CRONOGRAMA CANAL YAPAC - ALTERNATIVA N° O1
Transcript of CRONOGRAMA CANAL YAPAC - ALTERNATIVA N° O1
-
7/28/2019 CRONOGRAMA CANAL YAPAC - ALTERNATIVA N O1
1/18
CRONOG
OBRA : INSTALACION DEL SERVICIO DE AGUA DEL SISTEMA DE RIEGO, EN LA LOCALIDAD DE YAPAC, DISTRITO
UBICACIN : Departamento: HUNUCO Provincia: AMBO Distrito: COLPAS Localidad: YAPAC
1 QUINCENA 2 QUINCENA 1 QU
5.65 % 7.04 %
BOCATOMA
01 OBRAS PROVISIONALES
01.01 CARTEL DE IDENTIFICACION DE OBRA 100.00 %
01.02 ALMACEN DE OBRA Y GUARDIANIA 100.00 %
01.03 TRANSPORTE DE MAT. Y AGREGADOS 30.00 % 30.00 % 2
01.04 MOVILIZACION Y DESMOVILIZACION DE EQUIPO 50.00 %
02 MUROS DE ENCAUZAMIENTO
02.01 TRABAJOS PRELIMINARES 50.00 % 20.00 % 2
02.02 MOVIMIENTO DE TIERRAS 20.00 % 40.00 % 4
02.03 OBRAS DE CONCRETO SIMPLE 30.00 % 402.04 OBRAS DE CONCRETO ARMADO 5
02.05 REVOQUES Y ENLUCIDOS
03 PRESA DERIVADORA
03.01 TRABAJOS PRELIMINARES 50.00 % 5
03.02 MOVIMIENTO DE TIERRAS 75.00 % 2
03.03 OBRAS DE CONCRETO SIMPLE 50.00 % 5
03.04 OBRAS DE CONCRETO ARMADO 4
03.05 REVOQUES Y ENLUCIDOS
03.06 VARIOS
04 TOMA O CAPTACION
04.01 TRABAJOS PRELIMINARES
04.02 MOVIMIENTO DE TIERRAS
04.03 OBRAS DE CONCRETO SIMPLE
04.04 OBRAS DE CONCRETO ARMADO
04.05 REVOQUES Y ENLUCIDOS
04.06 VARIOS
05 LINEA DE CONDUCCION
05.01 TRABAJOS PRELIMINARES 40.00 % 50.00 % 1
05.02 MOVIMIENTO DE TIERRAS 5.00 % 20.00 % 2
05.03 TENDIDO DE TUBERIAS EN LINEA DE CONDUCCION 10.00 % 2
05.04 ACCESORIOS PARA TUBERIAS
05.05 PRUEBA HIDRAULICA
01 RESERVORIO DE GEOMENBRANA N 01
01.01 TRABAJOS PRELIMINARES
01.02 MOVIMIENTO DE TIERRAS
01.03 GEOMENBRANA
100 CAJA PARA VALVULAS
01.05 ACCESORIOS DE RESERVORIO
01.06 CERCO PERIMETRICO
02 RESERVORIO DE GEOMENBRANA N 02
02.01 TRABAJOS PRELIMINARES
02.02 MOVIMIENTO DE TIERRAS
02.03 GEOMENBRANA
02.04 CAJA PARA VALVULAS
02.05 ACCESORIOS DE RESERVORIO
02.06 CERCO PERIMETRICO3 RESERVORIO DE GEOMENBRANA N 03
02.01 TRABAJOS PRELIMINARES
ITEM DESCRIPCIN DE PARTIDAS
PLAZO D
1 MES
-
7/28/2019 CRONOGRAMA CANAL YAPAC - ALTERNATIVA N O1
2/18
CRONOGR
OBRA : INSTALACION DEL SERVICIO DE AGUA DEL SISTEMA DE RIEGO, EN LA LOCALIDAD DE YAPAC, DISTRITO DE
UBICACIN : Departamento: HUNUCO Provincia: AMBO Distrito: COLPAS Localidad: YAPAC
1 QUINCENA 2 QUINCENA 1 QUIN
5.65 % 7.04 % 9
ITEM DESCRIPCIN DE PARTIDAS
PLAZO DE
1 MES
08.06 CAMARA PARA VALVULA REGULADORA DE PRESION TIPO I (08 UNID)
08.07 CAMARA PARA VALVULA DE PURGA TIPO I (12 UNID)
08.08 CAMARA PARA HIDRANTE (75 UNID)
09 RED DE DISTRIBUCION
09.01 TRABAJOS PRELIMINARES 30
09.02 MOVIMIENTO DE TIERRAS
09.03 TENDIDO DE TUBERIAS EN LINEA DE DISTRIBUCION
09.04 ACCESORIOS PARA TUBERIAS
09.05 PRUEBA HIDRAULICA
10 PLAN DE MANEJO AMBIENTAL
10.01 ACTIVIDADES DE PREVENCION 10.00 % 10.00 % 1010.02 ACTIVIDADES DE MITIGACION 5.00 % 5.00 % 10
10.03 ACTIVIDADES DE MONITOREO 5.00 % 5.00 % 1010.04 FLETE 50.00 % 50.00 %11 CAPACITACION TECNICA
11.01 TRABAJOS DE CAMPO 50.00 % 50.00 %11.02 CONVOCATORIA 50.00 % 5011.03 DE LA CAPACITACION 5
-
7/28/2019 CRONOGRAMA CANAL YAPAC - ALTERNATIVA N O1
3/18
OBRA : INSTALACION DEL SERVICIO DE AGUA DEL SISTEMA DE RIEGO, EN LA LOCALIDAD DE YAPAC, DISTRITO DE COLPAS.
