CRONOGRAMA VALORIZADO ==================================== ACTIVIDAD : MANTENIMIENTO DE LA INFRAESTRUCTURA VIAL AV CIRCUNAVALACION MALECON RIBEREÑO DESDE EL PUENTE LA VILLA HASTA EL EMPALME CON LA CARRETERA PANAMERICANA META : MANTENIMIENTO DE LA INFRAESTRUCTURA VIAL AV CIRCUNAVALACION MALECON RIBEREÑO DESDE EL PUENTE LA VILLA HASTA EL EMPALME CON LA CARRETERA PANAMERICANA CLIENTE : MUNICIPALIDAD PROVINCIAL MARISCAL NIETO UBICACIÓN : MOQUEGUA - MARISCAL NIETO - MOQUEGUA ITEM DESCRIPCION UND METRADO MES 01 MES 02 MES 03 MES 0 S/. % S/. % S/. % S/. 01 OBRAS Y ACTIVIDADES PRELIMINARES 01.01 OBRAS PROVISIONALES 01.01.01 ALMACEN, OFICINA, GUARDIANIA m2 80.00 67.20 5,376.00 5,376.00 100% 0.00 0% 0.00 0% 0.00 01.01.02 CARTEL DE IDENTIFICACION DE OBRA und 1.00 695.17 695.17 695.17 100% 0.00 0% 0.00 0% 0.00 01.01.03 CERCO PROVISIONAL DE CAMPAMENTO DE OBRA m 200.00 15.72 3,144.00 3,144.00 100% 0.00 0% 0.00 0% 0.00 01.01.04 ALMACENERO A PIE DE OBRA dia 112.00 60.48 6,773.76 1,693.44 25% 1,693.44 25% 1,693.44 25% 1,693.44 01.01.05 GUARDIAN A PIE DE OBRA dia 112.00 60.48 6,773.76 1,693.44 25% 1,693.44 25% 1,693.44 25% 1,693.44 01.02 TRABAJOS PRELIMINARES 01.02.01 MOVILIZACION Y DESMOVILIZACION DE MAQUINARIA und 2.00 3,064.32 6,128.64 6,128.64 100% 0.00 0% 0.00 0% 0.00 01.02.02 TRANSPORTE DE MATERIAL, HERRAMIENTAS MENORES Y EQUIPOS día 75.00 203.53 15,264.75 4,361.36 29% 4,361.36 29% 4,361.36 29% 2,180.68 01.02.03 DESBROCE DE TERRENO m2 590.00 1.15 678.50 678.50 100% 0.00 0% 0.00 0% 0.00 01.02.04 LIMPIEZA DE AREAS AFECTADAS m2 9,711.00 0.24 2,330.64 2,330.64 100% 0.00 0% 0.00 0% 0.00 01.02.05 TRAZO, NIVELES Y REPLANTEO TOPOGRAFICO PRELIMINAR m2 9,711.00 0.14 1,359.54 1,359.54 100% 0.00 0% 0.00 0% 0.00 01.02.06 CONTROL TOPOGRAFICO DURANTE PROCESO CONSTRUCTIVO m2 9,711.00 0.12 1,165.32 0.00 0% 582.66 50% 582.66 50% 0.00 01.03 SEGURIDAD Y SALUD 01.03.01 EQUIPO DE PROTECCION INDIVIDUAL und 21.00 176.00 3,696.00 3,696.00 100% 0.00 0% 0.00 0% 0.00 01.03.02 EXAMENES PRE OCUPACIONALES und 21.00 120.00 2,520.00 2,520.00 100% 0.00 0% 0.00 0% 0.00 01.03.03 SEÑALIZACION TEMPORAL DE SEGURIDAD GLB 1.00 1,380.00 1,380.00 1,380.00 100% 0.00 0% 0.00 0% 0.00 02 PAVIMENTADO DE VIAS URBANAS 02.01 MOVIMIENTO DE TIERRAS 02.01.01 CORTE Y PICADO DE CARPETA ASFALTICA E=2" m2 202.12 6.23 1,259.21 1,076.25 85% 125.92 10% 57.04 5% 0.00 02.01.02 EXCAVACION MANUAL DE LA BASE GRANULAR E=0.20M m3 40.42 21.49 868.63 579.08 67% 289.54 33% 0.00 0% 0.00 02.01.03 ACARREO MANUAL DE MATERIAL EXCEDENTE DMT= 50 M m3 65.42 18.45 1,207.00 603.50 50% 603.50 50% 0.00 0% 0.00 02.01.04 CARGUIO Y TRANSPORTE DE MATERIAL EXCEDENTE m3 410.00 19.49 7,990.90 3,995.45 50% 3,995.45 50% 0.00 0% 0.00 02.01.05 ACARREO MANUAL DE MATERIAL BASE DMT= 50 M m3 40.42 18.45 745.75 248.58 33% 248.58 33% 248.58 33% 0.00 02.02 BACHEO EN PAVIMENTO FLEXIBLE 02.02.01 EXTENDIDO Y COMPACTADO DE BASE GRANULAR E=0.20 M m2 202.12 14.66 2,963.08 2,963.08 100% 0.00 0% 0.00 0% 0.00 02.02.02 IMPRIMACION ASFALTICA MANUAL m2 202.12 5.77 1,166.23 1,166.23 100% 0.00 0% 0.00 0% 0.00 02.02.03 PREPARACION DE MEZCLA ASFALTICA EN FRIO m3 12.36 693.29 8,569.06 8,569.06 100% 0.00 0% 0.00 0% 0.00 02.02.04 ACARREO MANUAL DE MEZCLA ASFALTICA DMT= 50 M m3 12.36 18.45 228.04 228.04 100% 0.00 0% 0.00 0% 0.00 02.02.05 m2 202.12 6.05 1,222.83 1,222.83 100% 0.00 0% 0.00 0% 0.00 02.03 MORTERO ASFALTICO (SLURRY SEAL) 02.03.01 MORTERO ASFALTICO EMULSIONADO E=10MM m2 7,056.00 12.13 85,589.28 57,059.52 67% 28,529.76 33% 0.00 0% 0.00 03 TRATAMIENTO DE BERMAS 03.01 MOVIMIENTO DE TIERRAS PRECIO (S/.) PARCIAL (S/.) EXTENDIDO Y COMPACTADO MANUAL DE MEZCLA ASFALTICA EN FRIO

