CLASE 3 - 17-03-2014

6
PARTIDAS UND METRADO COLUMNAS ACERO KG 85485.55 ENCOFRADO M2 8235.80 CONCRETO M3 895.50 ACERO CUAD1 CUAD2 OPERARIO 2 24 OFICIAL 1 12 ENCOFRADO CUAD1 CUAD2 OPERARIO 1 20 OFICIAL 1 20 RENDIMIENTO 3000 JORNADA RECURSOS UND CUAD CANT OPERARIO HH 24 0.064 OFICIAL HH 12 0.032 ACERO CORRUGADO KG 1.05 ALAMBRE KG 0.2 HERRAMIENTAS MANUALES %MO 5% CANT UNIT = #CUAD*JORNADA/REND PRECIO UNIT = HERR MANUALES * SUMA(PRECI PARC MANO OBRA) RENDIMIENTO 300 JORNADA RECURSOS UND CUAD CANT OPERARIO HH 20 0.533 OFICIAL HH 20 0.533 MADERA TORNILLO KG 5.4 ALAMBRE KG 0.1 HERRAMIENTAS MANUALES %MO 10% CANT UNIT = #CUAD*JORNADA/REND PRECIO UNIT = HERR MANUALES * SUMA(PRECI PARC MANO OBRA)

description

Clase con Fecha

Transcript of CLASE 3 - 17-03-2014

COLUMNASPARTIDASUNDMETRADOREND1DUR1 = METR/RENDNRO DE CUADREND 2DUR 2DURACION PROYECTCOLUMNASACEROKG85485.55250341.9412300028.5028ENCOFRADOM28235.8015549.052030027.4528CONCRETOM3895.502044.78102004.485 ACEROCUAD1CUAD2CONCRETOCUAD1CUAD2OPERARIO224OPERARIO220OFICIAL112OFICIAL110PEON10100ENCOFRADOCUAD1CUAD2OPERADOR110OPERARIO120MEZCLADORA110OFICIAL120ANALISIS TOTAL DE RECURSOS DE ACERORENDIMIENTO3000JORNADA8HORAS/DIARECURSOSUNDCUADCANTPRECIO UNITAPRECIO PARCIALTIPO DE RECURSOMETRADOCANT TOTALCOSTO TOTALOPERARIOHH240.064150.96TRABAJO85485.555471.0882066.13OFICIALHH120.032120.38TRABAJO85485.552735.5432826.45ACERO CORRUGADOKG1.0522.10MATERIAL85485.5589759.83179519.66ALAMBREKG0.22.50.50MATERIAL85485.5517097.1142742.78HERRAMIENTAS MANUALES%MO5%1.340.07COSTO85485.554274.285744.63CU4.01CT342899.64CANT UNIT = #CUAD*JORNADA/RENDMETRADO85485.55PRECIO UNIT = HERR MANUALES * SUMA(PRECI PARC MANO OBRA)COSTO TOTAL342899.64ANALISIS TOTAL DE RECURSOS DE ENCOFRADORENDIMIENTO300JORNADA8HORAS/DIARECURSOSUNDCUADCANTPRECIO UNITAPRECIO PARCIALTIPO DE RECURSOMETRADOCANT TOTALCOSTO TOTALOPERARIOHH200.533158.00TRABAJO8235.804392.4365886.40OFICIALHH200.533126.40TRABAJO8235.804392.4352709.12MADERA TORNILLOKG5.4316.20MATERIAL8235.8044473.32133419.96ALAMBREKG0.12.50.25MATERIAL8235.80823.582058.95HERRAMIENTAS MANUALES%MO10%14.401.44COSTO8235.80823.5811859.55CU32.29CT265933.98CANT UNIT = #CUAD*JORNADA/RENDMETRADO8235.80PRECIO UNIT = HERR MANUALES * SUMA(PRECI PARC MANO OBRA)COSTO TOTAL265933.98ANALISIS TOTAL DE RECURSOS DE CONCRETORENDIMIENTO200JORNADA8HORAS/DIARECURSOSUNDCUADCANTPRECIO UNITAPRECIO PARCIALTIPO DE RECURSOMETRADOCANT TOTALCOSTO TOTALOPERARIOHH200.8001512.00TRABAJO895.50716.4010746.00OFICIALHH100.400124.80TRABAJO895.50358.204298.40PEONHH1004.0001040.00TRABAJO895.503582.0035820.00OPERADORHH100.400156.00TRABAJO895.50358.205373.00CEMENTOBLS920180.00MATERIAL895.508059.50161190.00ARENA GRUESAM30.83024.00MATERIAL895.50716.4021492.00PIEDRA CHANCADAM30.54020.00MATERIAL895.50447.7517910.00AGUAM30.18101.80MATERIAL895.50161.191611.90MEZCLADORAHH100.4005020.00TRABAJO895.50358.2017910.00HERRAMIENTAS MANUALES%MO10%62.806.28COSTO895.5089.555623.74CU314.88CT281975.04CANT UNIT = #CUAD*JORNADA/RENDMETRADO895.50PRECIO UNIT = HERR MANUALES * SUMA(PRECI PARC MANO OBRA)COSTO TOTAL281975.04