COMPUTOS METRICOS OBRA: ADECUACION INTEGRAL Y CONSTRUCCION DE INSTALACIONES PARA LA REUBICACION DE LA ECONOMIA INFORMAL. FECHA: PARTIDA N° DESCRIPCION MEDIDAS UND LARGO ANCHO ALTO OBRAS PRELIMINARES 1 E-113.S/C CONSTRUCCION DE CERCAS PROVISIONALES DE LAMINA DE ZINC 37.34 3.00 2.00 M2 30.00 3.00 2.00 M2 TOTAL M2 2 E-123.200.000 RELACIONADO M2 TALA Y DESRAIZAMIENTO DE ARBOLES CON ALTURA ENTRE 5 M Y 12 M. EN CANTIDADES MENORES DE 5 PZA POR HECTAREA. 7.00 PZA TOTAL EJECUTADO PZA 3 E-132.721.101 DEMOLICION A MANO DE CERCAS DE MALLA CICLON CON RECUPERACION. FRENTE PARCELA 34.00 ML. TOTAL EJECUTADO ML. 4 E-131.420.006 DEMOLICION A MANO DE PUERTAS METALICAS, AMONTONAMIENTO Y/O BOTE HASTA 200 MTS. PUERTAS PERIMETRALES 1.00 2.10 2.00 M2 PUERTAS INTERIORES 0.90 2.10 22.00 M2 TOTAL EJECUTADO M2 5 E-131.S/C DEMOLICION DE CUBIERTA DE TECHO DE LAMINAS METALICAS, INCLUYE AMONTONAMIENTO Y/O BOTE HASTA 200 MTS. PERGOLA 11.00 4.00 M2 TOTAL EJECUTADO M2 6 E-132.800.002 REMOCION A MANO O DESMONTAJE DE MARCOS EN GENERAL, SIN RECUPERACION DE MATERIALES. PUERTAS PERIMETRALES 4.00 PZA PUERTAS INTERIORES 22.00 PZA VENTANAS 4.00 PZA TOTAL EJECUTADO PZA 7 E-111.200.000 DEPOSITO 5.00 5.00 M2 TOTAL EJECUTADO M2 8 E-111.300.000 VESTUARIOS 4.00 4.00 M2 TOTAL EJECUTADO M2 9 E-111.400.000 BAÑOS 2.00 2.00 M2 TOTAL EJECUTADO M2 10 E-114.203.S/C ADUCCION PROVISIONAL DE AGUAS CLARAS CON TUBERIA DE PVC D= 3/4" 25.00 ML TOTAL EJECUTADO ML 11 DES024 DESMONTAJE DE LAMPARAS FLUORESCENTES. 50.00 PZA TOTAL EJECUTADO PZA 12 E-131.410.006 DEMOLICION DE IMPERMEABILIZACION, SIN RECUPERACION DE MATERIALES, SIN PENDIENTE DE MORTERO. MEDIDOS SEGÚN EL AREA DE PISO. AREA EDIFICACION 34.00 10.10 M2 TOTAL EJECUTADO M2 EMPRESA: . ELEMET IGUALES CONSTRUCCION PROVISIONAL CONVENCIONAL DE DEPOSITOS. INCLUYE LA ACOMETIDA PROVISIONAL DENTRO DEL AREA DE LA CONSTRUCCION. INCLUYE DE LOS MATERIALES HASTA 50 KM. CONSTRUCCION PROVISIONAL CONVENCIONAL DE VESTUARIOS Y CASETAS. INCLUYE LA ACOMETIDA PROVISIONAL DENTRO DEL AREA DE LA CONSTRUCCION TRANS. MATERIALES HASTA 50 KM. CONSTRUCCION PROVISIONAL CONVENCIONAL DE SANITARIOS.INCLUYE ACOMETIDA. INCLUYE LA ACOMETIDA PROVISIONAL DENTRO DEL AREA DE LA CONS INCLUYE TRANS. MATERIALES HASTA 50 KM. CONTRATO N° REPUBLICA BOLIVARIANA DE VENEZUELA ALCALDIA DEL MUNICIPIO GIRARDOT DIRECCION DE OBRAS PUBLICAS HABITAT VIVIENDA Y ASUNTOS SOCIALES

Transcript of computos-metricos-presupuesto.xls

COMPUTOS METRICOS

OBRA: ADECUACION INTEGRAL Y CONSTRUCCION DE INSTALACIONES PARA LA REUBICACION DE LA ECONOMIA INFORMAL.

FECHA:

PARTIDA N° DESCRIPCIONMEDIDAS

UNDLARGO ANCHO ALTO

OBRAS PRELIMINARES

1 E-113.S/C

CONSTRUCCION DE CERCAS PROVISIONALES DE LAMINA DE ZINC

37.34 3.00 2.00 M2 112.02

30.00 3.00 2.00 M2 180.00

TOTAL M2 292.02

2 E-123.200.000 RELACIONADO M2 292.00

TALA Y DESRAIZAMIENTO DE ARBOLES CON ALTURA ENTRE 5 M Y 12 M. EN CANTIDADES MENORES DE 5 PZA POR HECTAREA.

7.00 PZA 7.00

TOTAL EJECUTADO PZA 7.00

3 E-132.721.101

DEMOLICION A MANO DE CERCAS DE MALLA CICLON CON RECUPERACION.

FRENTE PARCELA 34.00 ML. 34.00

TOTAL EJECUTADO ML. 34.00

4 E-131.420.006

DEMOLICION A MANO DE PUERTAS METALICAS, AMONTONAMIENTO Y/O BOTE HASTA 200 MTS.

PUERTAS PERIMETRALES 1.00 2.10 2.00 M2 4.20

PUERTAS INTERIORES 0.90 2.10 22.00 M2 41.58

TOTAL EJECUTADO M2 45.78

5 E-131.S/C

DEMOLICION DE CUBIERTA DE TECHO DE LAMINAS METALICAS, INCLUYE AMONTONAMIENTO Y/O BOTE HASTA 200 MTS.

PERGOLA 11.00 4.00 M2 44.00

TOTAL EJECUTADO M2 44.00

6 E-132.800.002

REMOCION A MANO O DESMONTAJE DE MARCOS EN GENERAL, SIN RECUPERACION DE MATERIALES.

PUERTAS PERIMETRALES 4.00 PZA 4.00

PUERTAS INTERIORES 22.00 PZA 22.00

VENTANAS 4.00 PZA 4.00

TOTAL EJECUTADO PZA 30.00

7 E-111.200.000

DEPOSITO 5.00 5.00 M2 25.00

TOTAL EJECUTADO M2 25.00

8 E-111.300.000

VESTUARIOS 4.00 4.00 M2 16.00

TOTAL EJECUTADO M2 16.00

9 E-111.400.000

BAÑOS 2.00 2.00 M2 4.00

TOTAL EJECUTADO M2 4.00

10 E-114.203.S/C

ADUCCION PROVISIONAL DE AGUAS CLARAS CON TUBERIA DE PVC D= 3/4"

25.00 ML 25.00

TOTAL EJECUTADO ML 25.00

11 DES024

DESMONTAJE DE LAMPARAS FLUORESCENTES.

50.00 PZA 50.00

TOTAL EJECUTADO PZA 50.00

12 E-131.410.006

DEMOLICION DE IMPERMEABILIZACION, SIN RECUPERACION DE MATERIALES, SIN PENDIENTE DE MORTERO. MEDIDOS SEGÚN EL AREA DE PISO.

AREA EDIFICACION 34.00 10.10 M2 343.40

TOTAL EJECUTADO M2 343.40

EMPRESA: .

ELEMET IGUALES

CANT. TOTAL

CONSTRUCCION PROVISIONAL CONVENCIONAL DE DEPOSITOS. INCLUYE LA ACOMETIDA PROVISIONAL DENTRO DEL AREA DE LA CONSTRUCCION. INCLUYE EL TRANSPORTE DE LOS MATERIALES HASTA 50 KM.

CONSTRUCCION PROVISIONAL CONVENCIONAL DE VESTUARIOS Y CASETAS. INCLUYE LA ACOMETIDA PROVISIONAL DENTRO DEL AREA DE LA CONSTRUCCION. INCLUYE TRANS. MATERIALES HASTA 50 KM.

CONSTRUCCION PROVISIONAL CONVENCIONAL DE SANITARIOS.INCLUYE ACOMETIDA. INCLUYE LA ACOMETIDA PROVISIONAL DENTRO DEL AREA DE LA CONSTRUCCION. INCLUYE TRANS. MATERIALES HASTA 50 KM.

CONTRATO N°REPUBLICA BOLIVARIANA DE VENEZUELA

ALCALDIA DEL MUNICIPIO GIRARDOTDIRECCION DE OBRAS PUBLICAS

HABITAT VIVIENDA Y ASUNTOS SOCIALES

COMPUTOS METRICOS

OBRA: ADECUACION INTEGRAL Y CONSTRUCCION DE INSTALACIONES PARA LA REUBICACION DE LA ECONOMIA INFORMAL.

FECHA:

PARTIDA N° DESCRIPCIONMEDIDAS

UNDLARGO ANCHO ALTO

EMPRESA: .

ELEMET IGUALES

CANT. TOTAL

CONTRATO N°REPUBLICA BOLIVARIANA DE VENEZUELA

ALCALDIA DEL MUNICIPIO GIRARDOTDIRECCION DE OBRAS PUBLICAS

HABITAT VIVIENDA Y ASUNTOS SOCIALES

ING. RESIDENTE/CONTRATISTA FISCAL ING. INSPECTOR

13 E-131.410.008

DEMOLICION DE PENDIENTES DE MORTERO, SIN RECUPERACION DE MATERIALES, MEDIDOS SEGUN EL AREA DE PISO.

AREA EDIFICACION 34.00 10.10 M2 343.40

TOTAL EJECUTADO M2 343.40

14 E-132.112.S/C

DEMOLICION DE MIEMBROS HORIZONTALES DE CONCRETO ARMADO CON EQUIPO LIVIANO (COMPRESOR)

VIGAS DE CARGA 34.00 0.30 0.40 3.00 M3 12.24

VIGAS DE CARGA 10.10 0.30 0.40 6.00 M3 7.27

VIGAS DE CARGA 3.00 0.20 0.40 5.00 M3 1.20

ZAPATAS 1.20 1.20 0.30 12.00 M3 5.18

V.RIOSTRA 34.00 0.30 0.40 3.00 M3 12.24

V.RIOSTRA 10.10 0.30 0.40 6.00 M3 7.27

PEDESTALES 1.20 0.50 0.50 12.00 M3 3.60

ENTREPISO Y TECHO 34.00 10.10 0.20 2.00 M3 137.36

MESON DE COCINA 10.00 0.60 0.20 1.00 M3 1.20

ESCALERA 3.00 1.50 0.20 2.00 M3 1.80

ESCALERA 3.00 1.50 0.20 1.00 M3 0.90

TOTAL EJECUTADO M3 190.26

15 E-132.122.000

DEMOLICION DE MIEMBROS VERTICALES DE CONCRETO ARMADO CON EQUIPO LIVIANO (COMPRESOR)

COLUMNAS 8.00 0.50 0.50 12.00 M3 24.00

PEDESTALES 0.90 0.50 0.50 12.00 M3 2.70

MESON DE COCINA 0.60 0.15 0.90 8.00 M3 0.65

TANQUE SUBTERRANEO (PAREDES) 3.00 0.20 2.50 4.00 6.00

TOTAL EJECUTADO M3 33.35

16 E-132.310.000

DEMOLICION DE PIEZAS SANITARIAS.

LAVAMANOS 8.00 PZA 8.00

POCETAS 8.00 PZA 8.00

FREGADEROS 1.00 PZA 1.00

BATEAS 2.00 PZA 2.00

TOTAL EJECUTADO PZA 19.00

17 E-132.5.S/C

BAÑOS 5.00 2.40 8.00 M2 96.00

BAÑOS 2.00 2.40 16.00 M2 76.80

BAÑOS -0.80 2.10 8.00 M2 -13.44

COCINA 10.00 2.40 1.00 M2 24.00

TOTAL EJECUTADO M2 183.36

18 E-132.500.000

DEMOLICION A MANO DE PAREDES DE BLOQUES

PAREDES EXTERIORES 34.00 7.50 2.00 M2. 510.00

PAREDES EXTERIORES 10.10 7.50 2.00 M2. 151.50

PAREDES EXTERIORES -1.00 2.50 4.00 M2. -10.00

PAREDES EXTERIORES -1.00 2.10 2.00 M2. -4.20

PAREDES INTERIORES 34.00 3.50 2.00 M2. 238.00

PAREDES INTERIORES -34.50 0.40 M2. -13.80

PAREDES INTERIORES 5.00 3.50 13.00 M2. 227.50

PAREDES INTERIORES 3.00 3.50 2.00 M2. 21.00

PAREDES INTERIORES 6.00 1.20 M2. 7.20

TOTAL EJECUTADO M2. 1,127.20

19 E-132.620.012

DEMOLICION DE TUBERIAS DE CONCRETO DIAMETROS MENORES A 12".

50.00 ML 50.00

TOTAL EJECUTADO ML 50.00

DEMOLICION A MANO DE REVESTIMIENTO DE CERAMICA, BALDOSAS, MOSAICOS Y SIMILARES, EN PAREDES. INCLUYE AMONTONAMIENTO Y/O BOTE HASTA 200 MTS.-

COMPUTOS METRICOS

OBRA: ADECUACION INTEGRAL Y CONSTRUCCION DE INSTALACIONES PARA LA REUBICACION DE LA ECONOMIA INFORMAL.

FECHA:

PARTIDA N° DESCRIPCIONMEDIDAS

UNDLARGO ANCHO ALTO

EMPRESA: .

ELEMET IGUALES

CANT. TOTAL

CONTRATO N°REPUBLICA BOLIVARIANA DE VENEZUELA

ALCALDIA DEL MUNICIPIO GIRARDOTDIRECCION DE OBRAS PUBLICAS

HABITAT VIVIENDA Y ASUNTOS SOCIALES

ING. RESIDENTE/CONTRATISTA FISCAL ING. INSPECTOR

20 E-132.711.000

DEMOLICION A MANO DE CERCAS DE ALAMBRE DE PUAS. SIN RECUPERACION DE LOS MATERIALES.

PERIMETRO 88.20 ML 88.20

TOTAL EJECUTADO ML 88.20

21 E-132.801.000

DEMOLICION A MANO DE VENTANAS Y PUERTAS EN GENERAL SIN RECUPERACION DE MATERIALES.

34.50 0.40 M2 13.80

2.50 1.00 4.00 M2 10.00

TOTAL EJECUTADO M2 23.80

22 E-132.800.001

DEMOLICION A MANO DE REJAS Y BARANDAS, SIN RECUPERACION DE MATERIAL.

PUERTAS PERIMETRALES 1.00 2.10 2.00 M2 4.20

PUERTAS INTERIORES 0.90 2.10 22.00 M2 41.58

VENTANAS 34.50 0.40 M2 13.80

VENTANAS 2.50 1.00 4.00 M2 10.00

TOTAL EJECUTADO M2 69.58

23 E-132.S/C.3

REMOCION SIN RECUPERACION DE INSTALACIONES ELECTRICAS, (CABLES, TUBERIAS) INCLUYE CARGA Y BOTE HASTA 200 MTS.

800.00 ML 800.00

TOTAL EJECUTADO ML 800.00

24 E-133.110.000

DEMOLICION DE PAVIMENTO DE CONCRETO, CON EQUIPO LIVIANO/COMPRESOR.

AREA PARCELA 24.10 34.30 0.20 M3 165.33

AREA PARCELA 3.80 1.50 0.20 M3 1.14

BANCADA 80.00 0.96 0.20 M3 15.36

TOTAL EJECUTADO M3 181.83

25 E-133.420.000

DEMOLICION DE PAVIMENTO DE ASFALTO CON EQUIPO LIVIANO (COMPRESOR).

AREA PARCELA 24.10 34.30 0.15 M3 123.99

AREA PARCELA 3.80 1.50 0.15 M3 0.86

TOTAL EJECUTADO M3 124.85

26 E-133.710.002

DEMOLICION A MANO DE PISO DE CERAMICA, BALDOSA, MOSAICO Y SIMILAR.

PISOS INTERIORES DE LA VIVIENDA 34.00 10.00 2.00 M2 680.00

TOTAL EJECUTADO M2 680.00

27 E-141.02.S/C

DESMONTAJE DE CANAL GALVANIZADO DE AGUAS DE LLUVIA CON RECUPERACION DE LOS MATERIALES Y ALMACENAMIENTO.