description

ergregrff vf

Transcript of 8. CRONOG VALORIZADO

Page 1: 8. CRONOG VALORIZADO

CRONOGRAMA VALORIZADO====================================

ACTIVIDAD : MANTENIMIENTO DE LA INFRAESTRUCTURA VIAL AV CIRCUNAVALACION MALECON RIBEREÑO DESDE EL PUENTE LA VILLA HASTA EL EMPALME CON LA CARRETERA PANAMERICANA

META : MANTENIMIENTO DE LA INFRAESTRUCTURA VIAL AV CIRCUNAVALACION MALECON RIBEREÑO DESDE EL PUENTE LA VILLA HASTA EL EMPALME CON LA CARRETERA PANAMERICANA

CLIENTE : MUNICIPALIDAD PROVINCIAL MARISCAL NIETOUBICACIÓN : MOQUEGUA - MARISCAL NIETO - MOQUEGUA

ITEM DESCRIPCION UND METRADO PRECIO (S/.)MES 01 MES 02 MES 03 MES 04

TOTALS/. % S/. % S/. % S/. %

01 OBRAS Y ACTIVIDADES PRELIMINARES

01.01 OBRAS PROVISIONALES

01.01.01 ALMACEN, OFICINA, GUARDIANIA m2 80.00 67.20 5,376.00 5,376.00 100% 0.00 0% 0.00 0% 0.00 0% 5,376.00

01.01.02 CARTEL DE IDENTIFICACION DE OBRA und 1.00 695.17 695.17 695.17 100% 0.00 0% 0.00 0% 0.00 0% 695.17

01.01.03 CERCO PROVISIONAL DE CAMPAMENTO DE OBRA m 200.00 15.72 3,144.00 3,144.00 100% 0.00 0% 0.00 0% 0.00 0% 3,144.00

01.01.04 ALMACENERO A PIE DE OBRA dia 112.00 60.48 6,773.76 1,693.44 25% 1,693.44 25% 1,693.44 25% 1,693.44 25% 6,773.76

01.01.05 GUARDIAN A PIE DE OBRA dia 112.00 60.48 6,773.76 1,693.44 25% 1,693.44 25% 1,693.44 25% 1,693.44 25% 6,773.76

01.02 TRABAJOS PRELIMINARES

01.02.01 MOVILIZACION Y DESMOVILIZACION DE MAQUINARIA und 2.00 3,064.32 6,128.64 6,128.64 100% 0.00 0% 0.00 0% 0.00 0% 6,128.64

