Transcript of 5.PLANILLA DE METRADOS - SSHH
PROYECTO SNIP 107240
COMPONENTE
FORMULA
Lugar : CP. ICHOCA - HUARAZ - ANCASH
Fecha : MAYO DEL 2010
LARGO ANCHO ALTO01 TRABAJOS PRELIMINARES
01.01 LIMPIEZA DE TERRENO MANUAL 1 10.00 8.12 81.20 81.20 m2
01.02 TRAZO Y REPLANTEO PRELIMINAR 1 10.00 8.12 81.20 81.20 m2
01.03 TRAZO Y REPLANTEO DURANTE EL PROCESO1 10.00 8.12 81.20 81.20 glb
02 MOVIMIENTO DE TIERRAS
02.01 EXCAVACION MANUAL (NIVELACIÓN) 1 12.00 10.00 0.20 24.00 24.00 m3
02.02 EXCAVACION MANUAL PARA CIMIENTOS HASTA PROF.=1.40m EN TERRENO NORMAL 21.48 m3
EN EL EJE A 1 6.50 0.60 1.00 3.90
EN EL EJE D 1 6.50 0.60 1.00 3.90
EN EL EJE B 1 4.55 0.60 1.00 2.73
1 1.60 0.60 1.00 0.96
EN EL EJE C 1 4.55 0.60 1.00 2.73
EJE 1 1 5.10 0.60 1.00 3.06
EJE 3 1 6.00 0.60 1.00 3.60
1 1.00 0.60 1.00 0.60
02.03 RELLENO Y COMPAC. C/MATERIAL PROPIO SELECCIONADO 10.34 m3
EN EL EJE A 1 6.50 0.45 0.30 0.88
EN EL EJE D 1 6.50 0.45 0.30 0.88
EN EL EJE B 1 4.55 0.45 0.30 0.61
1 1.60 0.45 0.30 0.22
EN EL EJE C 1 4.55 0.45 0.30 0.61
EJE 1 1 5.10 0.45 0.30 0.69
EJE 3 1 6.00 0.45 0.30 0.81
1 1.00 0.45 0.30 0.14
EJE 1 1 11.90 0.47 0.50 2.80
EJE 5 1 3.75 0.47 0.50 0.88
EJE 7 1 7.75 0.47 0.50 1.82
02.04 ACARREO DE MATERIAL EXCEDENTE HASTA DIST. PROMEDIO = 30m25% de Esponjamiento 43.93 43.93 m3
02.05 ELIMINACIÓN DE MATERIAL EXCEDENTE C/MAQUINARIA 43.93 m3
02.06 AFIRMADO E=4" EN PISOS Y VEREDAS 1 5.90 6.55 38.65 38.65 m2
03 OBRAS DE CONCRETO SIMPLE
03.01 CIMIENTOS CORRIDOS MEZCLA 1:10, C:H 30% P.G. 15.03 m3
EN EL EJE A 1 6.50 0.60 0.70 2.73
EN EL EJE D 1 6.50 0.60 0.70 2.73
EN EL EJE B 1 4.55 0.60 0.70 1.91
1 1.60 0.60 0.70 0.67
EN EL EJE C 1 4.55 0.60 0.70 1.91
EJE 1 1 5.10 0.60 0.70 2.14
EJE 3 1 6.00 0.60 0.70 2.52
1 1.00 0.60 0.70 0.42
Nº DE VECES
MEDIDAS PARCIAL TOTAL UND.