CANALES EXISTENTES 34.00 2.00 ML 68.00

TOTAL EJECUTADO ML 68.00

28 E-141.901.002

REMOCION A MANO O DESMONTAJE DE BAJANTES DE AGUA DE LLUVIA DE LAMINA GALVANIZADA.

BAJANTES EXISTENTES 7.00 8.00 ML 56.00

28.00 2.00 ML 56.00

TOTAL EJECUTADO ML 112.00

COMPUTOS METRICOS

OBRA: ADECUACION INTEGRAL Y CONSTRUCCION DE INSTALACIONES PARA LA REUBICACION DE LA ECONOMIA INFORMAL.

FECHA:

PARTIDA N° DESCRIPCIONMEDIDAS

UNDLARGO ANCHO ALTO

EMPRESA: .

ELEMET IGUALES

CANT. TOTAL

CONTRATO N°REPUBLICA BOLIVARIANA DE VENEZUELA

ALCALDIA DEL MUNICIPIO GIRARDOTDIRECCION DE OBRAS PUBLICAS

HABITAT VIVIENDA Y ASUNTOS SOCIALES

ING. RESIDENTE/CONTRATISTA FISCAL ING. INSPECTOR

29 E-134.010.000

CARGA A MANO DEL MATERIAL, PROVENIENTE DE LAS DEMOLICIONES O PREPARACION DEL SITIO.

PUERTAS 45.78 0.05 1.20 M3 2.75

LAMPARAS (1.20X0.60X0.05 C/U= 0.036 M3/CU) 50.00 0.04 1.20 M3 2.40

IMPERMEABILIZACION Y MORTERO 343.40 0.05 1.20 M3 20.60

MIEMBROS HORIZONTALES 190.26 1.20 M3 228.31

MIEMBROS VERTICALES 33.35 1.20 M3 40.02

CERAMICA 183.36 0.01 1.20 M3 2.20

PAREDES 1127.20 0.19 1.20 M3 257.00

PAVIMENTO DE CONCRETO 181.83 1.20 M3 218.20

PAVIMENTO DE ASFALTO 124.85 1.20 M3 149.82

CERAMICA 680.00 0.01 1.20 M3 8.16

TALA DE ARBOLES D= 2 MTS A= 3.14 M2 7.00 12.00 3.14 1.20 M3 316.51

TOTAL EJECUTADO M3 1,245.97

ESTRUCTURAS30 H-INOS 221.21

RELLENO COMPACTADO CON MATERIAL DE PRESTAMO. INCLUYE EL SUMINISTRO DE MATERIAL DEL SAQUE LAS CABRAS Y EL ROYALTY

CAPA VEGETAL 24.10 34.30 0.70 M3 578.64

CAPA VEGETAL 3.80 1.50 0.70 M3 3.99

TOTAL EJECUTADO M2 582.63

31 E-311.110.150

EXCAVACION EN TIERRA A MANO PARA ASIENTO DE FUNDACIONES, ZANJAS U OTROS, HASTA PROFUNDIDADES COMPRENDIDAS ENTRE 0.00 Y 1.50 M.

FUNDACIONES F-1 1.50 1.50 1.25 8.00 M3 22.50

FUNDACIONES F-2 1.20 1.80 1.25 16.00 M3 43.20

RIOSTRA 33.80 0.30 0.45 4.00 M3 18.25

RIOSTRA 24.10 0.30 0.45 4.00 M3 13.01

BANCADAS 120.00 0.40 0.60 M3 28.80

ADUCCION A.B. 30.00 0.30 0.27 M3 2.43

CONEXIÓN A.N. 30.00 0.30 1.00 M3 9.00

BASE PARA PAD MOUNTED 10.00 10.00 0.36 M3 36.00

ATERRAMIENTO TABLEROS 0.80 0.80 1.87 M3 1.20

TUBERIAS 4" 110.53 0.30 0.40 M3 13.26

TUBERIAS 6" 82.36 0.30 0.50 M3 12.35

TOTAL EJECUTADO M3 200.00

32 E-311.310.000

EXCAVACION EN TIERRAS CON USO DE EQUIPO DE RETROEXCAVADOR PARA ASIENTO DE FUNDACIONES, ZANJAS U OTROS.(INCLUYE PERFILAMIENTO A MANO)

CAPA VEGETAL 24.10 34.30 0.50 M3 413.32

CAPA VEGETAL 3.80 1.50 0.50 M3 2.85

AREA DE CASA EXISTENTE 34.30 10.10 1.00 M3 346.43

TANQUE 3.50 3.50 3.10 M3 37.98

TOTAL EJECUTADO M3 800.58

33 E-313.110.000

CARGA A MANO DEL MATERIAL PROVENIENTE DE LAS EXCAVACIONES PARA ASIENTO DE FUNDACIONES, ZANJAS U OTROS.

137.20 1.18 M3 161.90

800.58 1.18 M3 944.68

TOTAL EJECUTADO M3 1,106.58

34 E-317.000.000

COMPACTACION DE RELLENO CON USO DE APISONADORES DE PERCUSION, CORRESPONDIENTES A LOS ASIENTOS DE FUNDACIONES, ZANJAS U OTROS.

CAPA VEGETAL 24.10 34.30 0.70 M3 578.64

CAPA VEGETAL 3.80 1.50 0.70 M3 3.99

COMPUTOS METRICOS

OBRA: ADECUACION INTEGRAL Y CONSTRUCCION DE INSTALACIONES PARA LA REUBICACION DE LA ECONOMIA INFORMAL.

FECHA:

PARTIDA N° DESCRIPCIONMEDIDAS

UNDLARGO ANCHO ALTO

EMPRESA: .

ELEMET IGUALES

CANT. TOTAL

CONTRATO N°REPUBLICA BOLIVARIANA DE VENEZUELA

ALCALDIA DEL MUNICIPIO GIRARDOTDIRECCION DE OBRAS PUBLICAS

HABITAT VIVIENDA Y ASUNTOS SOCIALES

TOTAL EJECUTADO M3 582.63

ING. RESIDENTE/CONTRATISTA FISCAL ING. INSPECTOR

COMPUTOS METRICOS

OBRA: ADECUACION INTEGRAL Y CONSTRUCCION DE INSTALACIONES PARA LA REUBICACION DE LA ECONOMIA INFORMAL.

FECHA:

PARTIDA N° DESCRIPCIONMEDIDAS

UNDLARGO ANCHO ALTO

35 E-319.100.000

BASE DE PAV 24.10 34.30 0.05 M3 41.33

BASE DE PAV 3.80 1.50 0.05 M3 0.29

ZAPATA F-1 1.50 1.50 0.05 8.00 M3 0.90

ZAPATA F-2 1.20 1.80 0.05 16.00 M3 1.73

TANQUE (PISO) 3.50 3.50 0.05 M3 0.61

RIOSTRA 33.80 0.30 0.05 4.00 M3 2.03

RIOSTRA 24.10 0.30 0.05 4.00 M3 1.45

TOTAL EJECUTADO M3 48.34

36 E-323.000.125

ZAPATA F-1 1.50 1.50 0.30 8.00 M3 5.40

ZAPATA F-2 1.20 1.80 0.30 16.00 M3 10.37

TOTAL EJECUTADO M3 15.77

37 E-324.000.125

PEDESTALES 0.90 0.50 0.50 24.00 M3 5.40

TOTAL EJECUTADO M3 5.40

38 E-325.000.125

RIOSTRA 33.80 0.30 0.40 4.00 M3 16.22

RIOSTRA 24.10 0.30 0.40 4.00 M3 11.57

TOTAL EJECUTADO M3 27.79

39 E-328.000.121

BASE DE PAV 24.10 34.30 0.15 M3 123.99

BASE DE PAV 3.80 1.50 0.15 M3 0.86

BASE PARA EL TANQUE 2.00 1.05 0.15 M3 0.32

BANCADA 80.00 0.96 0.20 M3 15.36

BASE PAD MOUNTED 1.95 1.45 0.15 M3 0.42

TOTAL EJECUTADO M3 140.95

40 E-391.2S/C2

S/T/C DE CUBIERTA DE TECHO CON LAMINA TIPO LUMETEX O SIMILAR COLOR BLANCO LA CARA INTERNA.

TECHO 24.60 34.80 M2 856.08

TECHO 3.80 1.50 M2 5.70

DESCUENTO CLARABOYA -20.28 7.67 M2 -155.55

TOTAL EJECUTADO M2 706.23

41 E-391.2.S/C.4

S/T/C DE CUBIERTA DE TECHO CON LAMINA DE POLICARBONATO E= 10 MM. INCLUYE ELEMENTOS DE SUJECIÓN.

CLARABOYA 21.78 9.17 M2 199.72

LATERALES CLARABOYA 21.78 0.40 2.00 M2 17.42

TOTAL EJECUTADO M2 217.14

EMPRESA: .

ELEMET IGUALES

CANT. TOTAL

CONSTRUCCION DE BASE DE PIEDRA PICADA CORRESPONDIENTE A OBRAS PREPARATIVAS. INCLUYE EL SUMINISTRO Y TRANSPORTE DEL MATERIAL HASTA UNA DISTANCIA DE 50 km.

CONCRETO DE Fc 250 Kgf/CM2 A LOS 28 DIAS ACABADO CORRIENTE, PARA LA CONSTRUCCION DE BASES Y ESCALONES. INCLUYE EL TRANSPORTE DEL CEMENTO Y AGREGADOS HASTA 50 KM Y EXCLUYE EL REFUERZO METALICO Y EL ENCOFRADO.

CONCRETO DE Fc 250 Kgf/CM2 A LOS 28 DIAS ACABADO CORRIENTE, PARA LA CONSTRUCCION DE PEDESTALES. INCLUYE EL TRANSPORTE DEL CEMENTO Y AGREGADOS HASTA 50 KM Y EXCLUYE EL REFUERZO METALICO Y EL ENCOFRADO.

CONCRETO DE Fc 250 Kgf/CM2 A LOS 28 DIAS ACABADO CORRIENTE, PARA LA CONSTRUCCION DE VIGAS RIOSTRA, TIRANTES Y FUNDACIONES DE PARED. INCLUYE EL TRANSPORTE DEL CEMENTO Y AGREGADOS HASTA 50 KM Y EXCLUYE EL REFUERZO METALICO Y EL ENCOFRADO.

CONCRETO DE FC= 210 Kgf/CM2 A LOS 28 DIAS, ACABADO CORRIENTE, PARA LA CONSTRUCCION DE BASE DE PAVIMENTO. INCLUYE TRANSPORTE DEL CEMENTO Y AGREGADOS HASTA 50 KM. Y EXCLUYE EL REFUERZO METALICO Y EL ENCOFRADO.

CONTRATO N°REPUBLICA BOLIVARIANA DE VENEZUELA

ALCALDIA DEL MUNICIPIO GIRARDOTDIRECCION DE OBRAS PUBLICAS

HABITAT VIVIENDA Y ASUNTOS SOCIALES

COMPUTOS METRICOS

OBRA: ADECUACION INTEGRAL Y CONSTRUCCION DE INSTALACIONES PARA LA REUBICACION DE LA ECONOMIA INFORMAL.

FECHA:

PARTIDA N° DESCRIPCIONMEDIDAS

UNDLARGO ANCHO ALTO

EMPRESA: .

ELEMET IGUALES

CANT. TOTAL

CONTRATO N°REPUBLICA BOLIVARIANA DE VENEZUELA

ALCALDIA DEL MUNICIPIO GIRARDOTDIRECCION DE OBRAS PUBLICAS

HABITAT VIVIENDA Y ASUNTOS SOCIALES

ING. RESIDENTE/CONTRATISTA FISCAL ING. INSPECTOR

42 E-334.000.121

MACHONES PARED PERIMETRAL (FRENTE) 4.00 0.15 0.20 6.00 M3 0.72

MACHONES PARED PERIMETRAL (LATERAL) 4.00 0.15 0.20 20.00 M3 2.40

MACHONES PARED PERIMETRAL (TRASERA) 4.00 0.15 0.20 6.00 M3 0.72

MACHONES PAREDES INTERIORES 4.50 0.15 0.20 11.00 M3 1.49

VIGA CORONA FRENTE 13.46 0.15 0.20 M3 0.40

VIGA CORONA CUARTO DE CAVAS 16.50 0.15 0.20 M3 0.50

VIGA CORONA BAÑOS 12.53 0.15 0.20 M3 0.38

VIGA CORONA CUARTO DE BASURA 8.00 0.15 0.20 M3 0.24

DINTEL DE PUERTA 1.20 0.15 0.20 6.00 M3 0.22

TOTAL EJECUTADO M3 7.07

43 E-339.000.125

TANQUE (PAREDES) 3.50 3.00 0.15 4.00 M3 6.30

TANQUE (PISO) 3.50 3.50 0.15 M3 1.84

TANQUE (TAPA) 3.50 3.50 0.15 M3 1.84

TANQUE (TAPA) -0.70 0.70 0.15 M3 -0.07

0.70 0.30 0.15 4.00 M3 0.13

PEDESTAL SIAMESA 0.60 0.50 1.00 0.30

TOTAL EJECUTADO M3 10.34

44 E-341.010.110

ZAPATA F-1 1.50 0.30 32.00 M2 14.40

ZAPATA F-2 1.20 0.30 32.00 M2 11.52

ZAPATA F-2 1.80 0.30 32.00 M2 17.28

PEDESTALES 0.90 0.50 96.00 M2 43.20

RIOSTRA 33.80 0.30 8.00 M2 81.12

RIOSTRA 24.10 0.30 8.00 M2 57.84

BASE DE PAV 24.10 0.15 2.00 M2 7.23

BASE DE PAV 34.30 0.15 2.00 M2 10.29

BASE DE PAV 3.80 0.15 2.00 M2 1.14

BASE DE PAV 1.50 0.15 2.00 M2 0.45

BASE PULMON HIDRONEUMATICO 4.00 0.15 M2 0.60

BASE PAD MOUNTED 6.80 0.15 M2 1.02

TOTAL EJECUTADO M2 246.09

45 E-342.010.114

ENCOFRADO DE MADERA, TIPO RECTO, ACABADO CORRIENTE, EN MACHONES, VIGAS DE CORONA, DINTELES Y ARRIOSTRAMIENTO DE PAREDES.

MACHONES PARED PERIMETRAL (FRENTE) 4.00 0.20 24.00 M2 19.20

MACHONES PARED PERIMETRAL (LATERAL) 4.00 0.20 80.00 M2 64.00

MACHONES PARED PERIMETRAL (TRASERA) 4.00 0.20 24.00 M2 19.20

MACHONES PAREDES INTERIORES 4.50 0.20 44.00 M2 39.60

VIGA CORONA FRENTE 13.46 0.20 2.00 M2 5.38

VIGA CORONA CUARTO DE CAVAS 16.50 0.20 2.00 M2 6.60

VIGA CORONA BAÑOS 12.53 0.20 2.00 M2 5.01

VIGA CORONA CUARTO DE BASURA 8.00 0.20 2.00 M2 3.20

DINTEL DE PUERTA 1.20 0.20 12.00 M2 2.88

TOTAL EJECUTADO M2 165.07

CONCRETO Fc 210 Kgf/CM2 , ACAB. CORRIENTE PARA LA CONSTRUCCION DE MACHONES Y VIGAS DECORONAS. INCLUYE TRANSPORTE DEL CEMENTO Y AGREGADOS HASTA 50 KM. Y EXCLUYE EL REFUERZO METALICO Y EL ENCOFRADO.

CONCRETO DE FC 250 Kgf/CM2, A LOS 28 DIAS ACABADO CORRIENTE, PARA LA CONSTRUCCION DE MUROS Y PANTALLAS. EXCLUYE EL REFUERZO METALICO Y EL ENCOFRADO.

ENCOFRADO DE MADERA, TIPO RECTO, ACABADO CORRIENTE, EN CABEZALES DE PILOTES, BASES Y ESCALONES, PEDESTALES, VIGA DE RIOSTRAS, TIRANTES, FUNDACIONES DE PARED, VIGAS DE FUNDACION, LOSA DE FUNDACION Y BASES DE PAVIMENTOS.

COMPUTOS METRICOS

OBRA: ADECUACION INTEGRAL Y CONSTRUCCION DE INSTALACIONES PARA LA REUBICACION DE LA ECONOMIA INFORMAL.