UBICACIN : Departamento: HUNUCO Provincia: AMBO Distrito: COLPAS Localidad: YAPAC
1 QUINCENA 2 QUINCENA 1
15 30
BOCATOMA
01 OBRAS PROVISIONALES S/. 0.00 S/. 0.00
01.01 CARTEL DE IDENTIFICACION DE OBRA S/. 871.45 S/. 0.00
01.02 ALMACEN DE OBRA Y GUARDIANIA S/. 1,096.46 S/. 0.00
01.03 TRANSPORTE DE MAT. Y AGREGADOS S/. 35,209.34 S/. 35,209.34 S
01.04 MOVILIZACION Y DESMOVILIZACION DE EQUIPO S/. 529.41 S/. 0.00
02 MUROS DE ENCAUZAMIENTO
02.01 TRABAJOS PRELIMINARES S/. 230.98 S/. 92.39
02.02 MOVIMIENTO DE TIERRAS S/. 5,874.15 S/. 11,748.31 S
02.03 OBRAS DE CONCRETO SIMPLE S/. 0.00 S/. 347.93
02.04 OBRAS DE CONCRETO ARMADO S/. 0.00 S/. 0.00 S
02.05 REVOQUES Y ENLUCIDOS S/. 0.00 S/. 0.00
03 PRESA DERIVADORA S/. 0.00 S/. 0.00
03.01 TRABAJOS PRELIMINARES S/. 0.00 S/. 102.26
03.02 MOVIMIENTO DE TIERRAS S/. 0.00 S/. 86.66
03.03 OBRAS DE CONCRETO SIMPLE S/. 0.00 S/. 3,745.97
03.04 OBRAS DE CONCRETO ARMADO S/. 0.00 S/. 0.00
03.05 REVOQUES Y ENLUCIDOS S/. 0.00 S/. 0.00
03.06 VARIOS
04 TOMA O CAPTACION
04.01 TRABAJOS PRELIMINARES
04.02 MOVIMIENTO DE TIERRAS
04.03 OBRAS DE CONCRETO SIMPLE
04.04 OBRAS DE CONCRETO ARMADO
04.05 REVOQUES Y ENLUCIDOS S/. 0.00 S/. 0.00
04.06 VARIOS S/. 0.00 S/. 0.00
05 LINEA DE CONDUCCION S/. 0.00 S/. 0.00
05.01 TRABAJOS PRELIMINARES S/. 3,993.60 S/. 4,992.00
05.02 MOVIMIENTO DE TIERRAS S/. 8,138.33 S/. 32,553.32 S
05.03 TENDIDO DE TUBERIAS EN LINEA DE CONDUCCION S/. 0.00 S/. 12,958.40 S
05.04 ACCESORIOS PARA TUBERIAS S/. 0.00 S/. 0.00
05.05 PRUEBA HIDRAULICA S/. 0.00 S/. 0.00
01 RESERVORIO DE GEOMENBRANA N 01 S/. 0.00 S/. 0.00
01.01 TRABAJOS PRELIMINARES S/. 0.00 S/. 0.00
01.02 MOVIMIENTO DE TIERRAS S/. 0.00 S/. 0.00
01.03 GEOMENBRANA S/. 0.00 S/. 0.00
100 CAJA PARA VALVULAS S/. 0.00 S/. 0.00
01.05 ACCESORIOS DE RESERVORIO S/. 0.00 S/. 0.00
01.06 CERCO PERIMETRICO S/. 0.00 S/. 0.00
02 RESERVORIO DE GEOMENBRANA N 02 S/. 0.00 S/. 0.00
02.01 TRABAJOS PRELIMINARES S/. 0.00 S/. 0.00
02.02 MOVIMIENTO DE TIERRAS S/. 0.00 S/. 0.00
ITEM DESCRIPCIN DE PARTIDAS1 MES
-
7/28/2019 CRONOGRAMA CANAL YAPAC - ALTERNATIVA N O1
4/18
OBRA : INSTALACION DEL SERVICIO DE AGUA DEL SISTEMA DE RIEGO, EN LA LOCALIDAD DE YAPAC, DISTRITO DE COLPAS.