Nº DE LADO
S
PLANILLA DE METRADOS: "MEJORAMIENTO DE LOS SERVICIOS EDUCATIVOS DE LA I.E. 86079 – ICHOCA, DISTRITO DE HUARAZ, PROVINCIA DE HUARAZ - ANCASH"
: "CONSTRUCCIÓN DE AULAS Y SERVICIOS HIGIÉNICOS DE LA I.E. 86079 - ICHOCA"
PARTIDA Nº DESCRIPCION
: CONSTRUCCION DE SERVICIOS HIGIENICOS
PROYECTO SNIP 107240
COMPONENTE
FORMULA
Lugar : CP. ICHOCA - HUARAZ - ANCASH
Fecha : MAYO DEL 2010
LARGO ANCHO ALTONº DE
VECESMEDIDAS
PARCIAL TOTAL UND.Nº DE LADO
S
PLANILLA DE METRADOS: "MEJORAMIENTO DE LOS SERVICIOS EDUCATIVOS DE LA I.E. 86079 – ICHOCA, DISTRITO DE HUARAZ, PROVINCIA DE HUARAZ - ANCASH"
: "CONSTRUCCIÓN DE AULAS Y SERVICIOS HIGIÉNICOS DE LA I.E. 86079 - ICHOCA"
PARTIDA Nº DESCRIPCION
: CONSTRUCCION DE SERVICIOS HIGIENICOS
03.02 CONCRETO PARA SOBRECIMIENTO C:H 1:8+25% P.M. 2.15 m3
EN EL EJE A 1 6.50 0.15 0.40 0.39
EN EL EJE D 1 6.50 0.15 0.40 0.39
EN EL EJE B 1 4.55 0.15 0.40 0.27
1 1.60 0.15 0.40 0.10
EN EL EJE C 1 4.55 0.15 0.40 0.27
EJE 1 1 5.10 0.15 0.40 0.31
EJE 3 1 6.00 0.15 0.40 0.36
1 1.00 0.15 0.40 0.06
03.03 ENCOFRADO Y DESENCOFRADO DE SOBRECIMIENTOS 28.64 m2
EN EL EJE A 2 6.50 0.40 5.20
EN EL EJE D 2 6.50 0.40 5.20
EN EL EJE B 2 4.55 0.40 3.64
2 1.60 0.40 1.28
EN EL EJE C 2 4.55 0.40 3.64
EJE 1 2 5.10 0.40 4.08
EJE 3 2 6.00 0.40 4.80
2 1.00 0.40 0.80
03.04 DADOS DE CONCRETO 2 2.20 0.40 0.30 0.53 0.53 m3
03.05 ENCOFRADO Y DESENCOFRADO DE DADOS 4.84 m2
4 2.20 0.40 3.52
2 2.20 0.30 1.32
04 OBRAS DE CONCRETO ARMADO
04.01 CONCRETO f'c=175 Kg/cm P/VIGAS DE CIMENTACION 0.96 m3
EN EL EJE A 1 5.40 0.15 0.30 0.24
EN EL EJE D 1 5.40 0.15 0.30 0.24
EN EL EJE 1 1 5.90 0.15 0.30 0.27
EN EL EJE 3 1 4.70 0.15 0.30 0.21
04.02 ENCOFRADO Y DESENCOFRADO P/VIGAS DE CIMENTACION 12.84 m2
EN EL EJE A 2 5.40 0.30 3.24
EN EL EJE D 2 5.40 0.30 3.24
EN EL EJE 1 2 5.90 0.30 3.54
EN EL EJE 3 2 4.70 0.30 2.82
04.03 ACERO CORRUGADO fy=4200 kg/cm2 EN VIGAS DE CIMENTACIÓNCANTID. LONGITUD w (kg/m) 146.19 kg
EN EL EJE A
4 Ø 1/2" 1 4.00 8.00 0.994 33.40
Estribo Ø1/4" 1 46.00 0.60 0.250 7.25
EN EL EJE D
4 Ø 1/2" 1 4.00 8.00 0.994 33.40
Estribo Ø1/4" 1 46.00 0.60 0.250 7.25
EN EL EJE 1
4 Ø 1/2" 1 4.00 8.10 0.994 33.82