FECHA:

PARTIDA N° DESCRIPCIONMEDIDAS

UNDLARGO ANCHO ALTO

EMPRESA: .

ELEMET IGUALES

CANT. TOTAL

CONTRATO N°REPUBLICA BOLIVARIANA DE VENEZUELA

ALCALDIA DEL MUNICIPIO GIRARDOTDIRECCION DE OBRAS PUBLICAS

HABITAT VIVIENDA Y ASUNTOS SOCIALES

ING. RESIDENTE/CONTRATISTA FISCAL ING. INSPECTOR

46 E-342.010.119

ENCOFRADO DE MADERA, TIPO RECTO, ACABADO CORRIENTE, EN MUROS Y PANTALLAS.

TANQUE (PAREDES) 3.50 3.00 8.00 M2 84.00

TANQUE TAPA 3.50 3.50 M2 12.25

TANQUE (TAPA) -0.70 0.70 M2 -0.49

TANQUE (TAPA) 3.50 0.15 4.00 M2 2.10

0.85 0.30 8.00 M2 2.04

BASE PAD MOUNTED1.00 0.60 M2 0.60

1.00 0.50 2.00 M2 1.00

TOTAL EJECUTADO M2 101.50

47 E-351.110.210

ESTRIBOS PEDESTAL 1.70 0.559 216.00 KG 205.26

ESTRIBOS V.R. 1.10 0.559 1168.00 KG 718.20

BASE PAD MOUNTED1.45 0.559 14.00 KG 11.35

11.00 0.559 1.95 KG 11.99

TOTAL EJECUTADO KG 946.80

48 E-351.120.210

ZAPATAS F-1 1.60 1.554 176.00 KG 437.61

ZAPATAS F-2 1.90 1.554 208.00 KG 614.14

ZAPATAS F-3 1.30 1.554 144.00 KG 290.91

PEDESTAL 1.45 1.554 192.00 KG 432.63

V.R. 35.30 1.554 16.00 KG 877.70

V.R. 25.10 1.554 16.00 KG 624.09

TANQUE (REPARTICION) 15.60 1.554 30.00 M3 727.27

TANQUE (PRINCIPAL "U") 8.70 1.554 72.00 KG 973.43

TANQUE (TAPA) 4.40 1.554 72.00 KG 492.31

TANQUE (REFUERZO PAREDES EN "L") 2.10 1.554 70.00 KG 228.44

TOTAL EJECUTADO KG 5,698.53

49 E-351.200.250

PISO (PESO MALLA 1.996 KG/M2) 24.10 34.30 1.996 KG 1,649.95

PISO (PESO MALLA 1.996 KG/M2) 3.80 1.50 1.996 KG 11.38

BANCADA 80.00 0.96 1.996 KG 153.29

TOTAL EJECUTADO KG 1,814.62

50 E-352.110.210

ESTRIBOS MACHONES Y V.CORONA 0.60 0.559 1210.00 KG 405.83

TOTAL EJECUTADO KG 405.83

51 E-352.120.210

MACHONES PARED PERIMETRAL (FRENTE) 5.00 1.554 24.00 KG 186.48

MACHONES PARED PERIMETRAL (LATERAL) 5.00 1.554 80.00 KG 621.60

MACHONES PARED PERIMETRAL (TRASERA) 5.00 1.554 24.00 KG 186.48

MACHONES PAREDES INTERIORES 5.50 1.554 44.00 KG 376.07

VIGA CORONA FRENTE 16.46 1.554 4.00 KG 102.32

VIGA CORONA CUARTO DE CAVAS 18.50 1.554 4.00 KG 115.00

VIGA CORONA BAÑOS 14.53 1.554 4.00 KG 90.32

VIGA CORONA CUARTO DE BASURA 10.00 1.554 4.00 KG 62.16

DINTEL DE PUERTA 1.60 1.554 24.00 KG 59.67

SUMINISTRO, TRANSPORTE, PREPARACION Y COLOCACION DE ACERO DE REFUERZO FY= 4200 Kgf/CM2, UTILIZANDO CABILLA MENOR DEL Nº 3 PARA INFRAESTRUCTURA.INCLUYE TRANS. MATERIALES HASTA 50 KM.

SUMINISTRO, TRANSPORTE, PREPARACION Y COLOCACION DE ACERO DE REFUERZO FY= 4200 Kgf/CM2, UTILIZANDO CABILLAS Nº 4 A Nº 7, PARA INFRAESTRUCTURA. (1/2 A 7/8). INCLUYE TRANS. MATERIALES HASTA 50 KM

SUMINISTRO, TRANSPORTE, PREPARACION Y COLOCACIÓN DE MALLA SOLDADA DE ACERO, TIPO TRUCKSON. PARA INFRAESTRUCTURAS. INCLUYE TRANS. MATERIAL HASTA 50 KM.

SUMINISTRO, TRANSPORTE, PREPARACION Y COLOCACION DE ACERO DE REFUERZO FY 4200 Kgf/CM2, UTILIZANDO CABILLAS DE DIAMETRO INFERIOR AL Nº 3 PARA SUPERESTRUCTURA. INCLUYE TRANS. MATERIALES HASTA 50 KM.

SUMINISTRO, TRANSPORTE, PREPARACION Y COLOCACION DE ACERO DE REFUERZO FY 4200 kgf/cm2, UTILIZANDO CABILLAS DE DIAMETRO DE 1/2" A 7/8" PARA SUPERESTRUCTURA. INCLUYE TRANS. MATERIALES HASTA 50 KM.

COMPUTOS METRICOS

OBRA: ADECUACION INTEGRAL Y CONSTRUCCION DE INSTALACIONES PARA LA REUBICACION DE LA ECONOMIA INFORMAL.

FECHA:

PARTIDA N° DESCRIPCIONMEDIDAS

UNDLARGO ANCHO ALTO

EMPRESA: .

ELEMET IGUALES

CANT. TOTAL

CONTRATO N°REPUBLICA BOLIVARIANA DE VENEZUELA

ALCALDIA DEL MUNICIPIO GIRARDOTDIRECCION DE OBRAS PUBLICAS

HABITAT VIVIENDA Y ASUNTOS SOCIALES

TOTAL EJECUTADO KG 1,800.10

ING. RESIDENTE/CONTRATISTA FISCAL ING. INSPECTOR

52 E-361.124.S/C.3

S/T/C DE ANCLAJES COMPUESTOS POR LAMINAS METALICAS E= 16 MM Y PERNOS 5/8" X 0.75 MTS DE LONGITUD CON TUERCAS (40.00 CMS X 40.00 CMS)

24.00 PZA 24.00

TOTAL EJECUTADO PZA 24.00

53 E-362.330.S/C

CORREAS (ECO 140X60 PESO= 8.89 KG/M) 6.56 8.89 30.00 KG 1,749.55

CORREAS (ECO 140X60 PESO= 8.89 KG/M) 7.58 8.89 10.00 KG 673.86

CORREAS (ECO 140X60 PESO= 8.89 KG/M) 1.20 8.89 4.00 KG 42.67

CORREAS (ECO 140X60 PESO= 8.89 KG/M) 2.51 8.89 4.00 KG 89.26

CORREAS (ECO 140X60 PESO= 8.89 KG/M) 3.79 8.89 4.00 KG 134.77

CORREAS (ECO 140X60 PESO= 8.89 KG/M) 5.07 8.89 4.00 KG 180.29

CORREAS (ECO 140X60 PESO= 8.89 KG/M) 6.35 8.89 4.00 KG 225.81

CORREAS (ECO 140X60 PESO= 8.89 KG/M) 5.55 8.89 4.00 KG 197.36

CORREAS (ECO 140X60 PESO= 8.89 KG/M) 4.43 8.89 4.00 KG 157.53

CORREAS (ECO 140X60 PESO= 8.89 KG/M) 3.30 8.89 4.00 KG 117.35

CORREAS (ECO 140X60 PESO= 8.89 KG/M) 2.17 8.89 4.00 KG 77.17

CORREAS (ECO 140X60 PESO= 8.89 KG/M) 1.05 8.89 4.00 KG 37.34

TOTAL EJECUTADO KG 3,682.96

54 E-362.110.500

COLUMNAS EJES A Y D (ECO 200X200 PESO= 52.36 KG/M) 52.36 4.00 12.00 KG 2,513.28

COLUMNAS EJES B Y C (ECO 200X200 PESO= 52.36 KG/M) 52.36 5.70 12.00 KG 3,581.42

52.36 0.60 12.00 KG 376.99

TOTAL EJECUTADO KG 6,471.69

55 E-362.120.300

7.47 20.72 8.00 KG 1,238.23

6.56 20.72 10.00 KG 1,359.23

CARTELAS (ECO 220X90 PESO= 20.72 KG/M) 0.50 20.72 32.00 KG 331.52

VIGAS 6A-5B, 6D-5C, 1A-2B, 1D-2C (ECO 260X90 PESO= 28.46 KG/M) 10.03 28.46 4.00 KG 1,141.82

CARTELAS (ECO 260X90 PESO= 28.46 KG/M) 0.50 28.46 8.00 KG 113.84

VIGAS EJE A Y EJE D Y EJES B Y C (ECO 180X65 PESO= 14.45 KG/M) 6.56 14.45 16.00 KG 1,516.67

VIGAS EJES 1, 2, 5 Y 6 (ECO 180X65 PESO= 14.45 KG/M) 7.47 14.45 8.00 KG 863.53

VIGA CLARABOYA EJES 2 Y 5 (ECO 180X65 PESO= 14.45 KG/M) 7.47 14.45 2.00 KG 215.88

VIGA CLARABOYA EJES B Y C (PERFIL ECO 220X90 PESO= 20.72 KG/M) 6.56 20.72 6.00 KG 815.54

VIGA CLARABOYA alero (PERFIL ECO 220X90 PESO= 20.72 KG/M) 1.50 20.72 4.00 KG 124.32

TOTAL EJECUTADO KG 7,720.58

56 E-361.615.S/C

S/T/C DE ANCLAJES COMPUESTOS POR LAMINAS METALICAS E= 5 MM Y CABILLA DE 3/8" DE (15,00 CMS X 15,00 CMS)

20.00 PZA 20.00

TOTAL EJECUTADO PZA 20.00

57 E-JUNTA WATERS/T/C DE JUNTA WATER STOP

PAREDES DE TANQUE 3.50 8.00 28.00

TOTAL EJECUTADO ML 28.00

SUMINISTRO, CONFECCION Y COLOCACION DE TUBOS ESTRUCTURALES CONDUVEN EN CORREAS. INCLUYE GRUA Y EL TRANSPORTE DE LOS ELEMENTOS HASTA 50 KM.

SSUMINISTRO, CONFECCION Y COLOCACION EN ESTRUCTURA METALICA DE COLUMNAS SIMPLES CON PERFIL FORMADO EN FRIO (CONDUVEN). INCLUYE GRUA Y EL TRANSPORTE DE LOS ELEMENTOS HASTA 50 KM.

COLUMNAS EJES B Y C. NIVEL CLARABOYA (ECO 200X200 PESO= 52.36 KG/M)

SUMINISTRO, CONFECCION Y COLOCACION EN ESTRUCTURA METALICA DE VIGAS CONDUVEN. INCLUYE GRUA Y EL TRANSPORTE DE LOS ELEMENTOS HASTA 50 KM.

VIGAS 2-AB, 2-CD, 3-AB, 3-BC, 4-AB, 4-BC, 5-AB, 5-BC (ECO 220X90 PESO= 20.72 KG/M)

VIGAS B-56, C-56, B-45, C-45, B-34, C-34, B-23, C-23, B-12, C-12 (ECO 220X90 PESO= 20.72 KG/M)

COMPUTOS METRICOS

OBRA: ADECUACION INTEGRAL Y CONSTRUCCION DE INSTALACIONES PARA LA REUBICACION DE LA ECONOMIA INFORMAL.

FECHA:

PARTIDA N° DESCRIPCIONMEDIDAS

UNDLARGO ANCHO ALTO

EMPRESA: .

ELEMET IGUALES

CANT. TOTAL

CONTRATO N°REPUBLICA BOLIVARIANA DE VENEZUELA

ALCALDIA DEL MUNICIPIO GIRARDOTDIRECCION DE OBRAS PUBLICAS

HABITAT VIVIENDA Y ASUNTOS SOCIALES

ING. RESIDENTE/CONTRATISTA FISCAL ING. INSPECTOR

COMPUTOS METRICOS

OBRA: ADECUACION INTEGRAL Y CONSTRUCCION DE INSTALACIONES PARA LA REUBICACION DE LA ECONOMIA INFORMAL.

FECHA:

PARTIDA N° DESCRIPCIONMEDIDAS

UNDLARGO ANCHO ALTO

ARQUITECTURA

58 E-411.042.015

PERIMETRAL 24.10 4.00 M2 96.40

PERIMETRAL 25.60 4.00 M2 102.40

PERIMETRAL 34.30 4.00 2.00 M2 274.40

PERIMETRAL 1.50 4.00 M2 6.00

PERIMETRAL -1.20 2.10 2.00 M2 -5.04

PERIMETRAL (DCTO.) -5.00 2.80 M2 -14.00

PERIMETRAL (DCTO.) -4.00 2.80 2.00 M2 -22.40

BAÑO 9.00 4.70 M2 42.30

BAÑO 3.60 4.70 M2 16.92

BAÑO 2.50 4.70 2.00 M2 23.50

BAÑO (DCTO. ENTRADA) -2.00 2.10 M2 -4.20

DEPOSITO BASURA+CUARTO DE BOMBA 4.25 2.70 M2 11.48

DEPOSITO BASURA+CUARTO DE BOMBA 2.20 4.70 2.00 M2 20.68

DEPOSITO BASURA+CUARTO DE BOMBA -0.80 2.10 M2 -1.68

DEPOSITO BASURA+CUARTO DE BOMBA -1.20 2.10 M2 -2.52

CUARTO DE CAVAS 13.20 4.00 M2 52.80

CUARTO DE CAVAS 3.35 4.70 M2 15.75

CUARTO DE CAVAS -1.20 2.10 M2 -2.52

TOTAL EJECUTADO M2 610.27

59 E-412.202.003

CONSTRUCCION DE REVESTIMIENTO INTERIOR EN PAREDES, CON MORTERO A BASE DE CAL, ACABADO LISO. INCLUYE FRISO BASE DE 0 A 3 NIVELES.

PERIMETRAL 24.10 4.00 M2 96.40

PERIMETRAL (DCTO PTA) -1.20 2.10 2.00 M2 -5.04

PERIMETRAL (DCTO PORTON) -5.00 2.80 M2 -14.00

PERIMETRAL (DCTO PORTON) -4.00 2.80 2.00 M2 -22.40

PERIMETRAL TRASERA 22.00 4.00 M2 88.00

PERIMETRAL LATERAL IZQ 27.23 4.00 M2 108.92

PERIMETRAL LATERAL IZQ 1.50 4.00 M2 6.00

CUARTO DE BOMBA Y BASURA 7.07 4.70 2.00 M2 66.46

CUARTO DE BOMBA Y BASURA 2.05 4.70 4.00 M2 38.54

CUARTO DE BOMBA (DCTO) -0.90 2.10 4.00 M2 -7.56

PERIMETRAL LATERAL DER. 34.30 4.00 M2 137.20

BAÑO (FRENTE) 3.21 4.70 2.00 M2 30.17

BAÑO 3.21 2.20 4.00 M2 28.25

BAÑO 3.53 2.20 4.00 M2 31.06

BAÑO 2.20 2.20 4.00 M2 19.36

BAÑO 2.20 4.70 1.00 M2 10.34

CUARTO DE CAVAS 13.12 4.70 2.00 M2 123.33

CUARTO DE CAVAS 3.35 4.70 2.00 M2 31.49

CUARTO DE CAVAS -1.20 2.10 2.00 M2 -5.04

TOTAL EJECUTADO M2 761.48

60 E-412.202.001

PERIMETRAL 24.10 4.00 M2 96.40

PERIMETRAL -1.20 2.10 2.00 M2 -5.04

PERIMETRAL -5.00 2.80 M2 -14.00

PERIMETRAL -4.00 2.80 2.00 M2 -22.40

PERIMETRAL TRASERA 24.10 1.20 M2 28.92

PERIMETRAL LATERAL 34.30 1.20 2.00 M2 82.32

TOTAL EJECUTADO M2 166.20

61 E-412.103.003

CONSTRUCCION DE REVESTIMIENTO INTERIOR EN PAREDES, CON MORTERO HIDROFUGO, ACABADO LISO. INCLUYE FRISO BASE.