UBICACIN : Departamento: HUNUCO Provincia: AMBO Distrito: COLPAS Localidad: YAPAC
1 QUINCENA 2 QUINCENA 1 Q
15 30
ITEM DESCRIPCIN DE PARTIDAS1 MES
02.02 MOVIMIEN TO DE TIERRAS S/. 0.00 S/. 0.00
02.03 GEOMENBRANA S/. 0.00 S/. 0.00
02.04 CAJA PARA VALVULAS S/. 0.00 S/. 0.00
02.05 ACCESORIOS DE RESERVORIO S/. 0.00 S/. 0.00
02.06 CERCO PERIMETRICO S/. 0.00 S/. 0.00
08 OBRAS DE ESTRUCTURAS HIDRAULICAS S/. 0.00 S/. 0.00
08.01 CAJA PARA VALVULAS DE CONTROL TIPO I (06 UNID) S/. 0.00 S/. 0.00
08.04 CAMARA ROMPE PRESION (11 UNID) S/. 0.00 S/. 0.00
08.05 CAMARA DISTRIBUIDORA DE CAUDALES ( 05 UNID.) S/. 0.00 S/. 0.00
08.06 CAMARA PARA VALVULA REGULADORA DE PRESION TIPO I (08 UNID) S/. 0.00 S/. 0.00
08.07 CAMARA PARA VALVULA DE PURGA TIPO I (12 UNID) S/. 0.00 S/. 0.00
08.08 CAMARA PARA HIDRANTE (75 UNID) S/. 0.00 S/. 0.00
09 RED DE DISTRIBUCION S/. 0.00 S/. 0.00
09.01 TRABAJOS PRELIMINARES S/. 0.00 S/. 0.00
09.02 MOVIMIENTO DE TIERRAS S/. 0.00 S/. 0.00
09.03 TENDIDO DE TUBERIAS EN LINEA DE DISTRIBUCION S/. 0.00 S/. 0.00
09.04 ACCESORIOS PARA TUBERIAS S/. 0.00 S/. 0.00
09.05 PRUEBA HIDRAULICA S/. 0.00 S/. 0.00
10 PLAN DE MANEJO AMBIENTAL S/. 0.00 S/. 0.00
10.01 ACTIVIDADES DE PREVENCION S/. 1,169.51 S/. 1,169.51
10.02 ACTIVIDADES DE MITIGACION S/. 938.65 S/. 938.65
10.03 ACTIVIDADES DE MONITOREO S/. 32.44 S/. 32.44
10.04 FLETE S/. 500.00 S/. 500.00
11 CAPACITACION TECNICA S/. 0.00 S/. 0.00
11.01 TRABAJOS DE CAMPO S/. 600.00 S/. 600.00
11.02 CONVOCATORIA S/. 0.00 S/. 450.00
11.03 DE LA CAPACITACION S/. 0.00 S/. 0.00
COSTO DIRECTO DEL PROYECTO (A) S/. 59,184.33 S/. 105,527.17
GASTOS GENERALES (10 %) (B) S/. 5,918.43 S/. 10,552.72
GASTOS DE UTILIDAD (10%) ( C) S/. 5,918.43 S/. 10,552.72
COSTO SUB TOTAL DEL PROYECTO (A+B+C) S/. 71,021.20 S/. 126,632.60 S/
IGV (18 %) D= (A+B+C)*0.18 S/. 12,783.82 S/. 22,793.87
COSTO DE LA OBRA (CO=D+A+B+C) S/. 83,805.02 S/. 149,426.47 S/
GASTOS DE SUPERVISIN ( E) S/. 1,775.53 S/. 3,165.82
COSTO DE ELABORACION DE EXPEDIENTE DEFINITIVO S/. 36,853.52