Estribo Ø1/4" 1 46.00 0.60 0.250 7.25
EN EL EJE 3
PROYECTO SNIP 107240
COMPONENTE
FORMULA
Lugar : CP. ICHOCA - HUARAZ - ANCASH
Fecha : MAYO DEL 2010
LARGO ANCHO ALTONº DE
VECESMEDIDAS
PARCIAL TOTAL UND.Nº DE LADO
S
PLANILLA DE METRADOS: "MEJORAMIENTO DE LOS SERVICIOS EDUCATIVOS DE LA I.E. 86079 – ICHOCA, DISTRITO DE HUARAZ, PROVINCIA DE HUARAZ - ANCASH"
: "CONSTRUCCIÓN DE AULAS Y SERVICIOS HIGIÉNICOS DE LA I.E. 86079 - ICHOCA"
PARTIDA Nº DESCRIPCION
: CONSTRUCCION DE SERVICIOS HIGIENICOS
4 Ø 1/2" 1 4.00 4.80 0.994 20.04
Estribo Ø1/4" 1 24.00 0.60 0.250 3.78
04.04 CONCRETO EN COLUMNAS f'c=210 Kg/cm2 1.50 m3
EN EL EJE 1
C-1 2 3.35 0.15 0.25 0.25
C-2 2 4.95 0.15 0.25 0.37
EN EL EJE 2
C-2 2 3.35 0.15 0.25 0.25
C-2 1 4.95 0.15 0.25 0.19
EN EL EJE 3
C-1 2 3.35 0.15 0.25 0.25
C-2 1 4.95 0.15 0.25 0.19
04.05 ENCOFRADO Y DESENCOFRADO NORMAL EN COLUMNAS 29.96 m2
EN EL EJE 1
C-1 4 3.35 0.15 2.01
C-1 4 3.35 0.25 3.35
C-2 4 4.95 0.15 2.97
C-2 4 4.95 0.15 2.97
EN EL EJE 2
C-2 4 3.35 0.15 2.01
C-2 4 3.35 0.25 3.35
C-2 2 4.95 0.15 1.49
C-2 2 4.95 0.25 2.48
EN EL EJE 3
C-1 4 3.35 0.15 2.01
4 3.35 0.25 3.35
C-2 2 4.95 0.15 1.49
C-2 2 4.95 0.25 2.48
04.06 ACERO CORRUGADO fy=4200 kg/cm2 EN COLUMNAS CANTID. LONGITUD w (kg/m) 310.92 kg
EN EL EJE 1
C-1
4 Ø 1/2" 2 4.00 4.85 0.994 40.50
Estribo Ø1/4" 2 50.00 0.60 0.250 15.75
C-2
4 Ø 1/2" 2 4.00 6.25 0.994 52.19
Estribo Ø1/4" 2 60.00 0.60 0.250 18.90
EN EL EJE 2
C-2
4 Ø 1/2" 2 4.00 4.85 0.994 40.50
Estribo Ø1/4" 2 50.00 0.60 0.250 15.75
C-2
4 Ø 1/2" 1 4.00 6.25 0.994 26.09
Estribo Ø1/4" 1 60.00 0.60 0.250 9.45
EN EL EJE 3
C-1
4 Ø 1/2" 2 4.00 4.85 0.994 40.50
Estribo Ø1/4" 2 50.00 0.60 0.250 15.75
PROYECTO SNIP 107240
COMPONENTE
FORMULA
Lugar : CP. ICHOCA - HUARAZ - ANCASH
Fecha : MAYO DEL 2010
LARGO ANCHO ALTONº DE
VECESMEDIDAS
PARCIAL TOTAL UND.Nº DE LADO
S
PLANILLA DE METRADOS: "MEJORAMIENTO DE LOS SERVICIOS EDUCATIVOS DE LA I.E. 86079 – ICHOCA, DISTRITO DE HUARAZ, PROVINCIA DE HUARAZ - ANCASH"
: "CONSTRUCCIÓN DE AULAS Y SERVICIOS HIGIÉNICOS DE LA I.E. 86079 - ICHOCA"
PARTIDA Nº DESCRIPCION
: CONSTRUCCION DE SERVICIOS HIGIENICOS
C-2
4 Ø 1/2" 1 4.00 6.25 0.994 26.09