01.02.02 TRANSPORTE DE MATERIAL, HERRAMIENTAS MENORES Y EQUIPOS día 75.00 203.53 15,264.75 4,361.36 29% 4,361.36 29% 4,361.36 29% 2,180.68 14% 15,264.75

01.02.03 DESBROCE DE TERRENO m2 590.00 1.15 678.50 678.50 100% 0.00 0% 0.00 0% 0.00 0% 678.50

01.02.04 LIMPIEZA DE AREAS AFECTADAS m2 9,711.00 0.24 2,330.64 2,330.64 100% 0.00 0% 0.00 0% 0.00 0% 2,330.64

01.02.05 TRAZO, NIVELES Y REPLANTEO TOPOGRAFICO PRELIMINAR m2 9,711.00 0.14 1,359.54 1,359.54 100% 0.00 0% 0.00 0% 0.00 0% 1,359.54

01.02.06 CONTROL TOPOGRAFICO DURANTE PROCESO CONSTRUCTIVO m2 9,711.00 0.12 1,165.32 0.00 0% 582.66 50% 582.66 50% 0.00 0% 1,165.32

01.03 SEGURIDAD Y SALUD

01.03.01 EQUIPO DE PROTECCION INDIVIDUAL und 21.00 176.00 3,696.00 3,696.00 100% 0.00 0% 0.00 0% 0.00 0% 3,696.00

01.03.02 EXAMENES PRE OCUPACIONALES und 21.00 120.00 2,520.00 2,520.00 100% 0.00 0% 0.00 0% 0.00 0% 2,520.00

01.03.03 SEÑALIZACION TEMPORAL DE SEGURIDAD GLB 1.00 1,380.00 1,380.00 1,380.00 100% 0.00 0% 0.00 0% 0.00 0% 1,380.00

02 PAVIMENTADO DE VIAS URBANAS

02.01 MOVIMIENTO DE TIERRAS

02.01.01 CORTE Y PICADO DE CARPETA ASFALTICA E=2" m2 202.12 6.23 1,259.21 1,076.25 85% 125.92 10% 57.04 5% 0.00 0% 1,259.21

02.01.02 EXCAVACION MANUAL DE LA BASE GRANULAR E=0.20M m3 40.42 21.49 868.63 579.08 67% 289.54 33% 0.00 0% 0.00 0% 868.63

02.01.03 ACARREO MANUAL DE MATERIAL EXCEDENTE DMT= 50 M m3 65.42 18.45 1,207.00 603.50 50% 603.50 50% 0.00 0% 0.00 0% 1,207.00

02.01.04 CARGUIO Y TRANSPORTE DE MATERIAL EXCEDENTE m3 410.00 19.49 7,990.90 3,995.45 50% 3,995.45 50% 0.00 0% 0.00 0% 7,990.90

02.01.05 ACARREO MANUAL DE MATERIAL BASE DMT= 50 M m3 40.42 18.45 745.75 248.58 33% 248.58 33% 248.58 33% 0.00 0% 745.75

02.02 BACHEO EN PAVIMENTO FLEXIBLE

02.02.01 EXTENDIDO Y COMPACTADO DE BASE GRANULAR E=0.20 M m2 202.12 14.66 2,963.08 2,963.08 100% 0.00 0% 0.00 0% 0.00 0% 2,963.08

02.02.02 IMPRIMACION ASFALTICA MANUAL m2 202.12 5.77 1,166.23 1,166.23 100% 0.00 0% 0.00 0% 0.00 0% 1,166.23

02.02.03 PREPARACION DE MEZCLA ASFALTICA EN FRIO m3 12.36 693.29 8,569.06 8,569.06 100% 0.00 0% 0.00 0% 0.00 0% 8,569.06

02.02.04 ACARREO MANUAL DE MEZCLA ASFALTICA DMT= 50 M m3 12.36 18.45 228.04 228.04 100% 0.00 0% 0.00 0% 0.00 0% 228.04

02.02.05 EXTENDIDO Y COMPACTADO MANUAL DE MEZCLA ASFALTICA EN FRIO E=2" m2 202.12 6.05 1,222.83 1,222.83 100% 0.00 0% 0.00 0% 0.00 0% 1,222.83