COSTO TOTAL DEL PROYECTO (CO + E) S/. 122,434.06 S/. 152,592.29
AVANCE POR QUINCENA 5.65 % 7.04 % 9AVANCE POR MES
AVANCE ACUMULADO 12.68 %
12.68 %
-
7/28/2019 CRONOGRAMA CANAL YAPAC - ALTERNATIVA N O1
5/18
MONTO TOTAL DEL PPPTO.PLAZO DE EJECUCIN : 180 DAS CALENDARIO
2 QUINCENA 1 QUINCENA 2 QUINCENA
150 165 180 120 Das
S/. 0.00 S/. 0.00 S/. 0.00 S/. 120,391.21
S/. 0.00 S/. 0.00 S/. 0.00 S/. 871.45
S/. 0.00 S/. 0.00 S/. 0.00 S/. 1,096.46
S/. 0.00 S/. 0.00 S/. 0.00 S/. 117,364.48
S/. 0.00 S/. 0.00 S/. 529.41 S/. 1,058.82S/. 54,570.99
S/. 0.00 S/. 0.00 S/. 0.00 S/. 461.96
S/. 0.00 S/. 0.00 S/. 0.00 S/. 29,370.77
S/. 0.00 S/. 0.00 S/. 0.00 S/. 1,159.76
S/. 0.00 S/. 0.00 S/. 0.00 S/. 22,073.16
S/. 0.00 S/. 0.00 S/. 0.00 S/. 1,505.34
S/. 0.00 S/. 0.00 S/. 0.00 S/. 21,444.94
S/. 0.00 S/. 0.00 S/. 0.00 S/. 204.52
S/. 0.00 S/. 0.00 S/. 0.00 S/. 115.54
S/. 0.00 S/. 0.00 S/. 0.00 S/. 7,491.93
S/. 0.00 S/. 0.00 S/. 0.00 S/. 12,527.60
S/. 0.00 S/. 0.00 S/. 0.00 S/. 727.92
S/. 0.00 S/. 0.00 S/. 0.00 S/. 377.43
S/. 0.00 S/. 0.00 S/. 0.00 S/. 17,278.98
S/. 0.00 S/. 0.00 S/. 0.00 S/. 126.24
S/. 0.00 S/. 0.00 S/. 0.00 S/. 402.64
S/. 0.00 S/. 0.00 S/. 0.00 S/. 1,464.83
S/. 0.00 S/. 0.00 S/. 0.00 S/. 11,055.13
S/. 0.00 S/. 0.00 S/. 0.00 S/. 1,284.34
S/. 0.00 S/. 0.00 S/. 0.00 S/. 2,945.80
S/. 0.00 S/. 0.00 S/. 0.00 S/. 316,012.96
S/. 0.00 S/. 0.00 S/. 0.00 S/. 9,984.00
S/. 0.00 S/. 0.00 S/. 0.00 S/. 162,766.58
S/. 0.00 S/. 0.00 S/. 0.00 S/. 129,584.00
S/. 0.00 S/. 0.00 S/. 0.00 S/. 6,731.18
S/. 0.00 S/. 0.00 S/. 0.00 S/. 6,947.20
S/. 0.00 S/. 0.00 S/. 0.00 S/. 58,567.64
S/. 0.00 S/. 0.00 S/. 0.00 S/. 2,588.77
S/. 0.00 S/. 0.00 S/. 0.00 S/. 25,899.41
S/. 0.00 S/. 0.00 S/. 0.00 S/. 19,458.98
S/. 0.00 S/. 0.00 S/. 0.00 S/. 3,601.77S/. 0.00 S/. 0.00 S/. 0.00 S/. 5,556.61
S/. 0.00 S/. 0.00 S/. 0.00 S/. 1,462.10
2,168,461.01S/.
PRESUPUESTO
PROGRAMADOES 6 MES
-
7/28/2019 CRONOGRAMA CANAL YAPAC - ALTERNATIVA N O1
6/18
MONTO TOTAL DEL PPPTO.
PLAZO DE EJECUCIN : 180 DAS CALENDARIO
2 QUINCENA 1 QUINCENA 2 QUINCENA
150 165 180 120 Das
2,168,461.01S/.