Estribo Ø1/4" 1 60.00 0.60 0.250 9.45
04.07 CONCRETO EN VIGAS f'c=210 Kg/cm2 1.83 m3
VS-1
1 6.70 0.15 0.25 0.25
1 6.00 0.15 0.25 0.23
1 0.70 0.15 0.25 0.03
VS-2
2 6.20 0.15 0.25 0.47
1 2.20 0.15 0.25 0.08
2 4.20 0.15 0.25 0.32
2 6.00 0.15 0.25 0.45
04.08 ENCOFRADO Y DESENCOFRADO EN VIGAS 26.00 m2
VS-1
2 6.70 0.25 3.35
2 6.00 0.25 3.00
2 0.70 0.25 0.35
VS-2
4 6.20 0.25 6.20
2 2.20 0.25 1.10
4 4.20 0.25 4.20
4 6.00 0.25 6.00
2 6.00 0.15 1.80
04.09 ACERO CORRUGADO fy=4200 kg/cm2 EN VIGAS CANTID. LONGITUD w (kg/m) 279.23 kg
VS-1
4 Ø 1/2" 1 4.00 7.70 0.994 30.62
Estribo Ø1/4" 1 50.00 0.60 0.250 7.50
4 Ø 1/2" 1 4.00 7.00 0.994 27.83
Estribo Ø1/4" 1 45.00 0.60 0.250 6.75
4 Ø 1/2" 1 4.00 0.90 0.994 3.58
Estribo Ø1/4" 1 3.00 0.60 0.250 0.45
VS-2
4 Ø 1/2" 2 4.00 7.20 0.994 57.25
Estribo Ø1/4" 2 46.00 0.60 0.250 13.80
4 Ø 1/2" 1 4.00 2.80 0.994 11.13
Estribo Ø1/4" 1 16.00 0.60 0.250 2.40
4 Ø 1/2" 2 4.00 5.00 0.994 39.76
Estribo Ø1/4" 2 30.00 0.60 0.250 9.00
4 Ø 1/2" 2 4.00 7.00 0.994 55.66
Estribo Ø1/4" 2 45.00 0.60 0.250 13.50
05 ESTRUCTURAS DE MADERA Y COBERTURA
05.01 VIGAS DE MADERA 6"x3"x24' 2 6 12.00 3.00 6.00 216.00 216.00 p2
05.02 VIGAS DE MADERA 10"x3"x12' 2 1 12.00 3.00 10.00 60.00 60.00 p2
PROYECTO SNIP 107240
COMPONENTE
FORMULA
Lugar : CP. ICHOCA - HUARAZ - ANCASH
Fecha : MAYO DEL 2010
LARGO ANCHO ALTONº DE
VECESMEDIDAS
PARCIAL TOTAL UND.Nº DE LADO
S
PLANILLA DE METRADOS: "MEJORAMIENTO DE LOS SERVICIOS EDUCATIVOS DE LA I.E. 86079 – ICHOCA, DISTRITO DE HUARAZ, PROVINCIA DE HUARAZ - ANCASH"
: "CONSTRUCCIÓN DE AULAS Y SERVICIOS HIGIÉNICOS DE LA I.E. 86079 - ICHOCA"
PARTIDA Nº DESCRIPCION
: CONSTRUCCION DE SERVICIOS HIGIENICOS
05.03 CORREAS DE MADERA 3"x2"x24' 2 12 12.00 2.00 3.00 144.00 144.00 p2
05.04 COBETURA CON TEJA ANDINA 2 5.00 4.80 48.00 48.00 m2
05.05 CUMBRERAS DE TEJA ANDINA 1 10.00 10.00 10.00 m
06 MUROS Y TABIQUES DE ALBAÑILERIA
06.01 MURO DE LADRILLO KK DE ARCILLA DE SOGA 9x13x24cm 94.12 m2
EN EL EJE A 1 6.25 2.90 18.13
EN EL EJE B 1 3.80 2.90 11.02
1 1.75 2.90 5.08
EN EL EJE C 1 3.80 2.90 11.02
EJE D 1 6.25 2.90 18.13
EJE 3 2 2.50 2.90 14.50
EJE 1 2 2.80 2.90 16.24