TANQUE (PAREDES) 3.50 3.00 4.00 M2 42.00

TANQUE PISO 3.50 3.50 M2 12.25

TOTAL EJECUTADO M2 54.25

EMPRESA: .

ELEMET IGUALES

CANT. TOTAL

CONSTRUCCION DE PAREDES DE BLOQUE DE CONCRETO, ACABADO OBRA LIMPIA POR UNA CARA, E=15 CM. NO INCLUYE MACHONES, DINTELES, BROCALES. INCLUYE TRANSPORTE DE LOS MATERIALES HASTA 50 KM.

CONSTRUCCION DE REVESTIMIENTO EXTERIOR EN PAREDES CON MORTERO A BASE DE CAL, ACABADO RUSTICO. INCLUYE FRISO BASE DE 0 A 3 NIVELES CON ALTURA SUPERIOR A 3 MTS.

CONTRATO N°REPUBLICA BOLIVARIANA DE VENEZUELA

ALCALDIA DEL MUNICIPIO GIRARDOTDIRECCION DE OBRAS PUBLICAS

HABITAT VIVIENDA Y ASUNTOS SOCIALES

COMPUTOS METRICOS

OBRA: ADECUACION INTEGRAL Y CONSTRUCCION DE INSTALACIONES PARA LA REUBICACION DE LA ECONOMIA INFORMAL.

FECHA:

PARTIDA N° DESCRIPCIONMEDIDAS

UNDLARGO ANCHO ALTO

EMPRESA: .

ELEMET IGUALES

CANT. TOTAL

CONTRATO N°REPUBLICA BOLIVARIANA DE VENEZUELA

ALCALDIA DEL MUNICIPIO GIRARDOTDIRECCION DE OBRAS PUBLICAS

HABITAT VIVIENDA Y ASUNTOS SOCIALES

ING. RESIDENTE/CONTRATISTA FISCAL ING. INSPECTOR

62 E-412.111.006

CONSTRUCCION DE REVESTIMIENTO INTERIOR EN PAREDES CON BALDOSA DE CERAMICAS NACIONAL, ACABADO NATURAL. INCLUYE FRISO BASE.

BAÑOS 3.60 2.50 2.00 M2 18.00

BAÑOS 2.80 2.50 2.00 M2 14.00

BAÑOS 2.50 2.50 1.00 M2 6.25

BAÑOS 9.00 2.50 1.00 M2 22.50

BAÑOS 3.25 2.50 2.00 M2 16.25

AREAS DE SERVICIO 3.60 2.50 2.00 M2 18.00

TOTAL EJECUTADO M2 95.00

63 E-415.S/C

SUMINISTRO, TRANSPORTE E INSTALACION DE TOPE DE GRANITO NATURAL O SIMILAR, ACABADO PULIDO, SIN JUNTAS. INCLUYE MORTERO BASE.

BAÑOS 1.80 2.00 ML 3.60

TOTAL EJECUTADO ML 3.60

64 E-X-EMBONADO

EMBONADO DE VIGAS Y COLUMNAS METALICAS INCLUYE EL EMPLEO DE MALLA GALLINERO.

COLUMNAS CENTRALES 2.00 1.20 6.00 M2 14.40

EMBONADO DE BAJANTES 1.00 6.00 2.00 M2 12.00

TOTAL EJECUTADO M2 26.40

65 E-414.094.050

BAÑOS 9.00 3.60 M2 32.40

TOTAL EJECUTADO M2 32.40

66 E-SIKAFLOOR 3 QUARTZ

SUMINISTRO, TRANSPORTE Y APLICACION DE ADITIVO SIKAFLOOR QUARTZ.

AREA TOTAL PISO 24.10 34.30 M2 826.63

AREA TOTAL PISO 3.80 1.50 M2 5.70

DCTO BAÑOS -9.00 3.60 M2 -32.40

TOTAL EJECUTADO M2 799.93

67 E-SIKACURE

SUMINISTRO, TRANSPORTE Y APLICACION DE ADITIVO SIKACURE.

AREA TOTAL PISO 24.10 34.30 M2 826.63

AREA TOTAL PISO 3.80 1.50 M2 5.70

DCTO BAÑOS -9.00 3.60 M2 -32.40

TOTAL EJECUTADO M2 799.93

68 E-437.011.S/C.01

ACCESOS 1.20 2.10 2.00 M2 5.04

TOTAL EJECUTADO M2 5.04

69 E-474.522.S/C

SUMINISTRO E INSTALACION DE CERRADURA PARA PUERTA DE SEGURIDAD (MULTILOCK).

ACCESOS 2.00 PZA 2.00

TOTAL EJECUTADO PZA 2.00

70 E-437.011.S/C.02

BAÑOS 0.90 2.10 2.00 M2 3.78

TOTAL EJECUTADO M2 3.78

CONSTRUCCION DE REVESTIMIENTO INTERIOR EN PISOS CON CERAMICAS NACIONAL, ACABADO NATURAL. INCLUYE FRISO BASE.TRANS. MATERIAL HASTA 50 KM.

SUMINISTRO, TRANSPORTE Y COLOCACION DE PUERTAS DE SEGURIDAD BATIENTES DE LAMINA ENTAMBORADAS DE HIERRO Y VISOR 40x13 CM. INCLUYE ACRILICO TRANSPARENTE CON PAÑO FIJO Y TRANS. MATERIALES HASTA 50 KM.

SUMINISTRO, TRANSPORTE Y COLOCACION DE PUERTAS BATIENTES DE LAMINA ENTAMBORADA DE HIERRO Y VISOR LATERAL DE 1.45x22 CM, INCLUYE VIDRIO CON PAÑO FIJO Y TRANS. MATERIALES HASTA 50 KM.

COMPUTOS METRICOS

OBRA: ADECUACION INTEGRAL Y CONSTRUCCION DE INSTALACIONES PARA LA REUBICACION DE LA ECONOMIA INFORMAL.

FECHA:

PARTIDA N° DESCRIPCIONMEDIDAS

UNDLARGO ANCHO ALTO

EMPRESA: .

ELEMET IGUALES

CANT. TOTAL

CONTRATO N°REPUBLICA BOLIVARIANA DE VENEZUELA

ALCALDIA DEL MUNICIPIO GIRARDOTDIRECCION DE OBRAS PUBLICAS

HABITAT VIVIENDA Y ASUNTOS SOCIALES

ING. RESIDENTE/CONTRATISTA FISCAL ING. INSPECTOR

ING. RESIDENTE/CONTRATISTA FISCAL ING. INSPECTOR E-437.011.S/C

S/T/C DE PUERTAS ENTAMBORADAS DE HIERRO Y ROMANILLA, INCLUYE TRANSPORTE DE MATERIAL HASTA 50 KM.

CUARTO DE BOMBA 0.90 2.10 M2 1.89

CUARTO DE BASURA 1.20 2.10 M2 2.52

TOTAL EJECUTADO M2 4.41

72 E-437.015.S/C

SUMINISTRO, TRANSPORTE Y COLOCACION DE PUERTA METALICA ARROLLABLE MICROPERFORADO.

4.00 2.80 2.00 M2 22.40

5.00 2.80 1.00 M2 14.00

TOTAL EJECUTADO M2 36.40

73 E-437.037.S/C

2.50 2.00 2.00 M2 10.00

1.18 2.00 4.00 M2 9.44

0.90 2.00 2.00 M2 3.60

TOTAL EJECUTADO M2 23.04

74 E-437-1-S/C4

S/T/C DE PUERTA CON PANEL PREFABRICADO INYECTADO EN POLIURETANO (DENS=40 KG/M3), CON CARAS EN FIBRA.

CAVAS 1.20 2.10 M2 2.52

TOTAL EJECUTADO M2 2.52

75 E-473.632.253

7.00 PZA 7.00

TOTAL EJECUTADO PZA 7.00

76 E-437.028.S/C

SUMINISTRO, TRANSPORTE Y COLOCACION DE VENTANAS DE ROMANILLA PARA INCLUYE MARCO DE TUBO DE 2x1. INCLUYE TRANS. MATERIALES HASTA 50 KM.

0.30 0.70 8.00 M2 1.68

0.30 0.75 2.00 M2 0.45

0.30 0.70 2.00 M2 0.42

0.30 0.90 2.00 M2 0.54

0.30 0.20 2.00 M2 0.12

0.50 0.70 12.00 M2 4.20

1.00 0.70 2.00 M2 1.40

TOTAL EJECUTADO M2 8.81

77 E-437.024.S/C

SUMINISTRO, TRANSPORTE Y COLOCACION DE VENTANAS EN LAMINA METALICA PERFORADA. INCLUYE TRANS. MATERIALES HASTA 50 KM.

1.20 0.70 4.00 M2 3.36

1.20 0.90 2.00 M2 2.16

1.20 0.60 2.00 M2 1.44

2.74 0.70 4.00 M2 7.67

2.60 0.70 8.00 M2 14.56

TOTAL EJECUTADO M2 29.19

78 E-PANTALLA

25.00 0.90 M2 22.50

TOTAL EJECUTADO M2 22.50

79 E-394.022.062

LATERALES 32.40 2.00 ML 64.80

FRENTE Y POSTERIOR 24.10 2.00 ML 48.20

SUMINISTRO, TRANSPORTE Y COLOCACION DE TABIQUES METALICOS DE LAMINA SENCILLA. MEDIDO SEGUN AREA EFECTIVA DEL TABIQUE. INCLUYE PUERTAS Y TRANS. MATERIALES HASTA 50 KM.

CERRADURA DE EMBUTIR, ACABADO DE ACERO NIQUELADO, CILINDRO MOVIL, CERROJO SIMPLE, PESTILLO SIMPLE. AMBOS LADOS CON LLAVE. DISTANCIA DEL CILINDRO AL BORDE 35 MM. (MOD: YALE 52111 35 MM)

SUMINISTRO, TRANSPORTE, CONFECCION Y COLOCACION DE PANTALLA ELABORADA CON LAMINA METALICA. INCLUYE TRANSPORTE DE LOS MATERIALES HASTA 50 KM.

SUMINISTRO, TRANSPORTE Y COLOCACION DE CANAL DE AGUAS DE LLUVIAS CON LAMINA GALVANIZADA, CAL. 22; CON 62 CM. DE DESARROLLO. INCLUYE TRANS. HASTA 50 KM.

COMPUTOS METRICOS

OBRA: ADECUACION INTEGRAL Y CONSTRUCCION DE INSTALACIONES PARA LA REUBICACION DE LA ECONOMIA INFORMAL.

FECHA:

PARTIDA N° DESCRIPCIONMEDIDAS

UNDLARGO ANCHO ALTO

EMPRESA: .

ELEMET IGUALES

CANT. TOTAL

CONTRATO N°REPUBLICA BOLIVARIANA DE VENEZUELA

ALCALDIA DEL MUNICIPIO GIRARDOTDIRECCION DE OBRAS PUBLICAS

HABITAT VIVIENDA Y ASUNTOS SOCIALES

TOTAL EJECUTADO ML 113.00

ING. RESIDENTE/CONTRATISTA FISCAL ING. INSPECTOR

80 E-437.071.015

MARCO DE HIERRO, CAL. 18 PARA PARED, E= 15 CMS CON BISAGRA 3". INCLUYE TRANS. MATERIALES HASTA 50 KM.

5.40 4.00 M2 21.60

5.10 3.00 M2 15.30

TOTAL EJECUTADO M2 36.90

81 E-362.000.S/C.01

S/T/P/C DE ANGULOS METALICOS DE 50 X 5 MM.

ANGULO EN COLUMNAS 4.00 3.77 64.00 KG 965.12

ANGULO EN VIGAS 24.00 3.77 2.00 KG 180.96

ANGULO EN VIGAS 34.00 3.77 2.00 KG 256.36

TOTAL EJECUTADO KG 1,402.44

82 E-437.057.S/C3

S/T/C DE TUBO DE HIERRO DE 2 x 1 1/2". INCLUYE FONDO ANTICORROSIVO.

PERFIL 2 X 1 1/2" 21.78 4.00 ML 87.12

PERFIL 2 X 1 1/2" 9.17 4.00 ML 36.68

PERFIL 2 X 1 1/2" 0.60 4.00 ML 2.40

TOTAL EJECUTADO ML 126.20

83 E-665.150.020

SUMINISTRO, TRANSPORTE Y COLOCACION DE ESPEJO PARA BAÑO. INCLUYE TRANS. MATERIAL HASTA 50 KM.

2.00 PZA 2.00

TOTAL EJECUTADO PZA 2.00

84 E-412.119.007

RODAPIE DE VINYL.

PERIMETRAL 34.30 2.00 ML 68.60

PERIMETRAL 24.10 2.00 ML 48.20

BAÑO 3.21 3.00 ML 9.63

CTO CAVAS 13.12 2.00 ML 26.24

CTO CAVAS 3.35 2.00 ML 6.70

CTO BOMBAS 7.07 2.00 ML 14.14

CTO BOMBAS 2.05 4.00 ML 8.20

TOTAL EJECUTADO ML 181.71

85 E-461.000.101

ESMALTE EN COLUMNAS METALICAS. INCLUYE TRANS. MATERIAL HASTA 50 KM.

COLUMNAS EJES A Y D (ECO 200X200) 4.00 0.80 12.00 M2 38.40

COLUMNAS EJES B Y C (ECO 200X200) 5.70 0.80 12.00 M2 54.72

COLUMNAS EJES B Y C. NIVEL CLARABOYA (ECO 200X200) 0.60 0.80 12.00 M2 5.76

TOTAL EJECUTADO M2 98.88

86 E-461.000.101

ESMALTE EN VIGAS METALICAS DE ALMA LLENA. INCLUYE TRANS. MATERIAL HASTA 50 KM.

VIGAS 2-AB, 2-CD, 3-AB, 3-BC, 4-AB, 4-BC, 5-AB, 5-BC (ECO 220X90) 7.47 0.62 8.00 M2 37.05

6.56 0.62 10.00 M2 40.67

CARTELAS (ECO 220X90 ) 0.50 0.62 32.00 M2 9.92

VIGAS 6A-5B, 6D-5C, 1A-2B, 1D-2C (ECO 260X90 ) 10.03 0.70 4.00 M2 28.08

CARTELAS (ECO 260X90 ) 0.50 0.70 8.00 M2 2.80

VIGAS EJE A Y EJE D Y EJES B Y C (ECO 180X65 ) 6.56 0.50 16.00 M2 52.48

VIGAS EJES 1, 2, 5 Y 6 (ECO 180X65) 4.47 0.50 8.00 M2 17.88

VIGA CLARABOYA EJES 2 Y 5 (ECO 180X65) 7.47 0.50 2.00 M2 7.47

VIGAS B-56, C-56, B-45, C-45, B-34, C-34, B-23, C-23, B-12, C-12 (ECO 220X90)

COMPUTOS METRICOS

OBRA: ADECUACION INTEGRAL Y CONSTRUCCION DE INSTALACIONES PARA LA REUBICACION DE LA ECONOMIA INFORMAL.

FECHA:

PARTIDA N° DESCRIPCIONMEDIDAS

UNDLARGO ANCHO ALTO

EMPRESA: .

ELEMET IGUALES

CANT. TOTAL

CONTRATO N°REPUBLICA BOLIVARIANA DE VENEZUELA

ALCALDIA DEL MUNICIPIO GIRARDOTDIRECCION DE OBRAS PUBLICAS

HABITAT VIVIENDA Y ASUNTOS SOCIALES

VIGA CLARABOYA EJES B Y C (PERFIL ECO 220X90) 6.56 0.62 6.00 M2 24.40

CORREAS (ECO 140X60) 6.56 0.40 30.00 M2 78.72

VAN 299.47

ING. RESIDENTE/CONTRATISTA FISCAL ING. INSPECTOR

VIENEN 299.47

CORREAS (ECO 140X60) 7.58 0.40 10.00 M2 30.32

CORREAS (ECO 140X60) 1.20 0.40 4.00 M2 1.92

CORREAS (ECO 140X60) 2.51 0.40 4.00 M2 4.02

CORREAS (ECO 140X60) 3.79 0.40 4.00 M2 6.06

CORREAS (ECO 140X60) 5.07 0.40 4.00 M2 8.11

CORREAS (ECO 140X60) 6.35 0.40 4.00 M2 10.16

CORREAS (ECO 140X60) 5.55 0.40 4.00 M2 8.88

CORREAS (ECO 140X60) 4.43 0.40 4.00 M2 7.09

CORREAS (ECO 140X60) 3.30 0.40 4.00 M2 5.28

CORREAS (ECO 140X60) 2.17 0.40 4.00 M2 3.47

CORREAS (ECO 140X60) 1.05 0.40 4.00 M2 1.68

PERFIL CIRCULAR 2" 8.87 0.16 12.00 M2 17.03

PERFIL DE CIERRE DE 3 X 1 1/2" 20.28 0.24 2.00 M2 9.73

TOTAL EJECUTADO M2 413.22

87 E-461.000.701

ESMALTE EN PUERTA METALICA. INCLUYE TRANS. MATERIAL HASTA 50 KM.