PRESUPUESTO
PROGRAMADOES 6 MES
S/. 0.00 S/. 0.00 S/. 0.00 S/. 30,017.70
S/. 0.00 S/. 0.00 S/. 0.00 S/. 30,376.19
S/. 0.00 S/. 0.00 S/. 0.00 S/. 3,601.77
S/. 5,556.61 S/. 0.00 S/. 0.00 S/. 5,556.61
S/. 1,326.70 S/. 0.00 S/. 0.00 S/. 1,326.70
S/. 0.00 S/. 0.00 S/. 0.00 S/. 242,550.52
S/. 2,462.30 S/. 820.77 S/. 0.00 S/. 8,207.68
S/. 7,372.83 S/. 0.00 S/. 0.00 S/. 73,728.27
S/. 0.00 S/. 0.00 S/. 0.00 S/. 7,565.33
S/. 0.00 S/. 0.00 S/. 0.00 S/. 14,247.72
S/. 0.00 S/. 0.00 S/. 0.00 S/. 18,317.21
S/. 36,145.29 S/. 48,193.72 S/. 0.00 S/. 120,484.31
S/. 0.00 S/. 0.00 S/. 0.00 S/. 467,026.68
S/. 0.00 S/. 0.00 S/. 0.00 S/. 30,088.80
S/. 17,189.70 S/. 0.00 S/. 0.00 S/. 171,896.99
S/. 46,734.30 S/. 46,734.30 S/. 11,683.57 S/. 233,671.48
S/. 1,147.73 S/. 765.16 S/. 382.58 S/. 3,825.78S/. 8,263.09 S/. 11,017.45 S/. 5,508.73 S/. 27,543.63
S/. 0.00 S/. 0.00 S/. 0.00 S/. 32,116.92
S/. 1,169.51 S/. 0.00 S/. 0.00 S/. 11,695.13
S/. 1,877.30 S/. 938.65 S/. 938.65 S/. 18,772.99
S/. 64.88 S/. 32.44 S/. 32.44 S/. 648.80
S/. 0.00 S/. 0.00 S/. 0.00 S/. 1,000.00
S/. 0.00 S/. 0.00 S/. 0.00 S/. 8,500.00
S/. 0.00 S/. 0.00 S/. 0.00 S/. 1,200.00
S/. 0.00 S/. 0.00 S/. 0.00 S/. 900.00
S/. 0.00 S/. 0.00 S/. 0.00 S/. 6,400.00
S/. 136,396.65 S/. 108,502.49 S/. 19,075.38 S/. 1,474,140.73
S/. 13,639.67 S/. 10,850.25 S/. 1,907.54 S/. 147,414.07
S/. 13,639.67 S/. 10,850.25 S/. 1,907.54 S/. 147,414.07
S/. 163,675.98 S/. 130,202.98 S/. 22,890.45 S/. 1,768,968.88
S/. 29,461.68 S/. 23,436.54 S/. 4,120.28 S/. 318,414.40
S/. 193,137.66 S/. 153,639.52 S/. 27,010.73 S/. 2,087,383.27
S/. 4,091.90 S/. 3,255.07 S/. 572.26 S/. 44,224.22
S/. 36,853.52
S/. 197,229.56 S/. 156,894.59 S/. 27,582.99 S/. 2,168,461.01
9.10 % 7.24 % 1.27 %
1 % 8.51 %91.49 % 100.00 %
-
7/28/2019 CRONOGRAMA CANAL YAPAC - ALTERNATIVA N O1
7/18
Item Descripcin UndMetr
ado
Precio
(S/.)Parcial (S/.)