02.03 MORTERO ASFALTICO (SLURRY SEAL)

02.03.01 MORTERO ASFALTICO EMULSIONADO E=10MM m2 7,056.00 12.13 85,589.28 57,059.52 67% 28,529.76 33% 0.00 0% 0.00 0% 85,589.28

03 TRATAMIENTO DE BERMAS

03.01 MOVIMIENTO DE TIERRAS

PARCIAL (S/.)

Page 2: 8. CRONOG VALORIZADO

CRONOGRAMA VALORIZADO====================================

ACTIVIDAD : MANTENIMIENTO DE LA INFRAESTRUCTURA VIAL AV CIRCUNAVALACION MALECON RIBEREÑO DESDE EL PUENTE LA VILLA HASTA EL EMPALME CON LA CARRETERA PANAMERICANA

META : MANTENIMIENTO DE LA INFRAESTRUCTURA VIAL AV CIRCUNAVALACION MALECON RIBEREÑO DESDE EL PUENTE LA VILLA HASTA EL EMPALME CON LA CARRETERA PANAMERICANA

CLIENTE : MUNICIPALIDAD PROVINCIAL MARISCAL NIETOUBICACIÓN : MOQUEGUA - MARISCAL NIETO - MOQUEGUA

ITEM DESCRIPCION UND METRADO PRECIO (S/.)MES 01 MES 02 MES 03 MES 04

TOTALS/. % S/. % S/. % S/. %

PARCIAL (S/.)

03.01.01 EXCAVACION MANUAL DE LA BASE GRANULAR E=0.10M m3 422.90 19.20 8,119.68 0.00 0% 4,059.84 50% 4,059.84 50% 0.00 0% 8,119.68

03.01.02 ACARREO MANUAL DE MATERIAL EXCEDENTE DMT= 50 M m3 449.33 18.45 8,290.14 0.00 0% 4,145.07 50% 4,145.07 50% 0.00 0% 8,290.14

03.01.03 CARGUIO Y TRANSPORTE DE MATERIAL EXCEDENTE m3 449.33 19.49 8,757.44 0.00 0% 4,378.72 50% 4,378.72 50% 0.00 0% 8,757.44

03.01.04 ACARREO MANUAL DE MATERIAL BASE DMT= 50 M m3 422.90 18.45 7,802.51 0.00 0% 3,901.25 50% 3,901.25 50% 0.00 0% 7,802.51

Page 3: 8. CRONOG VALORIZADO

CRONOGRAMA VALORIZADO====================================

ACTIVIDAD : MANTENIMIENTO DE LA INFRAESTRUCTURA VIAL AV CIRCUNAVALACION MALECON RIBEREÑO DESDE EL PUENTE LA VILLA HASTA EL EMPALME CON LA CARRETERA PANAMERICANA

META : MANTENIMIENTO DE LA INFRAESTRUCTURA VIAL AV CIRCUNAVALACION MALECON RIBEREÑO DESDE EL PUENTE LA VILLA HASTA EL EMPALME CON LA CARRETERA PANAMERICANA

CLIENTE : MUNICIPALIDAD PROVINCIAL MARISCAL NIETOUBICACIÓN : MOQUEGUA - MARISCAL NIETO - MOQUEGUA

ITEM DESCRIPCION UND METRADO PRECIO (S/.)MES 01 MES 02 MES 03 MES 04

TOTALS/. % S/. % S/. % S/. %

PARCIAL (S/.)