1.20 2.10 6.00 M2 15.12

1.25 2.10 2.00 M2 5.25

0.80 2.10 2.00 M2 3.36

0.90 2.10 4.00 M2 7.56

TOTAL EJECUTADO M2 31.29

88 E-461.000.801

ESMALTE EN MARCOS METALICOS . INCLUYE TRANS. MATERIAL HASTA 50 KM.

5.40 3.00 ML 16.20

5.45 1.00 ML 5.45

5.00 1.00 ML 5.00

5.10 2.00 ML 10.20

21.78 4.00 ML 87.12

9.17 4.00 ML 36.68

0.60 4.00 ML 2.40

TOTAL EJECUTADO ML 163.05

89 E-461.000.601

ESMALTE EN TABIQUES METALICOS. INCLUYE TRANS. MATERIAL HASTA 50 KM.

2.60 2.00 4.00 M2 20.80

1.18 2.00 8.00 M2 18.88

0.90 2.00 4.00 M2 7.20

TOTAL EJECUTADO M2 46.88

90 E-461.000.701

ESMALTE EN VENTANAS DE LAMINAS METALICAS. INCLUYE TRANS. MATERIAL HASTA 50 KM.

0.30 0.70 16.00 M2 3.36

0.30 0.75 4.00 M2 0.90

0.30 0.70 4.00 M2 0.84

0.30 0.90 4.00 M2 1.08

0.30 0.20 4.00 M2 0.24

0.50 0.70 24.00 M2 8.40

1.00 0.70 4.00 M2 2.80

1.20 0.70 8.00 M2 6.72

1.20 0.90 4.00 M2 4.32

1.20 0.60 4.00 M2 2.88

2.74 0.70 8.00 M2 15.34

2.60 0.70 16.00 M2 29.12

TOTAL EJECUTADO M2 76.00

COMPUTOS METRICOS

OBRA: ADECUACION INTEGRAL Y CONSTRUCCION DE INSTALACIONES PARA LA REUBICACION DE LA ECONOMIA INFORMAL.

FECHA:

PARTIDA N° DESCRIPCIONMEDIDAS

UNDLARGO ANCHO ALTO

EMPRESA: .

ELEMET IGUALES

CANT. TOTAL

CONTRATO N°REPUBLICA BOLIVARIANA DE VENEZUELA

ALCALDIA DEL MUNICIPIO GIRARDOTDIRECCION DE OBRAS PUBLICAS

HABITAT VIVIENDA Y ASUNTOS SOCIALES

91 E-461.S/C

ESMALTE EN LAMINAS METALICAS (TIPO 1 MARCA MONTANA O SHERWIN WILLIAMS)

25.00 0.95 2.00 M2 47.50

TOTAL EJECUTADO M2 47.50

ING. RESIDENTE/CONTRATISTA FISCAL ING. INSPECTOR

92 E-461.100.S/C

HIDROESMALTE EN PAREDES INTERIORES. INCLUYENDO FONDO ANTIALCALINO. TRANS. MATERIAL HASTA 50 KM.

PERIMETRAL 24.10 4.00 M2 96.40

PERIMETRAL (DCTO PTA) -1.20 2.10 2.00 M2 -5.04

PERIMETRAL (DCTO PORTON) -5.00 2.80 M2 -14.00

PERIMETRAL (DCTO PORTON) -4.00 2.80 2.00 M2 -22.40

PERIMETRAL TRASERA 22.00 4.00 M2 88.00

PERIMETRAL LATERAL IZQ 27.23 4.00 M2 108.92

PERIMETRAL LATERAL IZQ 1.50 4.00 M2 6.00

CUARTO DE BOMBA Y BASURA 7.07 4.70 2.00 M2 66.46

CUARTO DE BOMBA Y BASURA 2.05 4.70 4.00 M2 38.54

CUARTO DE BOMBA (DCTO) -0.90 2.10 4.00 M2 -7.56

PERIMETRAL LATERAL DER. 34.30 4.00 M2 137.20

BAÑO (FRENTE) 3.21 4.70 2.00 M2 30.17

BAÑO 3.21 2.20 4.00 M2 28.25

BAÑO 3.53 2.20 4.00 M2 31.06

BAÑO 2.20 2.20 4.00 M2 19.36

BAÑO 2.20 4.70 1.00 M2 10.34

CUARTO DE CAVAS 13.12 4.70 2.00 M2 123.33

CUARTO DE CAVAS 3.35 4.70 2.00 M2 31.49

CUARTO DE CAVAS -1.20 2.10 2.00 M2 -5.04

TOTAL EJECUTADO M2 761.48

93 E-461.200.S/C

HIDROESMALTE EN PAREDES EXTERIORES. INCLUYENDO FONDO ANTIALCALINO. TRANS. MATERIAL HASTA 50 KM.

PERIMETRAL 24.10 4.00 1.00 M2 96.40

PERIMETRAL 25.60 1.20 1.00 M2 30.72

PERIMETRAL 34.30 1.20 2.00 M2 82.32

PERIMETRAL 1.50 4.00 1.00 M2 6.00

PERIMETRAL -5.00 2.20 1.00 M2 -11.00

PERIMETRAL -4.00 2.20 2.00 M2 -17.60

TOTAL EJECUTADO M2 186.84

94 E-46.S/C-EP

ENCAMISADO (MACILLADO) Y LIJADO DE PAREDES, ALTURA MAXIMA 5 MTS.

PERIMETRAL 24.10 4.00 M2 96.40

PERIMETRAL (DCTO PTA) -1.20 2.10 2.00 M2 -5.04

PERIMETRAL (DCTO PORTON) -5.00 2.80 M2 -14.00

PERIMETRAL (DCTO PORTON) -4.00 2.80 2.00 M2 -22.40

PERIMETRAL TRASERA 22.00 4.00 M2 88.00

PERIMETRAL LATERAL IZQ 27.23 4.00 M2 108.92

PERIMETRAL LATERAL IZQ 1.50 4.00 M2 6.00

CUARTO DE BOMBA Y BASURA 7.07 4.70 2.00 M2 66.46

CUARTO DE BOMBA Y BASURA 2.05 4.70 4.00 M2 38.54

CUARTO DE BOMBA (DCTO) -0.90 2.10 4.00 M2 -7.56

PERIMETRAL LATERAL DER. 34.30 4.00 M2 137.20

BAÑO (FRENTE) 3.21 4.70 2.00 M2 30.17

BAÑO 3.21 2.20 4.00 M2 28.25

BAÑO 3.53 2.20 4.00 M2 31.06

BAÑO 2.20 2.20 4.00 M2 19.36

BAÑO 2.20 4.70 1.00 M2 10.34

CUARTO DE CAVAS 13.12 4.70 2.00 M2 123.33

CUARTO DE CAVAS 3.35 4.70 2.00 M2 31.49

COMPUTOS METRICOS

OBRA: ADECUACION INTEGRAL Y CONSTRUCCION DE INSTALACIONES PARA LA REUBICACION DE LA ECONOMIA INFORMAL.

FECHA:

PARTIDA N° DESCRIPCIONMEDIDAS

UNDLARGO ANCHO ALTO

EMPRESA: .

ELEMET IGUALES

CANT. TOTAL

CONTRATO N°REPUBLICA BOLIVARIANA DE VENEZUELA

ALCALDIA DEL MUNICIPIO GIRARDOTDIRECCION DE OBRAS PUBLICAS

HABITAT VIVIENDA Y ASUNTOS SOCIALES

CUARTO DE CAVAS -1.20 2.10 2.00 M2 -5.04

PERIMETRAL EXT 24.10 4.00 1.00 M2 96.40

PERIMETRAL EXT 25.60 1.20 1.00 M2 30.72

PERIMETRAL EXT 34.30 1.20 2.00 M2 82.32

PERIMETRAL EXT 1.50 4.00 1.00 M2 6.00

PERIMETRAL EXT -5.00 2.20 1.00 M2 -11.00

PERIMETRAL EXT -4.00 2.20 2.00 M2 -17.60

TOTAL EJECUTADO M2 948.32

ING. RESIDENTE/CONTRATISTA FISCAL ING. INSPECTOR

95 E-463.100.513

CAUCHO CLORADO EN PAREDES. INCLUYE TRANS. MATERIAL HASTA 50 KM.

TANQUE (PAREDES) 3.50 3.00 4.00 M2 42.00

TANQUE TAPA Y PISO 3.50 3.50 2.00 M2 24.50

TANQUE (TAPA) -0.70 0.70 M2 -0.49

TOTAL EJECUTADO M2 66.01

96 E-411.051.S/C

CONSTRUCCION DE PAREDES DE BLOQUE DE VENTILACION DE CONCRETO, ACABADO CORRIENTE, E=15 CM NO INCLUYE MACHONES, DINTELES Y BROCALES.

DEPOSITO BASURA+CUARTO DE BOMBA 4.25 2.00 M2 8.50

DEPOSITO BASURA+CUARTO DE BOMBA 2.20 2.00 M2 4.40

CUARTO DE CAVAS 13.20 0.70 M2 9.24

22.14

COMPUTOS METRICOS

OBRA: ADECUACION INTEGRAL Y CONSTRUCCION DE INSTALACIONES PARA LA REUBICACION DE LA ECONOMIA INFORMAL.

FECHA:

PARTIDA N° DESCRIPCIONMEDIDAS

UNDLARGO ANCHO ALTO

EMPRESA: .

ELEMET IGUALES

CANT. TOTAL

CONTRATO N°REPUBLICA BOLIVARIANA DE VENEZUELA

ALCALDIA DEL MUNICIPIO GIRARDOTDIRECCION DE OBRAS PUBLICAS

HABITAT VIVIENDA Y ASUNTOS SOCIALES

ING. RESIDENTE/CONTRATISTA FISCAL ING. INSPECTOR

COMPUTOS METRICOS

OBRA: ADECUACION INTEGRAL Y CONSTRUCCION DE INSTALACIONES PARA LA REUBICACION DE LA ECONOMIA INFORMAL.

FECHA:

PARTIDA N° DESCRIPCIONMEDIDAS

UNDLARGO ANCHO ALTO

ELECTRICIDAD

97 E-512.211.051

I.E. TUBERIA DE HIERRO GALVANIZADO, SIN ROSCA TIPO EMT, EMBUTIDA, DIAMETRO 2" (51mm). INCLUYE TRANS. MATERIAL HASTA 50 KM.

CIRCUITOS DE ILUMINACION 25.00 ML 25.00

TOTAL EJECUTADO ML 25.00

98 E-512.211.019

I.E. TUBERIA DE HIERRO GALVANIZADO, SIN ROSCA, TIPO EMT, EMBUTIDA. D= 3/4" (19 MM). INCLUYE TRANS. MATERIAL HASTA 50 KM.

CIRCUITOS DE ILUMINICION Y TOMACORRIENTES 600.00 ML 600.00

TOTAL EJECUTADO ML 600.00

99 E-512.211.076

I.E. TUBERIA DE HIERRO GALVANIZADO, SIN ROSCA, TIPO EMT, EMBUTIDA. D= 3 " (76 MM). INCLUYE TRANS. MATERIAL HASTA 50 KM.

ACOMETIDA PRINCIPAL 15.00 ML 15.00

TABLEROS 10.00 ML 10.00

TOTAL EJECUTADO ML 25.00

100 E-512.211.038

I.E. TUBERIA DE HIERRO GALVANIZADO, SIN ROSCA, TIPO EMT, EMBUTIDA. D= 1 1/2" (38 MM). INCLUYE TRANS. MATERIAL HASTA 50 KM.

CIRCUITOS DE ILUMINICION Y TOMACORRIENTES 100.00 ML 100.00

TOTAL EJECUTADO ML 100.00

101 E-512.211.025

I.E. TUBERIA DE HIERRO GALVANIZADO, SIN ROSCA, TIPO EMT, EMBUTIDA. D= 1" (25 MM). INCLUYE TRANS. MATERIAL HASTA 50 KM.

CIRCUITOS DE ILUMINICION Y TOMACORRIENTES 170.00 ML 170.00

TOTAL EJECUTADO ML 170.00

102 E-512.211.019

I.E. TUBERIA DE HIERRO GALVANIZADO, SIN ROSCA, TIPO EMT, EMBUTIDA. D= 3/4" (19 MM). INCLUYE TRANS. MATERIAL HASTA 50 KM.

CIRCUITOS DE ILUMINICION Y TOMACORRIENTES 65.00 ML 65.00

TOTAL EJECUTADO ML 65.00

103 E-521.223.023

I.E CABLE DE COBRE, TRENSADO, REVESTIDO, THW, CALIBRE 12 AWG (2.32 MM).

1350.00 ML 1,350.00

TOTAL EJECUTADO ML 1,350.00

104 E-521.223.095

I.E CABLE DE COBRE, TRENSADO, REVESTIDO, THW, CALIBRE 1/0 AWG (9.47 MM).

30.00 ML 30.00

TOTAL EJECUTADO ML 30.00

105 E-521.223.030

I.E CABLE DE COBRE, TRENSADO, REVESTIDO, THW, CALIBRE 10 AWG (2.95 MM).

2100.00 ML 2,100.00

TOTAL EJECUTADO ML 2,100.00

106 E-521.223.037

I.E CABLE DE COBRE, TRENSADO, REVESTIDO, THW, CALIBRE 8 AWG (3.71 MM).

850.00 ML 850.00

TOTAL EJECUTADO ML 850.00

107 E-521.223.074

I.E CABLE DE COBRE, TRENSADO, REVESTIDO, THW, CALIBRE 2 AWG (7.42 MM)

15.00 ML 15.00

TOTAL EJECUTADO ML 15.00

108 E-521.224.095

I.E CABLE DE COBRE, TRENSADO, REVESTIDO, TTU, CALIBRE 1/0 AWG (9.47 MM)

180.00 ML 180.00

TOTAL EJECUTADO ML 180.00

EMPRESA: .

ELEMET IGUALES

CANT. TOTAL

CONTRATO N°REPUBLICA BOLIVARIANA DE VENEZUELA

ALCALDIA DEL MUNICIPIO GIRARDOTDIRECCION DE OBRAS PUBLICAS

HABITAT VIVIENDA Y ASUNTOS SOCIALES

COMPUTOS METRICOS

OBRA: ADECUACION INTEGRAL Y CONSTRUCCION DE INSTALACIONES PARA LA REUBICACION DE LA ECONOMIA INFORMAL.

FECHA:

PARTIDA N° DESCRIPCIONMEDIDAS

UNDLARGO ANCHO ALTO

EMPRESA: .

ELEMET IGUALES

CANT. TOTAL

CONTRATO N°REPUBLICA BOLIVARIANA DE VENEZUELA

ALCALDIA DEL MUNICIPIO GIRARDOTDIRECCION DE OBRAS PUBLICAS

HABITAT VIVIENDA Y ASUNTOS SOCIALES

ING. RESIDENTE/CONTRATISTA FISCAL ING. INSPECTOR

109 E-521.224.106

I.E CABLE DE COBRE, TRENSADO, REVESTIDO, TTU, CALIBRE 2/0 AWG (10.64 MM)

540.00 ML 540.00

TOTAL EJECUTADO ML 540.00

110 E-531.210.010

I.E. CAJETINES METALICOS, SALIDA DE 1/2", PROFUNDIDAD 1 1/2". OCTOGONALES 4" (10.2 CM).

80.00 PZA 80.00

TOTAL EJECUTADO PZA 80.00

111 E-531.210.510

I.E. CAJETINES METALICOS, SALIDA DE 1/2" - 3/4" PLG PROFUNDIDAD 1 1/2". RECTANGULARES DE 2" X 4" (5.1 CM X 10.2 CMS) PARA TOMAS E INTERRUPTORES.