BOCATOMA
01 OBRAS PROVISIONALES
01.01 CARTEL DE IDENTIFICACION DE OBRA01.02 ALMACEN DE OBRA Y GUARDIANIA
01.03 TRANSPORTE DE MAT. Y AGREGADOS
01.04 MOVILIZACION Y DESMOVILIZACION DE EQUIPO
02 MUROS DE ENCAUZAMIENTO
02.01 TRABAJOS PRELIMINARES
02.02 MOVIMIENTO DE TIERRAS
02.03 OBRAS DE CONCRETO SIMPLE
02.04 OBRAS DE CONCRETO ARMADO
02.05 REVOQUES Y ENLUCIDOS
03 PRESA DERIVADORA
03.01 TRABAJOS PRELIMINARES
03.02 MOVIMIENTO DE TIERRAS
03.03 OBRAS DE CONCRETO SIMPLE
03.04 OBRAS DE CONCRETO ARMADO03.05 REVOQUES Y ENLUCIDOS
03.06 VARIOS
04 TOMA O CAPTACION
04.01 TRABAJOS PRELIMINARES
04.02 MOVIMIENTO DE TIERRAS
04.03 OBRAS DE CONCRETO SIMPLE
04.04 OBRAS DE CONCRETO ARMADO
04.05 REVOQUES Y ENLUCIDOS
04.06 VARIOS
05 LINEA DE CONDUCCION
05.01 TRABAJOS PRELIMINARES
05.02 MOVIMIENTO DE TIERRAS
05.03 TENDIDO DE TUBERIAS EN LINEA DE CONDUCCION
05.04 ACCESORIOS PARA TUBERIAS05.05 PRUEBA HIDRAULICA
01 RESERVORIO DE GEOMENBRANA N 01
01.01 TRABAJOS PRELIMINARES
01.02 MOVIMIENTO DE TIERRAS
01.03 GEOMENBRANA
01.04 CAJA PARA VALVULAS
01.05 ACCESORIOS DE RESERVORIO
01.06 CERCO PERIMETRICO
02 RESERVORIO DE GEOMENBRANA N 02
02.01 TRABAJOS PRELIMINARES
02.02 MOVIMIENTO DE TIERRAS
02.03 GEOMENBRANA
02.04 CAJA PARA VALVULAS
02.05 ACCESORIOS DE RESERVORIO02.06 CERCO PERIMETRICO
3 RESERVORIO DE GEOMENBRANA N 03
02.01 TRABAJOS PRELIMINARES
02.02 MOVIMIENTO DE TIERRAS
02.03 GEOMENBRANA
02.04 CAJA PARA VALVULAS
02.05 ACCESORIOS DE RESERVORIO
02.06 CERCO PERIMETRICO
08 OBRAS DE ESTRUCTURAS HIDRAULICAS
-
7/28/2019 CRONOGRAMA CANAL YAPAC - ALTERNATIVA N O1
8/18
08.01 CAJA PARA VALVULAS DE CONTROL TIPO I (06 UNID)
08.04 CAMARA ROMPE PRESION (11 UNID)
08.05 CAMARA DISTRIBUIDORA DE CAUDALES ( 05 UNID.)
08.06 CAMARA PARA VALVULA REGULADORA DE PRESION TIPO I (08 UNID)
08.07 CAMARA PARA VALVULA DE PURGA TIPO I (12 UNID)
08.08 CAMARA PARA HIDRANTE (75 UNID)
09 RED DE DISTRIBUCION
09.01 TRABAJOS PRELIMINARES
09.02 MOVIMIENTO DE TIERRAS
09.03 TENDIDO DE TUBERIAS EN LINEA DE DISTRIBUCION
09.04 ACCESORIOS PARA TUBERIAS
09.05 PRUEBA HIDRAULICA
10 PLAN DE MANEJO AMBIENTAL
10.01 ACTIVIDADES DE PREVENCION
10.02 ACTIVIDADES DE MITIGACION
10.03 ACTIVIDADES DE MONITOREO
10.04 FLETE
11 CAPACITACION TECNICA
11.01 TRABAJOS DE CAMPO
11.02 CONVOCATORIA
11.03 DE LA CAPACITACION
-
7/28/2019 CRONOGRAMA CANAL YAPAC - ALTERNATIVA N O1
9/18
SUB PRES. PRES. TOTAL
213,686.12
120,391.21 120,391.21
871.451,096.46
117,364.48
1,058.82
54,570.99 54,570.99
461.96
29,370.77
1,159.76
22,073.16
1,505.34
21,444.94 21,444.94
204.52
115.54
7,491.93
12,527.60727.92
377.43
17,278.98 17,278.98
126.24
402.64
1,464.83
11,055.13
1,284.34
2,945.80
316,012.96 316,012.96
9,984.00
162,766.58
129,584.00
6,731.186,947.20
58,567.64 58,567.64
2,588.77
25,899.41
19,458.98
3,601.77
5,556.61
1,462.10
62,691.56 62,691.56
2,056.32
21,396.18
28,550.88
3,601.77
5,556.611,529.80
72,988.33 72,988.33
2,109.36
30,017.70
30,376.19
3,601.77
5,556.61
1,326.70
242,550.52 242,550.52
-
7/28/2019 CRONOGRAMA CANAL YAPAC - ALTERNATIVA N O1
10/18
8,207.68
73,728.27
7,565.33
14,247.72
18,317.21
120,484.31
467,026.68 467,026.68
30,088.80
171,896.99
233,671.48
3,825.78
27,543.63
32,116.92 32,116.92
11,695.13
18,772.99
648.80
1,000.00
8,500.00 8,500.00
1,200.00
900.00
6,400.00
1,474,140.73 1,474,140.73 1,474,140.73
-
7/28/2019 CRONOGRAMA CANAL YAPAC - ALTERNATIVA N O1
11/18
Item Descripcin Und Metrado Precio (S/.)