03.02 BASE EN BERMAS

03.02.01 EXTENDIDO Y COMPACTADO DE BASE GRANULAR E=0.10 M m2 4,229.00 11.13 47,068.77 0.00 0% 47,068.77 100% 0.00 0% 0.00 0% 47,068.77

03.02.02 IMPRIMACION ASFALTICA m2 4,229.00 6.04 25,543.16 0.00 0% 17,028.77 67% 8,514.39 33% 0.00 0% 25,543.16

03.03 MORTERO ASFALTICO (SLURRY SEAL)

03.04 MORTERO ASFALTICO EMULSIONADO E=10MM m2 2,779.00 12.13 33,709.27 0.00 0% 0.00 0% 33,709.27 100% 0.00 0% 33,709.27

04 OBRAS DE CONCRETO SIMPLE

04.01 MOVIMIENTO DE TIERRAS

04.01.01 EXCAVACION MANUAL DE HOYOS PARA POSTES DELINEADORES m3 3.40 21.49 73.07 0.00 0% 73.07 100% 0.00 0% 0.00 0% 73.07

04.01.02 ACARREO MANUAL DE MATERIAL EXCEDENTE DMT= 50 M m3 4.25 18.45 78.42 0.00 0% 39.21 50% 39.21 50% 0.00 0% 78.42

04.01.03 CARGUIO Y TRANSPORTE DE MATERIAL EXCEDENTE m3 4.25 19.49 82.83 0.00 0% 41.42 50% 41.42 50% 0.00 0% 82.83

04.02 CONCRETO SIMPLE EN VARIOS ELEMENTOS

04.02.01 m3 3.40 127.66 434.040.00 0% 289.36 67% 144.68 33% 0.00 0% 434.04

04.02.02 POSTES DELINEADORES und 34.00 22.88 777.92 0.00 0% 518.61 67% 259.31 33% 0.00 0% 777.92

04.02.03 RESANE DE VEREDAS m2 42.60 25.91 1,103.77 0.00 0% 0.00 0% 1,103.77 100% 0.00 0% 1,103.77

04.02.04 ENCOFRADO Y DESENCOFRADO DE VEREDAS m2 42.60 24.18 1,030.07 0.00 0% 0.00 0% 1,030.07 100% 0.00 0% 1,030.07

05 SEÑALIZACION VIAL URBANO

05.01 SEÑALIZACION HORIZONTAL

05.01.01 PINTADO DE LINEA DE BORDE (ANCHO=10 CM) m 3,180.00 1.59 5,056.20 0.00 0% 0.00 0% 0.00 0% 5,056.20 100% 5,056.20

05.01.02 PINTADO DE LINEA CENTRAL (ANCHO=10 CM) m 1,090.00 1.81 1,972.90 0.00 0% 0.00 0% 0.00 0% 1,972.90 100% 1,972.90

05.01.03 PINTADO DE PASE PEATONAL m2 148.20 10.29 1,524.98 0.00 0% 0.00 0% 0.00 0% 1,524.98 100% 1,524.98

05.01.04 PINTADO DE SIMBOLOS Y LETRAS m2 19.90 11.58 230.44 0.00 0% 0.00 0% 0.00 0% 230.44 100% 230.44

6 OBRAS COMPLEMENTARIAS

6.01 TRABAJOS PRELIMINARES

06.01.01 LIMPIEZA FINAL EN OBRA m2 9,835.00 2.75 27,046.25 0.00 0% 0.00 0% 0.00 0% 27,046.25 100% 27,046.25

COSTO DIRECTO 347,797.93 112,768.36 32.42% 123,667.75 35.56% 69,963.51 20.12% 41,398.33 11.90% 347,797.93

========== ========== ========== ========== ========== ==========

GASTOS GENERALES Y DIRECCION TECNICA (12%) 41,735.75 13,532.20 14,840.13 8,395.62 4,967.80 41,735.75

GASTOS DE SUPERVISION Y EVALUACION (4%) 13,911.92 4,510.73 4,946.71 2,798.54 1,655.93 13,911.92

GASTOS DE LIQUIDACION DE OBRA (2%) 6,955.96 2,255.37 2,473.35 1,399.27 827.97 6,955.96

GASTOS ADMINISTRATIVOS (3%) 10,433.94 3,383.05 3,710.03 2,098.91 1,241.95 10,433.94

========== ========== ========== ========== ========== ==========

TOTAL PRESUPUESTO 420,835.50 136,449.71 149,637.97 84,655.85 50,091.98 420,835.50

CONCRETO CICLOPEO f'c=140 kg/cm2 + 30% PM PARA CIMIENTO DE POSTES DELINEADORES