100.00 PZA 100.00

TOTAL EJECUTADO PZA 100.00

112 E-538.080.S/C

I.E. CAJA METALICA DE (10X10X4) CM. INCLUYE TRANS. MATERIAL.

20.00 PZA 20.00

TOTAL EJECUTADO PZA 20.00

113 E-531.231.010

I.E. CAJETIN METALICO, SALIDA 1/2" - 3/4" PROFUNDIDAD 2 1/8" CUADRADO 4X4". (10.2 X 10.2 CM).

12.00 UNIDAD 12.00

TOTAL EJECUTADO UNIDAD 12.00

114 E-541.111.120

I.E. INTERRUPTORES COMBINABLES SIMPLES, CON TAPA METALICA, PUENTE Y TORNILLOS, 20 A.

9.00 PZA 9.00

TOTAL EJECUTADO PZA 9.00

115 E-542.121.120

I.E. TOMACORRIENTES CON TAPA METALICA, PUENTE Y TORNILLOS. DOBLE, UNA (1) FASE, 15 A.

73.00 PZA 73.00

TOTAL EJECUTADO PZA 73.00

116 E-551.120.412

CAVAS DE REFRIGERACION 4.00 PZA 4.00

TOTAL EJECUTADO PZA 4.00

117 E-551.121.212

1.00 PZA 1.00

TOTAL EJECUTADO PZA 1.00

118 E-552.131.S/C

I.E. TABLERO METALICO SUPERFICIAL SIN BREAKER, CON PUERTA, 3 FASES + NEUTRO, DE 4 HILOS, 18 CIRCUITOS BARRAS 150 A. INCLUYE TRANS. MATERIAL.

1.00 PZA 1.00

TOTAL EJECUTADO PZA 1.00

119 E-551.131.S/C

I.E. TABLERO METALICO CONVERTIBLE, EMBUTIDO, CON PUERTA 3 FASES+ NEUTRO, 12 CIRCUITOS, BARRAS DE 225 A. NO INCLUYE BREAKER.

1.00 PZA 1.00

TOTAL EJECUTADO PZA 1.00

120 E-551.131.S/C.01

I.E. TABLERO METALICO CONVERTIBLE EMBUTIDO, CON PUERTA 3 FASES+ NEUTRO , 12 CIRCUITOS, BARRAS DE 350 AMP. NO INCLUYE BREAKERS.

1.00 PZA 1.00

TOTAL EJECUTADO PZA 1.00

121 E-563.110.020

I.E. INTERRUPTOR TERMOMAGNETICO (BREAKER), CON TORNILLOS, 1 POLO, 10 KA ICC, 120/240 V, CAP 20 AMP. (HQC).

CAVAS DE REFRIGERACION 4.00 PZA 4.00

TOMAS E ILUMINACION CAVAS 2.00 PZA 2.00

TOMAS E ILUMINACION HIDRONEUMATICO 2.00 PZA 2.00

TOMAS E ILUMINACION GALPON 17.00 PZA 17.00

TOTAL EJECUTADO PZA 25.00

I.E. TABLERO METALICO CONVERTIBLE, EMBUTIDO, CON PUERTA 2 FASE+ NEUTRO, 4 CIRCUITOS, BARRAS DE 125 A. NO INCLUYE BREAKER. INCLUYE TRANS. MATERIAL.

I.E. TABLERO METALICO CONVERTIBLE, EMBUTIDO, CON PUERTA 2 FASES+ NEUTRO, 12 CIRCUITOS, BARRAS DE 125 A. NO INCLUYE BREAKER. INCLUYE TRANS. MATERIAL.

COMPUTOS METRICOS

OBRA: ADECUACION INTEGRAL Y CONSTRUCCION DE INSTALACIONES PARA LA REUBICACION DE LA ECONOMIA INFORMAL.

FECHA:

PARTIDA N° DESCRIPCIONMEDIDAS

UNDLARGO ANCHO ALTO

EMPRESA: .

ELEMET IGUALES

CANT. TOTAL

CONTRATO N°REPUBLICA BOLIVARIANA DE VENEZUELA

ALCALDIA DEL MUNICIPIO GIRARDOTDIRECCION DE OBRAS PUBLICAS

HABITAT VIVIENDA Y ASUNTOS SOCIALES

ING. RESIDENTE/CONTRATISTA FISCAL ING. INSPECTOR

123 E-563.210.060

I.E. INTERRUPTOR TERMOMAGNETICO (BREAKER), CON TORNILLOS, 2 POLOS, 10 KA ICC, 120/240 V, CAPACIDAD 60 AMP.

6.00 PZA 6.00

TOTAL EJECUTADO PZA 6.00

124 E-563.318.S/C

I.E. INTERRUPTOR TERMOMAGNETICO (BREAKER) CON TORNILLOS, 3 POLOS, 42/30/22 KA ICC, 248/480 V, CAP. 40 A.

1.00 PZA 1.00

TOTAL EJECUTADO PZA 1.00

125 E-563.318.S/C.01

I.E. INTERRUPTOR TERMOMAGNETICO (BREAKER) CON TORNILLOS, 3 POLOS, 42/30/22 KA ICC, 248/480 V, CAP. 150 A.

1.00 PZA 1.00

TOTAL EJECUTADO PZA 1.00

126 E-563.310.070

I.E. INTERRUPTOR TERMOMAGNETICO (BREAKER), CON TORNILLOS, 3 POLOS, 10 KA ICC, 120/240 V, CAP. 70 A. (HQC)

2.00 PZA 2.00

TOTAL EJECUTADO PZA 2.00

127 E-564.210.350

I.E. INTERRUPTOR TERMOMAGNETICO BREAKER 208/120 V, 3 P X 350 AMP.

1.00 PZA 1.00

TOTAL EJECUTADO PZA 1.00

128 E-581.S/C.02

I.E. SUMINISTRO, TRANSPORTE E INSTALACION DE LUMINARIA TIPO ESPECULAR DE 40 W. DE 3 X 40 W X 0.60 M. INCLUYE TUBOS.

10.00 PZA 10.00

TOTAL EJECUTADO PZA 10.00

129 E-581.S/C.01

I.E. SUMINISTRO, TRANSPORTE E INSTALACION DE LUMINARIA TIPO ESPECULAR DE 40 W. DE 2 X 40 W X 1.20 M. INCLUYE TUBOS.

21.00 PZA 21.00

TOTAL EJECUTADO PZA 21.00

130 E-581.S/C

I.E. SUMINISTRO E INSTALACION DE LAMPARA FLUORESCENTE CON REFLECTOR PARABOLICO Y BOMBILLO 2 X 32 W.

49.00 PZA 49.00

TOTAL EJECUTADO PZA 49.00

131 E-EXTRACTOR 24"

SUMINISTRO, TRANSPORTE Y COLOCACION DE EXTRACTORES DE 24" CAPACIDAD 5000 M3/HORA. INCLUYE TRANS. MATERIAL HASTA 50 KM.

12.00 PZA 12.00

TOTAL EJECUTADO PZA 12.00

132 E-EXTRACTOR 16"

SUMINISTRO, TRANSPORTE Y COLOCACION DE EXTRACTORES DE 16" CAPACIDAD 2400 M3/HORA. INCLUYE TRANS. MATERIAL HASTA 50 KM.

5.00 PZA 5.00

TOTAL EJECUTADO PZA 5.00

133 E-VENTILADOR

SUMINISTRO, TRANSPORTE Y COLOCACION DE VENTILADOR PARA INYECCION DE AIRE 24 PLG POTENCIA 1.5 HP. INCLUYE DUCTO DE ENTRADA.

2.00 PZA 2.00

TOTAL EJECUTADO PZA 2.00

134 E-DUCTO DE TRANSICION

SUMINISTRO Y COLOCACION DE DUCTO DE TRANSICION PARA COLOCACION DE VENTILADOR.

19.00 PZA 19.00

TOTAL EJECUTADO PZA 19.00

135 RAB307

BANCADA DE DOS TUBOS DE PVC 4"0 EN CTO. (RCC 100 KG/CM2) PARA B.T. (B2C-4"0)

80.00 ML 80.00

TOTAL EJECUTADO ML 80.00

136 RAB305

BANCADA DE DOS TUBOS DE PVC 2"0 EN CTO. (RCC 100 KG/CM2) PARA B.T. (B2C-2"0)

50.00 ML 50.00

COMPUTOS METRICOS

OBRA: ADECUACION INTEGRAL Y CONSTRUCCION DE INSTALACIONES PARA LA REUBICACION DE LA ECONOMIA INFORMAL.

FECHA:

PARTIDA N° DESCRIPCIONMEDIDAS

UNDLARGO ANCHO ALTO

EMPRESA: .

ELEMET IGUALES

CANT. TOTAL

CONTRATO N°REPUBLICA BOLIVARIANA DE VENEZUELA

ALCALDIA DEL MUNICIPIO GIRARDOTDIRECCION DE OBRAS PUBLICAS

HABITAT VIVIENDA Y ASUNTOS SOCIALES

TOTAL EJECUTADO ML 50.00

ING. RESIDENTE/CONTRATISTA FISCAL ING. INSPECTOR

COMPUTOS METRICOS

OBRA: ADECUACION INTEGRAL Y CONSTRUCCION DE INSTALACIONES PARA LA REUBICACION DE LA ECONOMIA INFORMAL.

FECHA:

PARTIDA N° DESCRIPCIONMEDIDAS

UNDLARGO ANCHO ALTO

PLOMERIA

137 E-394.100.004

SUMINISTRO Y COLOCACION DE BAJANTE PARA A.LL. EN PVC 4 ". INCLUYE TRANS. MATERIALES HASTA 50 KM.

BAJANTES 1.50 10.00 ML

TOTAL EJECUTADO ML

138 E-600.S/C

SUMINISTRO, Y COLOCACION DE BAJANTE PARA A.LL. EN PVC 6". INCLUYE TRANS. MATERIALES HASTA 50 KM.

LATERALES 34.00 2.00 ML

TRASERAS 6.00 2.00 ML

BAJANTE 4.50 2.00 ML

TOTAL EJECUTADO ML

139 E-611.132.051

SUMINISTRO, TRANSPORTE E INSTALACION DE TUBERIA AGUAS CLARAS, P.V.C., ASTM, D= 2" AMBIENTE EXTERIOR AL RECINTO SANITARIO.

61.75 ML

52.70 ML

TOTAL EJECUTADO ML

140 E-611.132.064

45.36 ML

TOTAL EJECUTADO ML

141 E-611.142.019

SUMINISTRO, TRANSPORTE E INSTALACION DE TUBERIA AGUAS CLARAS, P.V.C., ASTM, D= 3/4". AMBIENTE EXTERIOR AL RECINTO SANITARIO.

100.62 ML

TOTAL EJECUTADO ML

142 E-621.122.038

SUMINISTRO, TRANSPORTE E INSTALACION DE TUBERIA AGUAS CLARAS, P.V.C., ASTM, D= 1". AMBIENTE EXTERIOR AL RECINTO SANITARIO.

22.95 ML

TOTAL EJECUTADO ML

143 E-612.142.051

SUMINISTRO, TRANSPORTE E INSTALACION DE TUBERIA AGUA RESIDUALES, P.V.C., ASTM, D= 2". AMBIENTE EXTERIOR AL RECINTO SANITARIO.

36.60 ML

TOTAL EJECUTADO ML

144 E-612.144.102

SUMINISTRO, TRANSPORTE E INSTALACION TUBERIA AGUAS RESIDUALES, P.V.C., ASTM, D= 4". AMBIENTE EXTERIOR AL RECINTO SANITARIO.

75.53 ML

ACOMETIDA PROVISIONAL 35.00 ML

TOTAL EJECUTADO ML

145 E-612.144.152

82.36 ML

TOTAL EJECUTADO ML

146 E-611.142.025

61.88 ML

TOTAL EJECUTADO ML

EMPRESA: .

ELEMET IGUALES

SUMINISTRO, TRANSPORTE E INSTALACION DE TUBERIA AGUAS CLARAS, P.V.C., ASTM, D=2 1/2" (E= 3.0 MM), AMBIENTE EXTERIOR AL RECINTO SANITARIO. INCLUYE CONEXIONES DE H.G.

SUMINISTRO, TRANSPORTE E INSTALACION TUBERIA AGUAS RESIDUALES, P.V.C., ASTM, D= 6". (152 MM) E=3.3 MM. AMBIENTE EXTERIOR AL RECINTO SANITARIO. INCLUYE CONEXIONES.

SUMINISTRO, TRANSPORTE E INSTALACION TUBERIA AGUAS RESIDUALES, P.V.C., D= 3". (76 MM) E=1.8 MM. AMBIENTE EXTERIOR AL RECINTO SANITARIO. INCLUYE CONEXIONES. TRANS. MATERIAL HASTA 50 KM.

CONTRATO N°REPUBLICA BOLIVARIANA DE VENEZUELA

ALCALDIA DEL MUNICIPIO GIRARDOTDIRECCION DE OBRAS PUBLICAS

HABITAT VIVIENDA Y ASUNTOS SOCIALES

COMPUTOS METRICOS

OBRA: ADECUACION INTEGRAL Y CONSTRUCCION DE INSTALACIONES PARA LA REUBICACION DE LA ECONOMIA INFORMAL.

FECHA:

PARTIDA N° DESCRIPCIONMEDIDAS

UNDLARGO ANCHO ALTO

EMPRESA: .

ELEMET IGUALES

CONTRATO N°REPUBLICA BOLIVARIANA DE VENEZUELA

ALCALDIA DEL MUNICIPIO GIRARDOTDIRECCION DE OBRAS PUBLICAS

HABITAT VIVIENDA Y ASUNTOS SOCIALES

ING. RESIDENTE/CONTRATISTA FISCAL ING. INSPECTOR

147 E-621.132.038

SUMINISTRO, TRANSPORTE E INSTALACION PUNTOS AGUAS CLARAS, DE P.V.C., ASTM, D= 1 1/2". AMBIENTE INTERIOR AL RECINTO SANITARIO.

W.C. 6.00 PTO

LAVAMANOS 4.00 PTO

URINARIOS 2.00 PTO

TOTAL EJECUTADO PTO

148 E-621.132.013

SUMINISTRO, TRANSPORTE E INSTALACION PUNTOS AGUAS CLARAS, DE P.V.C., ASTM, D= 1/2". AMBIENTE INTERIOR AL RECINTO SANITARIO.

FREGADERO 15.00 PTO

LLAVES DE CHORRO 7.00 PTO

CAVAS 3.00 PTO

TOTAL EJECUTADO PTO

149 E-622.131.051

SUMINISTRO, TRANSPORTE E INSTALACION PUNTOS DE AGUAS NEGRAS, DE P.V.C., D= 2". (E=1.8 MM). AMBIENTE INTERIOR AL RECINTO SANITARIO.

FREGADERO 15.00 PTO

LAVAMANOS 4.00 PTO

URINARIOS 2.00 PTO

C.P. 2" 4.00 PTO

TOTAL EJECUTADO PTO

150 E-622.131.076

SUMINISTRO, TRANSPORTE E INSTALACION PUNTOS DE AGUAS NEGRAS, DE P.V.C., D= 3". (E=1.8 MM). AMBIENTE INTERIOR AL RECINTO SANITARIO.

CAVAS 6.00 PTO

CENTRO PISO 6.00 PTO

BASURA 1.00 PTO

GALPON 4.00 PTO

TOTAL EJECUTADO PTO

151 E-622.132.102

SUMINISTRO, TRANSPORTE E INSTALACION PUNTOS AGUAS RESIDUALES, DE P.V.C., ASTM, D= 4". AMBIENTE INTERIOR AL RECINTO SANITARIO.

W.C. 6.00 PTO

T.R. 7.00 PTO

TOTAL EJECUTADO PTO

152 E-631.001.013

SUMINISTRO Y TRANSPORTE DE LLAVE DE PASO TIPO COMPUERTA, DE BRONCE, D= 1/2" (13 MM). (150 PSI).

FREGADEROS 15.00 PZA

TOTAL EJECUTADO PZA

153 E-631.001.051

SUMINISTRO Y TRANSPORTE DE LLAVE DE PASO TIPO COMPUERTA, DE BRONCE, D= 2" (51 MM). (150 PSI).

3.00 PZA

TOTAL EJECUTADO PZA

154 E-632.002.S/C

SUMINISTRO Y TRANSPORTE DE LLAVE DE PASO TIPO ESFERICA O DE BOLA DE ALEACION DE METALES, D= 2 1/2" .