BOCATOMA
01 OBRAS PROVISIONALES
01.01 CARTEL DE IDENTIFICACION DE OBRA
01.02 ALMACEN DE OBRA Y GUARDIANIA
01.03 TRANSPORTE DE MAT. Y AGREGADOS
01.04 MOVILIZACION Y DESMOVILIZACION DE EQUIPO
02 MUROS DE ENCAUZAMIENTO
02.01 TRABAJOS PRELIMINARES
02.02 MOVIMIENTO DE TIERRAS
02.03 OBRAS DE CONCRETO SIMPLE
02.04 OBRAS DE CONCRETO ARMADO
02.05 REVOQUES Y ENLUCIDOS
03 PRESA DERIVADORA
03.01 TRABAJOS PRELIMINARES
03.02 MOVIMIENTO DE TIERRAS
03.03 OBRAS DE CONCRETO SIMPLE
03.04 OBRAS DE CONCRETO ARMADO
03.05 REVOQUES Y ENLUCIDOS
03.06 VARIOS04 TOMA O CAPTACION
04.01 TRABAJOS PRELIMINARES
04.02 MOVIMIENTO DE TIERRAS
04.03 OBRAS DE CONCRETO SIMPLE
04.04 OBRAS DE CONCRETO ARMADO
04.05 REVOQUES Y ENLUCIDOS
04.06 VARIOS
05 LINEA DE CONDUCCION
05.01 TRABAJOS PRELIMINARES
05.02 MOVIMIENTO DE TIERRAS
05.03 TENDIDO DE TUBERIAS EN LINEA DE CONDUCCION
05.04 ACCESORIOS PARA TUBERIAS
05.05 PRUEBA HIDRAULICA
01 RESERVORIO DE GEOMENBRANA N 0101.01 TRABAJOS PRELIMINARES
01.02 MOVIMIENTO DE TIERRAS
01.03 GEOMENBRANA
01.04 CAJA PARA VALVULAS
01.05 ACCESORIOS DE RESERVORIO
01.06 CERCO PERIMETRICO
02 RESERVORIO DE GEOMENBRANA N 02
02.01 TRABAJOS PRELIMINARES
02.02 MOVIMIENTO DE TIERRAS
02.03 GEOMENBRANA
02.04 CAJA PARA VALVULAS
02.05 ACCESORIOS DE RESERVORIO
02.06 CERCO PERIMETRICO
3 RESERVORIO DE GEOMENBRANA N 0302.01 TRABAJOS PRELIMINARES
02.02 MOVIMIENTO DE TIERRAS
02.03 GEOMENBRANA
02.04 CAJA PARA VALVULAS
02.05 ACCESORIOS DE RESERVORIO
02.06 CERCO PERIMETRICO
08 OBRAS DE ESTRUCTURAS HIDRAULICAS
08.01 CAJA PARA VALVULAS DE CONTROL TIPO I (06 UNID)
08.04 CAMARA ROMPE PRESION (11 UNID)
-
7/28/2019 CRONOGRAMA CANAL YAPAC - ALTERNATIVA N O1
12/18
08.05 CAMARA DISTRIBUIDORA DE CAUDALES ( 05 UNID.)
08.06 CAMARA PARA VALVULA REGULADORA DE PRESION TIPO I (08 UNID)
08.07 CAMARA PARA VALVULA DE PURGA TIPO I (12 UNID)
08.08 CAMARA PARA HIDRANTE (75 UNID)
09 RED DE DISTRIBUCION
09.01 TRABAJOS PRELIMINARES
09.02 MOVIMIENTO DE TIERRAS
09.03 TENDIDO DE TUBERIAS EN LINEA DE DISTRIBUCION09.04 ACCESORIOS PARA TUBERIAS
09.05 PRUEBA HIDRAULICA
10 PLAN DE MANEJO AMBIENTAL
10.01 ACTIVIDADES DE PREVENCION
10.02 ACTIVIDADES DE MITIGACION
10.03 ACTIVIDADES DE MONITOREO
10.04 FLETE
11 CAPACITACION TECNICA
11.01 TRABAJOS DE CAMPO
11.02 CONVOCATORIA
11.03 DE LA CAPACITACION
#REF!
