 22.32 8.33 22.32 8.33 22.32 8.33 22.32 8.33
05.06.01 CONCRETO F'C= 210 KG/CM2. PARA VIGAS m3 267.84
05.07 LOSAS MACIZAS 2.61 0.97 2.61 8.33 2.61 8.33 2.61 0.97
05.07.01 CONCRETO F'C= 210 KG/CM2. PARA LOSAS MACIZAS m3 31.26
05.08 LOSAS ALIGERADAS 37.54 14.01 37.54 9.03 37.54 9.03 20.27 7.57
05.08.01 CONCRETO F'C= 210 KG/CM2. PARA LOSAS ALIGERADAS m3 415.90
m3 TOTAL62.46 62.46 62.46 45.20
124.92 107.66
MARZO ABRIL
ITEM DESCRIPCION DE PARTIDA UNDCANT.SEMANA 1 SEMANA 2 SEMANA 3 SEMANA 4 SEMANA 5 SEMANA 6 SEMANA 7 SEMANA 8
D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S
m3 % m3 % m3 % m3 % m3 % m3 % m3 % m3 %
05.06 VIGAS 22.32 8.33
05.06.01 CONCRETO F'C= 210 KG/CM2. PARA VIGAS m3 267.84
05.07 LOSAS MACIZAS 2.61 8.33
05.07.01 CONCRETO F'C= 210 KG/CM2. PARA LOSAS MACIZAS m3 31.26
05.08 LOSAS ALIGERADAS 20.27 4.87
05.08.01 CONCRETO F'C= 210 KG/CM2. PARA LOSAS ALIGERADAS m3 415.90
m3 TOTAL45.20
m3 TOTAL45.20
NOTA : EL PRESENTE CRONOGRAMA ES REFERENCIAL YA QUE SE SUJETARA AL VERDADERO REQUERIMIENTO EN OBRA
CRONOGRAMA DE REQUERIMIENTO CONCRETO PREMEZCLADO
OBRA : MEJORAMIENTO DE LA CAPACIDAD OPERATIVA DEL ARCHIVO REGIONAL PUNO
PROPIETARIO : GOBIERNO REGIONAL DE PUNO
DESCRIPCION DE PARTIDA UNDCANT.
SETIEMBRE OCTUBRE NOVIEMBRE DICIEMBRE ENERO FEBRERO MARZO
1ra entrega 2da. entrega 3ra. Entrega 4ta. Entrega 5ta. Entrega 6ta. Entrega 7ma. Entrega 8va. Entrega 9na. Entrega 10 ma. Entrega 11 va. Entrega 12 va. Entrega
lunes 16 lunes 01 Jueves 17 Lunes 04 Martes 19 Miercoles 04 Jueves 19 Viernes 03 Jueves 16 Sabado 01 Sabado 15 Lunes 02
VIGAS
CONCRETO F'C= 210 KG/CM2. PARA VIGAS m3 267.84 22.32 22.32 22.32 22.32 22.32 22.32 22.32 22.32 22.32 22.32 22.32 22.32
LOSAS MACIZAS
CONCRETO F'C= 210 KG/CM2. PARA LOSAS MACIZASm3 31.26 2.605 2.605 2.605 2.605 2.605 2.605 2.605 2.605 2.605 2.605 2.605 2.605
LOSAS ALIGERADAS
CONCRETO F'C= 210 KG/CM2. PARA LOSAS ALIGERADAS m3 415.90 34.66 34.66 34.658 34.658 34.658 34.658 34.658 34.658 34.658 34.658 34.658 34.658
CRONOGRAMA REPROGRAMADO DE REQUERIMIENTO CONCRETO PREMEZCLADO
OBRA : MEJORAMIENTO DE LA CAPACIDAD OPERATIVA DEL ARCHIVO REGIONAL PUNO
PROPIETARIO : GOBIERNO REGIONAL DE PUNO
DESCRIPCION DE PARTIDA UNDCANT.
OCTUBRE NOVIEMBRE DICIEMBRE ENERO FEBRERO MARZO
1ra entrega 2da. entrega 3ra. Entrega 4ta. Entrega 5ta. Entrega 6ta. Entrega 7ma. Entrega 8va. Entrega 9na. Entrega 10 ma. Entrega 11 va. Entrega 12 va. Entrega
Viernes 04 Lunes 21 Martes 05 Miercoles 20 Jueves 05 Viernes 20 Sabado 04 Lunes 20 Lunes 03 Martes 18 Miercoles 05 Jueves 20
VIGAS
CONCRETO F'C= 210 KG/CM2. PARA VIGAS m3 267.84 22.32 22.32 22.32 22.32 22.32 22.32 22.32 22.32 22.32 22.32 22.32 22.32
LOSAS MACIZAS
CONCRETO F'C= 210 KG/CM2. PARA LOSAS MACIZASm3 31.26 2.605 2.605 2.605 2.605 2.605 2.605 2.605 2.605 2.605 2.605 2.605 2.605
LOSAS ALIGERADAS
CONCRETO F'C= 210 KG/CM2. PARA LOSAS ALIGERADAS m3 415.90 34.66 34.658 34.658 34.658 34.658 34.658 34.658 34.658 34.658 34.658 34.658 34.66
12 va. Entrega
CRONOGRAMA REPROGRAMADO DE REQUERIMIENTO CONCRETO PREMEZCLADO
OBRA : MEJORAMIENTO DE LA CAPACIDAD OPERATIVA DEL ARCHIVO REGIONAL PUNO
PROPIETARIO : GOBIERNO REGIONAL DE PUNO
DESCRIPCION DE PARTIDA UNDCANT.
OCTUBRE NOVIEMBRE DICIEMBRE ENERO FEBRERO MARZO
1ra entrega 2da. entrega 3ra. Entrega 4ta. Entrega 5ta. Entrega 6ta. Entrega 7ma. Entrega 8va. Entrega 9na. Entrega 10 ma. Entrega 11 va. Entrega 12 va. Entrega
VIGAS
CONCRETO F'C= 210 KG/CM2. PARA VIGAS m3 267.84 22.32 22.32 22.32 22.32 22.32 22.32 22.32 22.32 22.32 22.32 22.32 22.32
LOSAS MACIZAS
CONCRETO F'C= 210 KG/CM2. PARA LOSAS MACIZASm3 31.26 2.605 2.605 2.605 2.605 2.605 2.605 2.605 2.605 2.605 2.605 2.605 2.605
LOSAS ALIGERADAS
CONCRETO F'C= 210 KG/CM2. PARA LOSAS ALIGERADAS m3 415.90 34.66 34.658 34.658 34.658 34.658 34.658 34.658 34.658 34.658 34.658 34.658 34.66
TOTAL m3 715.00 59.58 59.58 59.58 59.58 59.58 59.58 59.58 59.58 59.58 59.58 59.58 59.58
12 va. Entrega