2.00 PZA

TOTAL EJECUTADO PZA

155 E-631.001.038

SUMINISTRO Y TRANSPORTE DE LLAVE DE PASO TIPO COMPUERTA, DE BRONCE, D= 1 1/2" (38 MM). (150 PSI).

12.00 PZA

TOTAL EJECUTADO PZA

COMPUTOS METRICOS

OBRA: ADECUACION INTEGRAL Y CONSTRUCCION DE INSTALACIONES PARA LA REUBICACION DE LA ECONOMIA INFORMAL.

FECHA:

PARTIDA N° DESCRIPCIONMEDIDAS

UNDLARGO ANCHO ALTO

EMPRESA: .

ELEMET IGUALES

CONTRATO N°REPUBLICA BOLIVARIANA DE VENEZUELA

ALCALDIA DEL MUNICIPIO GIRARDOTDIRECCION DE OBRAS PUBLICAS

HABITAT VIVIENDA Y ASUNTOS SOCIALES

ING. RESIDENTE/CONTRATISTA FISCAL ING. INSPECTOR

156 E-631.001.019

SUMINISTRO Y TRANSPORTE DE LLAVE DE PASO TIPO COMPUERTA, DE BRONCE, DIAMETRO 3/4" (19 MM). (150 PSI).

2.00 PZA

TOTAL EJECUTADO PZA

157 E-661.110.121

ING. RESIDENTE/CONTRATISTA FISCAL ING. INSPECTOR 4.00 PZA

TOTAL EJECUTADO PZA

158 E-662.141.111

6.00 PZA

TOTAL EJECUTADO PZA

159 E-666.222.111

2.00 PZA

TOTAL EJECUTADO PZA

160 E-665.101.S/C

SUMINISTRO, TRANSPORTE Y COLOCACION DE PORTARROLLO DE PAPEL TIPO INDUSTRIAL.

BAÑO DAMAS Y CABALLEROS 2.00 PZA

TOTAL EJECUTADO PZA

161 E-665.S/C

S/T/C DE DISPENSADOR DE JABON. INCLUYE ELEMENTOS DE FIJACION.

2.00 PZA

TOTAL EJECUTADO PZA

162 E-678.112.S/C

11.00 PZA

TOTAL EJECUTADO PZA

163 E-678.112.S/C.01

SUMINISTRO, TRANSPORTE Y COLOCACION DE FREGADERO DE ACERO INOXIDABLE. DE 2 PONCHERA Y MESA DE TRABAJO. INCLUIYE GRIFERIA.

2.00 PZA

TOTAL EJECUTADO PZA

164 E-666.311.051

I.S. SUMINISTRO, TRANSPORTE E INSTALACION DE CENTRO PISO CIRCULAR STANDAR, DE BRONCE, PARA TUBO DE DESCARGA DE 2PGDS. DE DIAMETRO 51 MM.

4.00 PZA

TOTAL EJECUTADO PZA

165 E-666.311.076

I.S. SUMINISTRO, TRANSPORTE E INSTALACION DE CENTRO PISO CIRCULAR STANDAR, DE BRONCE, PARA TUBO DE DESCARGA DE 3 PGDS. DE DIAMETRO 76 MM.

16.00 PZA

TOTAL EJECUTADO PZA

166 E-666.371.076

I/S. SUMINISTRO, TRANSPORTE E INSTALACION DE TAPON DE REGISTRO CIRCULAR, DE BRONCE, PARA TUBO DE DESCARGA DE 3 PGDS. DE DIAMETRO (76 MM)

1.00 PZA

TOTAL EJECUTADO PZA

167 E-666.371.102

I/S. SUMINISTRO, TRANSPORTE E INSTALACION DE TAPON DE REGISTRO CIRCULAR, DE BRONCE, PARA TUBO DE DECARGA DE 4 PGDS. DE DIAMETRO (102 MM)

7.00 PZA

TOTAL EJECUTADO PZA

SUMINISTRO, TRANSPORTE E INSTALACION DE LAVAMANOS PARA EMPOTRAR, DE UNA LLAVE, BLANCO O COLOR CLARO. INCLUYE GRIFERIA. TRANS. MATERIAL HASTA 50 KM.

I.S. SUMINISTRO, TRANSPORTE E INSTALACION DE W.C. DE ASIENTO, CON FLUXOMETRO INCLUIDO, DESCARGA AL PISO, BLANCO O COLOR CLARO. INCLUYE GRIFERIA. TRANS. MATERIAL HASTA 50 KM.

I.S. SUMINISTRO, TRANSPORTE E INSTALACION DE URINARIOS, CON SIFON INTEGRADO, ALIMENTADO CON FLUXOMETRO/INCLUIDO/DESCARGA A LA PARED, BLANCO O COLOR CLARO, LINEA ECONOMICA/INCLUYE GRIFERIA.

SUMINISTRO, TRANSPORTE E INSTALACION DE FREGADERO AUTOPORTANTE DE UNA (1) PONCHERA Y MESA DE TRABAJO TOTALMENTE EN ACERO INOXIDABLE. INCLUIYE GRIFERIA.

COMPUTOS METRICOS

OBRA: ADECUACION INTEGRAL Y CONSTRUCCION DE INSTALACIONES PARA LA REUBICACION DE LA ECONOMIA INFORMAL.

FECHA:

PARTIDA N° DESCRIPCIONMEDIDAS

UNDLARGO ANCHO ALTO

EMPRESA: .

ELEMET IGUALES

CONTRATO N°REPUBLICA BOLIVARIANA DE VENEZUELA

ALCALDIA DEL MUNICIPIO GIRARDOTDIRECCION DE OBRAS PUBLICAS

HABITAT VIVIENDA Y ASUNTOS SOCIALES

ING. RESIDENTE/CONTRATISTA FISCAL ING. INSPECTOR

COMPUTOS METRICOS

ADECUACION INTEGRAL Y CONSTRUCCION DE INSTALACIONES PARA LA REUBICACION DE LA ECONOMIA INFORMAL.

SUMINISTRO Y COLOCACION DE BAJANTE PARA A.LL. EN PVC 4 ". INCLUYE TRANS. MATERIALES HASTA 50 KM.

15.00

15.00

SUMINISTRO, Y COLOCACION DE BAJANTE PARA A.LL. EN PVC 6". INCLUYE TRANS. MATERIALES HASTA 50 KM.

68.00

12.00

9.00

89.00

SUMINISTRO, TRANSPORTE E INSTALACION DE TUBERIA AGUAS CLARAS, P.V.C., ASTM, D= 2" AMBIENTE EXTERIOR AL RECINTO SANITARIO.

61.75

52.70

114.45

45.36

45.36

SUMINISTRO, TRANSPORTE E INSTALACION DE TUBERIA AGUAS CLARAS, P.V.C., ASTM, D= 3/4". AMBIENTE EXTERIOR AL RECINTO SANITARIO.

100.62

100.62

SUMINISTRO, TRANSPORTE E INSTALACION DE TUBERIA AGUAS CLARAS, P.V.C., ASTM, D= 1". AMBIENTE EXTERIOR AL RECINTO SANITARIO.

22.95

22.95

SUMINISTRO, TRANSPORTE E INSTALACION DE TUBERIA AGUA RESIDUALES, P.V.C., ASTM, D= 2". AMBIENTE EXTERIOR AL RECINTO SANITARIO.

36.60

36.60

SUMINISTRO, TRANSPORTE E INSTALACION TUBERIA AGUAS RESIDUALES, P.V.C., ASTM, D= 4". AMBIENTE EXTERIOR AL RECINTO SANITARIO.

75.53

35.00

110.53

82.36

82.36

61.88

61.88

CANT. TOTAL

SUMINISTRO, TRANSPORTE E INSTALACION DE TUBERIA AGUAS CLARAS, P.V.C., ASTM, D=2 1/2" (E= 3.0 MM), AMBIENTE EXTERIOR AL RECINTO SANITARIO. INCLUYE

SUMINISTRO, TRANSPORTE E INSTALACION TUBERIA AGUAS RESIDUALES, P.V.C., ASTM, D= 6". (152 MM) E=3.3 MM. AMBIENTE EXTERIOR AL RECINTO SANITARIO.

SUMINISTRO, TRANSPORTE E INSTALACION TUBERIA AGUAS RESIDUALES, P.V.C., D= 3". (76 MM) E=1.8 MM. AMBIENTE EXTERIOR AL RECINTO SANITARIO. INCLUYE

CONTRATO N°

COMPUTOS METRICOS

ADECUACION INTEGRAL Y CONSTRUCCION DE INSTALACIONES PARA LA REUBICACION DE LA ECONOMIA INFORMAL.

CANT. TOTAL

CONTRATO N°

ING. RESIDENTE/CONTRATISTA FISCAL ING. INSPECTOR

SUMINISTRO, TRANSPORTE E INSTALACION PUNTOS AGUAS CLARAS, DE P.V.C., ASTM, D= 1 1/2". AMBIENTE INTERIOR AL RECINTO SANITARIO.

6.00

4.00

2.00

12.00

SUMINISTRO, TRANSPORTE E INSTALACION PUNTOS AGUAS CLARAS, DE P.V.C., ASTM, D= 1/2". AMBIENTE INTERIOR AL RECINTO SANITARIO.

15.00

7.00

3.00

25.00

SUMINISTRO, TRANSPORTE E INSTALACION PUNTOS DE AGUAS NEGRAS, DE P.V.C., D= 2". (E=1.8 MM). AMBIENTE INTERIOR AL RECINTO SANITARIO.

15.00

4.00

2.00

4.00

25.00

SUMINISTRO, TRANSPORTE E INSTALACION PUNTOS DE AGUAS NEGRAS, DE P.V.C., D= 3". (E=1.8 MM). AMBIENTE INTERIOR AL RECINTO SANITARIO.

6.00

6.00

1.00

4.00

17.00

SUMINISTRO, TRANSPORTE E INSTALACION PUNTOS AGUAS RESIDUALES, DE P.V.C., ASTM, D= 4". AMBIENTE INTERIOR AL RECINTO SANITARIO.

6.00

7.00

13.00

SUMINISTRO Y TRANSPORTE DE LLAVE DE PASO TIPO COMPUERTA, DE BRONCE, D= 1/2" (13 MM). (150 PSI).

15.00

15.00

SUMINISTRO Y TRANSPORTE DE LLAVE DE PASO TIPO COMPUERTA, DE BRONCE, D= 2" (51 MM). (150 PSI).

3.00

3.00

SUMINISTRO Y TRANSPORTE DE LLAVE DE PASO TIPO ESFERICA O DE BOLA DE ALEACION DE METALES, D= 2 1/2" .

2.00

2.00

SUMINISTRO Y TRANSPORTE DE LLAVE DE PASO TIPO COMPUERTA, DE BRONCE, D= 1 1/2" (38 MM). (150 PSI).

12.00

12.00

COMPUTOS METRICOS

ADECUACION INTEGRAL Y CONSTRUCCION DE INSTALACIONES PARA LA REUBICACION DE LA ECONOMIA INFORMAL.

CANT. TOTAL

CONTRATO N°

ING. RESIDENTE/CONTRATISTA FISCAL ING. INSPECTOR

SUMINISTRO Y TRANSPORTE DE LLAVE DE PASO TIPO COMPUERTA, DE BRONCE, DIAMETRO 3/4" (19 MM). (150 PSI).

2.00

2.00

4.00

4.00

6.00

6.00

2.00

2.00

2.00

2.00

2.00

2.00

11.00

11.00

SUMINISTRO, TRANSPORTE Y COLOCACION DE FREGADERO DE ACERO INOXIDABLE. DE 2 PONCHERA Y MESA DE TRABAJO. INCLUIYE GRIFERIA.

2.00

2.00

I.S. SUMINISTRO, TRANSPORTE E INSTALACION DE CENTRO PISO CIRCULAR STANDAR, DE BRONCE, PARA TUBO DE DESCARGA DE 2PGDS. DE DIAMETRO 51 MM.

4.00

4.00

I.S. SUMINISTRO, TRANSPORTE E INSTALACION DE CENTRO PISO CIRCULAR STANDAR, DE BRONCE, PARA TUBO DE DESCARGA DE 3 PGDS. DE DIAMETRO 76 MM.

16.00

16.00

I/S. SUMINISTRO, TRANSPORTE E INSTALACION DE TAPON DE REGISTRO CIRCULAR, DE BRONCE, PARA TUBO DE DESCARGA DE 3 PGDS. DE DIAMETRO (76 MM)

1.00

1.00

I/S. SUMINISTRO, TRANSPORTE E INSTALACION DE TAPON DE REGISTRO CIRCULAR, DE BRONCE, PARA TUBO DE DECARGA DE 4 PGDS. DE DIAMETRO (102 MM)

7.00

7.00

SUMINISTRO, TRANSPORTE E INSTALACION DE LAVAMANOS PARA EMPOTRAR, DE UNA LLAVE, BLANCO O COLOR CLARO. INCLUYE GRIFERIA. TRANS. MATERIAL

I.S. SUMINISTRO, TRANSPORTE E INSTALACION DE W.C. DE ASIENTO, CON FLUXOMETRO INCLUIDO, DESCARGA AL PISO, BLANCO O COLOR CLARO. INCLUYE

I.S. SUMINISTRO, TRANSPORTE E INSTALACION DE URINARIOS, CON SIFON INTEGRADO, ALIMENTADO CON FLUXOMETRO/INCLUIDO/DESCARGA A LA PARED, BLANCO

SUMINISTRO, TRANSPORTE E INSTALACION DE FREGADERO AUTOPORTANTE DE UNA (1) PONCHERA Y MESA DE TRABAJO TOTALMENTE EN ACERO INOXIDABLE.

COMPUTOS METRICOS

ADECUACION INTEGRAL Y CONSTRUCCION DE INSTALACIONES PARA LA REUBICACION DE LA ECONOMIA INFORMAL.

CANT. TOTAL

CONTRATO N°

ING. RESIDENTE/CONTRATISTA FISCAL ING. INSPECTOR

COMPUTOS METRICOS

OBRA: ADECUACION INTEGRAL Y CONSTRUCCION DE INSTALACIONES PARA LA REUBICACION DE LA ECONOMIA INFORMAL.

FECHA:

PARTIDA N° DESCRIPCIONMEDIDAS

UNDLARGO ANCHO ALTO

SISTEMA CONTRA INCENDIO

168 E-700.S/C

I/E. DETECTOR TERMICO

21.00 PZA 21.00

TOTAL EJECUTADO PZA 21.00

169 E-700.CID001

I/E. DIFUSOR DE SONIDO DE 8 OHMNIOS Y 5 W.

4.00 PZA 4.00

TOTAL EJECUTADO PZA 4.00

170 E-700.CID002

I/E DETECTOR OPTICO DE HUMO.

4.00 PZA 4.00

TOTAL EJECUTADO PZA 4.00

171 E-700.CIE000

SUMINISTRO Y COLOCACION DE EXTINTORES DE POLVO QUIMICO. TIPO ABC. 10 LBS.

4.00 PZA 4.00

TOTAL EJECUTADO PZA 4.00

172 E-700.CIG001

SUMINISTRO, TRANSPORTE E INSTALACION DE CAJAS PARA EXTINTORES. (EMPOTRABLE)

4.00 PZA 4.00

TOTAL EJECUTADO PZA 4.00

173 E-700.CII001

I/E. SUMINISTRO E INSTALACION DE ESTACIONES MANUALES DE DOBLE ACCION.

4.00 PZA 4.00

TOTAL EJECUTADO PZA 4.00

174 E-700.S/C.01

SUMINISTRO E INSTALACION DE CENTRAL DE INCENDIOS DE 8 ZONAS HASTA 4 DIFUSORES DE SONIDOS DE 10 W. INCLUYE BATERIA.

1.00 UND 1.00

TOTAL EJECUTADO UND 1.00

175 E-700.S/C.02

SUMINISTRO, TRANSPORTE E INSTALACION DE CONEXION SIAMESA TIPO "Y" 2 1/2" X 4"

1.00 PZA 1.00

TOTAL EJECUTADO PZA 1.00

176 E-643.002.039

SUMINISTRO, TRANSPORTE DE VALVULA DE RETENCION VERTICAL (MARACA - CHECK VALVE), DE BRONCE, D= 2" (38 MM) (150 PSI)

1.00 PZA 1.00

TOTAL EJECUTADO PZA 1.00

177 E-700.CIG002-A

SUMINISTRO, TRANSPORTE E INSTALACION DE CAJAS CON MANGUERAS DE EXTINCION DE INCENDIO. INCLUYE PITON DE BRONCE DE 1 1/2".