COSTO DIRECTO 1,474,140.73
GASTOS GENERALES 10% 147,414.07
UTLIDAD 10% 147,414.07
=============
SUB TOTAL DEL PROYECTO 1,768,968.88
IGV 18% 318,414.40
=============
COSTO SUB TOTAL DEL PROYECTO 2,087,383.27
EXPEDIENTE TECNICO 2.5% 36,853.52
SUPERVISION 3% 44,224.22
=============
-
7/28/2019 CRONOGRAMA CANAL YAPAC - ALTERNATIVA N O1
13/18
PRESUPUESTO TOTAL DEL PROYECTO 2,168,461.01
-
7/28/2019 CRONOGRAMA CANAL YAPAC - ALTERNATIVA N O1
14/18
-
7/28/2019 CRONOGRAMA CANAL YAPAC - ALTERNATIVA N O1
15/18
Parcial (S/.) SUB PRES. PRES. TOTAL
213,686.12
120,391.21 120,391.21
871.45
1,096.46
117,364.48
1,058.82
54,570.99 54,570.99
461.96
29,370.77
1,159.76
22,073.16
1,505.34
21,444.94 21,444.94
204.52
115.54
7,491.93
12,527.60
727.92
377.43
17,278.98 17,278.98
126.24
402.64
1,464.83
11,055.13
1,284.34
2,945.80
316,012.96 316,012.96
9,984.00
162,766.58
129,584.00
6,731.18
6,947.20
58,567.64 58,567.64
2,588.77
25,899.41
19,458.98
3,601.77
5,556.61
1,462.10
62,691.56 62,691.56
2,056.32
21,396.18
28,550.88
3,601.77
5,556.61
1,529.80
72,988.33 72,988.33
2,109.36
30,017.70
30,376.19
3,601.77
5,556.61
1,326.70
242,550.52 242,550.52
8,207.68
73,728.27
-
7/28/2019 CRONOGRAMA CANAL YAPAC - ALTERNATIVA N O1
16/18
7,565.33
14,247.72
18,317.21
120,484.31
467,026.68 467,026.68
30,088.80
171,896.99
233,671.48
3,825.78
27,543.63
32,116.92 32,116.92
11,695.13
18,772.99
648.80
1,000.00
8,500.00 8,500.00
1,200.00
900.00
6,400.00
1,474,140.73 1,474,140.73 1,474,140.73
#REF! #REF!
1,474,140.73
147,414.07
147,414.07
=============
1,768,968.88
318,414.40
=============
2,087,383.27
36,853.52
44,224.22
=============
-
7/28/2019 CRONOGRAMA CANAL YAPAC - ALTERNATIVA N O1
17/18
2,168,461.01
Regin : Hunuco
Provincia : Ambo
Distrito : Colpas
Lugar : Yapac
COSTO DIRECTO 1,474,140.73
GASTOS
GENERALES
10%
147,414.07
UTLIDAD 10% 147,414.07
SUB TOTAL DEL
PROYECTO
1,768,968.88
IGV 18% 318,414.40
COSTO SUB
TOTAL DEL
PROYECTO
2,087,383.27
DESCRIPSION DEL COSTO
RESUMEN DE INVERSION
OBRA: INSTALACION DEL SERVICIO DE AGUA DEL SISTEMA
DE RIEGO EN LA
LOCALIDAD YAPAC-DISTRITO DE COLPAS, PROVINCIAAMBO, REGION HUANUCO
RESUMEN DE GASTOS DE INVERSION
-
7/28/2019 CRONOGRAMA CANAL YAPAC - ALTERNATIVA N O1
18/18
EXPEDIENTE
TECNICO 2.5%
36,853.52
SUPERVISION
3%
44,224.22
PRESUPUESTO
TOTAL DEL
PROYECTO
2,168,461.01
NOTA: Los costos Unitarios sin I.G.V. son Vigentes al: Mes de Febrero del 2