2.00 PZA 2.00

TOTAL EJECUTADO PZA 2.00

178 E-521.S/C

I.E CABLE DE COBRE, TRENSADO, REVESTIDO, TF CALIBRE 18

1700.00 ML 1,700.00

TOTAL EJECUTADO ML 1,700.00

179 E-531.210.010

I.E. CAJETINES METALICOS, SALIDA DE 1/2", PROFUNDIDAD 1 1/2". OCTOGONAL 4" (10.2 CM).

25.00 PZA 25.00

TOTAL EJECUTADO PZA 25.00

ING. RESIDENTE/CONTRATISTA FISCAL ING. INSPECTOR

EMPRESA: .

ELEMET IGUALES

CANT. TOTAL

CONTRATO N°REPUBLICA BOLIVARIANA DE VENEZUELA

ALCALDIA DEL MUNICIPIO GIRARDOTDIRECCION DE OBRAS PUBLICAS

HABITAT VIVIENDA Y ASUNTOS SOCIALES

COMPUTOS METRICOS

OBRA: ADECUACION INTEGRAL Y CONSTRUCCION DE INSTALACIONES PARA LA REUBICACION DE LA ECONOMIA INFORMAL.

FECHA:

PARTIDA N° DESCRIPCIONMEDIDAS

UNDLARGO ANCHO ALTO

EMPRESA: .

ELEMET IGUALES

CANT. TOTAL

CONTRATO N°REPUBLICA BOLIVARIANA DE VENEZUELA

ALCALDIA DEL MUNICIPIO GIRARDOTDIRECCION DE OBRAS PUBLICAS

HABITAT VIVIENDA Y ASUNTOS SOCIALES

180 E-531.210.510

I.E. CAJETINES METALICOS, SALIDA 1/2 - 3/4 PLG PROFUNDIDAD 1 1/2 PLG. RECTANGULARES 4X2 PLG (10.2 CM X 5.1 CM). PARA TOMAS E INTERRUPTORES

40.00 PZA 40.00

TOTAL EJECUTADO PZA 40.00

181 E-512.211.019

I.E. TUBERIA DE HIERRO GALVANIZADO, SIN ROSCA, TIPO EMT, EMBUTIDA. D= 3/4" (19 MM). INCLUYE TRANS. MATERIAL HASTA 50 KM.

260.00 ML 260.00

TOTAL EJECUTADO ML 260.00

182 E-611.111.051

52.70 ML 52.70

TOTAL EJECUTADO ML 52.70

OBRAS DE SERVICIO

183 E-802.305.S/C.01

2.00 PZA 2.00

TOTAL EJECUTADO PZA 2.00

184 E-802.305.S/C.02

4.00 PZA 4.00

TOTAL EJECUTADO PZA 4.00

185 E-8-D-S/C.

PINTURA EN FRANJA DE ANCHO 10 CMS. PARA DEMARCACION.

27.00 4.00 ML 108.00

7.00 2.00 ML 14.00

5.50 2.00 ML 11.00

11.50 1.00 ML 11.50

0.50 1.00 ML 0.50

16.50 1.00 ML 16.50

23.00 1.00 ML 23.00

3.00 2.00 ML 6.00

TOTAL EJECUTADO ML 190.50

186 E-SEÑALIZACION

SEÑALIZACIONES VARIAS EN ACRILICO.

12.00 UND 12.00

TOTAL EJECUTADO UND 12.00

TRANSPORTES

187 E-903.142.020

1245.97 20.00 M3.KM 24,919.40

1200.70 20.00 M3.KM 24,014.00

TOTAL EJECUTADO M3.KM 48,933.40

188 E-904.242.025

TRANSPORTE URBANO EN CAMIONES DE MATERIALES PROVENIENTES DE MOVIMIENTO DE TIERRA, MEDIDO POR SECCIONES, A DISTANCIA MAYOR DE 20 KM.

1019.60 20.00 M3.KM 20,392.00

TOTAL EJECUTADO M3.KM 20,392.00

SUMINISTRO, TRANSPORTE E INSTALACION TUBERIA AGUA CLARA, H.G., 2" ISO II, 150 PSI. AMBIENTE EXTERIOR AL RECINTO SANITARIO. INCLUYE CONEXIONES. TRANS. MATERIAL HASTA 50 KM

CONSTRUCCION DE TANQUILLAS DE AGUAS SERVIDAS DE CONCRETO FCC=180 KG/CM2 A LOS 28 DIAS, DE 0.80 X 0.80 X 0.80, CORRESPONDIENTE A O.S. INCLUYE ENCOFRADO, ACERO DE REFUERZO, Y TAPA DEL MISMO MATERIAL Y EXCAVACION.

CONSTRUCCION DE TANQUILLAS DE AGUAS SERVIDAS DE CONCRETO FCC=180 KG/CM2 A LOS 28 DIAS, DE 0.40 X 0.40 X 0.40, CORRESPONDIENTE A O.S. INCLUYE ENCOFRADO, ACERO DE REFUERZO, Y TAPA DEL MISMO MATERIAL Y EXCAVACION.

TRANSPORTE URBANO EN CAMIONES DE CUALQUIER TIPO DE MATERIAL, PROVENIENTE DE LA PREPARACION DEL SITIO, MEDIDO EN ESTADO SUELTO, DISTANCIA MAYOR QUE 15 KM. MENOR O IGUAL A 20 KM.

COMPUTOS METRICOS

OBRA: ADECUACION INTEGRAL Y CONSTRUCCION DE INSTALACIONES PARA LA REUBICACION DE LA ECONOMIA INFORMAL.

FECHA:

PARTIDA N° DESCRIPCIONMEDIDAS

UNDLARGO ANCHO ALTO

EMPRESA: .

ELEMET IGUALES

CANT. TOTAL

CONTRATO N°REPUBLICA BOLIVARIANA DE VENEZUELA

ALCALDIA DEL MUNICIPIO GIRARDOTDIRECCION DE OBRAS PUBLICAS

HABITAT VIVIENDA Y ASUNTOS SOCIALES

ING. RESIDENTE/CONTRATISTA FISCAL ING. INSPECTOR

COMPUTOS METRICOS

OBRA: ADECUACION INTEGRAL Y CONSTRUCCION DE INSTALACIONES PARA LA REUBICACION DE LA ECONOMIA INFORMAL.

FECHA:

PARTIDA N° DESCRIPCIONMEDIDAS

UNDLARGO ANCHO ALTO

ALTA TENSION

189 E-807.137.211

SUMINISTRO, TRANSPORTE Y COLOCACION DE POSTE DE 37´ 211 KG D=6" - 5"- 4". INCLUYE EXCAVACION Y BASE DE CONCRETO.

2.00 PZA 2.00

TOTAL EJECUTADO PZA 2.00

190 RAB106

CRUCETA DOBLE DE 1.80 MTS EN TERMINAL LINEA TRIFASICA DE 13.8 KV.

2.00 PZA 2.00

TOTAL EJECUTADO PZA 2.00

191 RAB127

TRES AISLADORES DE ESPIGA 15 KV.

2.00 PZA 2.00

TOTAL EJECUTADO PZA 2.00

192 RAB166

TRES PARARRAYOS PARA 15 KV EN CRUCETA EXISTENTE.

1.00 PZA 1.00

TOTAL EJECUTADO PZA 1.00

193 RAB169

TRES CORTACORRIENTES 15 KV EN CRUCETA EXISTENTE.

1.00 PZA 1.00

TOTAL EJECUTADO PZA 1.00

194 RAB202

CONDUCTOR ARVIDAL Nº 1/0

50.00 ML 50.00

TOTAL EJECUTADO ML 50.00

195 RAB231

CONEXION A TIERRA POSTE DE ALTA TENSION.

2.00 PZA 2.00

TOTAL EJECUTADO PZA 2.00

196 RAB243

BAJANTE DE H.G. (CONDUIT) DE 6 MTS X 4".

2.00 PZA 2.00

TOTAL EJECUTADO PZA 2.00

197 RAB273

PINTURA DE UN POSTE DE ALTA TENSION.

2.00 PZA 2.00

TOTAL EJECUTADO PZA 2.00

198 RAB338-1

TANQUILLA TIPO T-3- INCLUYE MARCO Y TAPA H.F. PESADA (120 X 120 X 140 CMS) Y BASE DE PIEDRA PICADA.

3.00 PZA 3.00

TOTAL EJECUTADO PZA 3.00

199 E-CABLE MONOPOLAR Nº2

I.E CABLE DE COBRE, MONOPOLAR CON AISLAMIENTO XLPE 15 KV Nº 2

320.00 ML 320.00

TOTAL EJECUTADO ML 320.00

200 E-CABLE MONOPOLAR Nº 2/0

I.E CABLE DE COBRE, MONOPOLAR CON AISLAMIENTO XLPE 15 KV Nº 2/0

320.00 ML 320.00

TOTAL EJECUTADO ML 320.00

201 E-521.224.207

I.E CABLE DE COBRE, TRENSADO, REVESTIDO, TTU, CALIBRE 500 MCM (20.65 MM)

60.00 ML 60.00

TOTAL EJECUTADO ML 60.00

202 E-521.224.173

I.E CABLE DE COBRE, TRENSADO, REVESTIDO, TTU, CALIBRE 350 MCM (17.30 MM)

20.00 ML 20.00

TOTAL EJECUTADO ML 20.00

EMPRESA: .

ELEMET IGUALES

CANT. TOTAL

CONTRATO N°REPUBLICA BOLIVARIANA DE VENEZUELA

ALCALDIA DEL MUNICIPIO GIRARDOTDIRECCION DE OBRAS PUBLICAS

HABITAT VIVIENDA Y ASUNTOS SOCIALES

COMPUTOS METRICOS

OBRA: ADECUACION INTEGRAL Y CONSTRUCCION DE INSTALACIONES PARA LA REUBICACION DE LA ECONOMIA INFORMAL.

FECHA:

PARTIDA N° DESCRIPCIONMEDIDAS

UNDLARGO ANCHO ALTO

EMPRESA: .

ELEMET IGUALES

CANT. TOTAL

CONTRATO N°REPUBLICA BOLIVARIANA DE VENEZUELA

ALCALDIA DEL MUNICIPIO GIRARDOTDIRECCION DE OBRAS PUBLICAS

HABITAT VIVIENDA Y ASUNTOS SOCIALES

ING. RESIDENTE/CONTRATISTA FISCAL ING. INSPECTOR

203 RAB313

BANCADA DE DOS TUBOS DE PVC 4"0 EN CTO. (RCC 100 KG/CM2) PARA A.T. (A2C-4"0)

80.00 ML 80.00

TOTAL EJECUTADO ML 80.00

204 E-561.110.

I.E. INTERRUPTOR DE POTENCIA DE 700 AMP.

1.00 PZA 1.00

TOTAL EJECUTADO PZA 1.00

205 E-PAD-MOUNTED 75KVA

TRANSFORMADOR TRIFASICO TIPO PAD-MOUNTED, CAPACIDAD 75 KVA

1.00 PZA 1.00

TOTAL EJECUTADO PZA 1.00

206 E-COPAS

S.I. DE COPAS TERMINALES TERMOCONTRAIDAS DE USO EXTERIOR PARA CONDUCTORES 15 KV.

2.00 JGO 2.00

TOTAL EJECUTADO JGO 2.00

207 E-EMPALME 15K

I.E. EMPALME CONTRACTIL DE 15 KV

3.00 JGO 3.00

TOTAL EJECUTADO JGO 3.00

208 RAB074

PERCHA DE CINCO AISLADORES PARA ALINEACION.

1.00 PZA 1.00

TOTAL EJECUTADO PZA 1.00

209 E-BARRAS

S/T/C DE BARRAS COOPERWELD DE 5/8" X 2.40 MTS.

8.00 PZA 8.00

TOTAL EJECUTADO PZA 8.00

210 E-521.010.000

I.E CABLE DE COBRE, DESNUDO, SOLIDO O TRENZADO PARA DIFERENTES CALIBRES. INCLUYE TRANS. MATERIAL HASTA 50 KM.

20.00 KG 20.00

TOTAL EJECUTADO KG 20.00

211 E-ACOPLES

SUMINISTRO Y COLOCACION DE TERMINAL DE ACOPLE DE A.T. 15 KV

1.00 JGO 1.00

TOTAL EJECUTADO JGO 1.00

MOBILIARIO

212 E-BALANZA

SUMINISTRO Y TRANSPORTE DE BALANZA MECANICA COLGANTE

12.00 PZA 12.00

TOTAL EJECUTADO PZA 12.00

213 E-MUEBLE DISP. 2,10 X 1,5 X 35 M

40.00 PZA 40.00

TOTAL EJECUTADO PZA 40.00

214 E-MUEBLE DISP. 2,10 X 1,5 X 70

54.00 PZA 54.00

TOTAL EJECUTADO PZA 54.00

215 E-CESTA 75X78X72 CM.

188.00 PZA 188.00

TOTAL EJECUTADO PZA 188.00

SUMINISTRO Y TRANSPORTE DE CARRO DISPENSADOR DE FRUTAS Y VERDURAS DE 2.10 X 1.50 X .35 MTS. CON ESTRUCTURA EN TUBO CUADRADO DE 1 1/2" EN HIERRO. CAJON CON PUERTAS EN LAMINAS DE HIERRO CAL. 18. FONDEADO CON ANTICORROSIVO Y PINTURA DE ESMALTE SECAMIENTO RAPIDO.

SUMINISTRO Y TRANSPORTE DE CARRO DISPENSADOR DE FRUTAS Y VERDURAS DE 2.10 X 1.50 X .70 MTS. CON ESTRUCTURA EN TUBO CUADRADO DE 1 1/2" EN HIERRO. CAJON CON PUERTAS EN LAMINAS DE HIERRO CAL. 18. FONDEADO CON ANTICORROSIVO Y PINTURA DE ESMALTE SECAMIENTO RAPIDO

SUMINISTRO Y TRANSPORTE DE CESTA TIPO REJILLA EN CABILLA EN HIERRO GALVANIZADO D= 5 MM. RUEDAS DE 4" GIRATORIAS Y FIJAS EN POLIURETANO CON BASE CROMADA.

COMPUTOS METRICOS

OBRA: ADECUACION INTEGRAL Y CONSTRUCCION DE INSTALACIONES PARA LA REUBICACION DE LA ECONOMIA INFORMAL.

FECHA:

PARTIDA N° DESCRIPCIONMEDIDAS

UNDLARGO ANCHO ALTO

EMPRESA: .

ELEMET IGUALES

CANT. TOTAL

CONTRATO N°REPUBLICA BOLIVARIANA DE VENEZUELA

ALCALDIA DEL MUNICIPIO GIRARDOTDIRECCION DE OBRAS PUBLICAS

HABITAT VIVIENDA Y ASUNTOS SOCIALES

ING. RESIDENTE/CONTRATISTA FISCAL ING. INSPECTOR

216 E-PASAMANO

S/C DE PASAMANOS DE ACERO INOXIDABLE FIJADA EN PARED.

2.00 ML 2.00

217 E-CAVA 250X165X250 CMS

SUMINISTRO, TRANSPORTE Y COLOCACION DE CAVA REFRIGERACION DE HORTALIZAS Y VERDURAS DE 250 x 165 x 250 CMS. E= 8 CMS.

3.00 UND 3.00

TOTAL EJECUTADO UND 3.00

218 E-CAVA 250X165X250 CMS

SUMINISTRO, TRANSPORTE Y COLOCACION DE REFRIGERACION DE HORTALIZAS Y VERDURAS DE 205 x 165 x 250 CMS. E= 8 CMS.

1.00 UND 1.00

TOTAL EJECUTADO UND 1.00

219 E-667.121.000

S/T/I DE SISTEMA HIDRONEUMATICO DE CAPACIDAD DE TANQUE DE 600 GALONES. INCLUYE 2 BOMBA DE 5 HP. TABLERO DE CONTROL Y COMPRESOR.

1.00 UND 1.00

TOTAL EJECUTADO UND 1.00

COMPUTOS METRICOS

OBRA: ADECUACION INTEGRAL Y CONSTRUCCION DE INSTALACIONES PARA LA REUBICACION DE LA ECONOMIA INFORMAL.

FECHA:

PARTIDA N° DESCRIPCIONMEDIDAS

UNDLARGO ANCHO ALTO

EMPRESA: .

ELEMET IGUALES

CANT. TOTAL