06.02 MURO DE LADRILLO KK DE ARCILLA DE CANTO 9x13x24cm8 1.95 - 1.90 29.64 29.64 m2
07 REVOQUES, ENLUCIDOS Y MOLDURAS
07.01 TARRAJEO PRIMARIO RAYADO ACABADO CEMENTO - ARENA 87.22 m2
EN EL EJE A 1 5.80 1.40 8.12
EN EL EJE B 4 0.80 1.40 4.48
2 1.20 1.40 3.36
EN EL EJE C 4 0.80 1.40 4.48
EJE 1 2 2.50 1.40 7.00
EJE 3 2 2.00 1.40 5.60
16 1.95 1.40 43.68
LAVADERO
3 2.25 0.60 4.05
4 0.50 0.60 1.20
URINARIO
3 2.25 0.60 4.05
4 0.50 0.60 1.20
07.02 TARRAJEO EN INTERIORES Y EXTERIORES ACABADO CEMENTO - ARENA 168.81 m2
EN EL EJE A 1 6.25 - 2.90 18.13
1 6.25 - 1.90 11.88
EN EL EJE B 1 3.75 - 1.90 7.13
2 3.75 - 3.10 23.25
EN EL EJE C 1 3.75 - 1.90 7.13
2 2.00 - 1.90 7.60
EN EL EJE D 1 6.25 - 2.90 18.13
1 6.25 - 1.90 11.88
EJE 1 2 3.00 - 2.30 13.80
2 3.00 - 1.30 7.80
EJE 3 2 2.00 - 1.60 6.40
2 2.00 - 1.90 7.60
16 1.95 - 0.90 28.08
PROYECTO SNIP 107240
COMPONENTE
FORMULA
Lugar : CP. ICHOCA - HUARAZ - ANCASH
Fecha : MAYO DEL 2010
LARGO ANCHO ALTONº DE
VECESMEDIDAS
PARCIAL TOTAL UND.Nº DE LADO
S
PLANILLA DE METRADOS: "MEJORAMIENTO DE LOS SERVICIOS EDUCATIVOS DE LA I.E. 86079 – ICHOCA, DISTRITO DE HUARAZ, PROVINCIA DE HUARAZ - ANCASH"
: "CONSTRUCCIÓN DE AULAS Y SERVICIOS HIGIÉNICOS DE LA I.E. 86079 - ICHOCA"
PARTIDA Nº DESCRIPCION
: CONSTRUCCION DE SERVICIOS HIGIENICOS
07.03 VESTIDURA DE DERRAMES EN PUERTAS, VENTANAS 68.00 m
en ventanas 4 3.00 12.00
4 0.50 2.00
en puertas 2 2.20 4.40
1 1.00 1.00
4 2.80 11.20
2 1.00 2.00
8 1.80 14.40
REMATE DE PARAPETOS 1 3.80 3.80
1 11.50 11.50
1 5.70 5.70
07.04 BRUÑA EN MUROS 109.60 m
EJE A 4 2.90 11.60
1 5.30 5.30
1 5.80 5.80
EJE D 4 2.80 11.20
1 5.30 5.30
1 5.80 5.80
EJE 3 2 2.25 4.50
2 2.25 4.50
EJE 1 2 3.10 6.20
2 2.00 4.00
2 3.10 6.20
EJE B 1 4.00 4.00
8 1.95 15.60
EJE C 1 4.00 4.00
8 1.95 15.60
08 CIELORRASOS
08.01 CIELO RASO CON PLANCHAS DE FIBROCEMENTODE 1.20x2.40 m Y ALEROS 77.36 m2
CIELO RASO 2 7.30 3.10 45.26
ALEROS 2 7.50 1.50 22.50
FRISOS 4 4.80 0.50 9.60
09 PISOS Y PAVIMENTOS
09.01 FALSO PISO DE 4" CONCRETO 1:10 1 6.50 6.00 - 39.00 39.00 m2
09.02 PISO DE CEMENTO PULIDO 1 8.00 1.50 - 12.00 12.00 m2
09.03 PISO DE CERAMICA 35.90 m2
2 3.80 2.90 - 22.04
1 6.60 2.10 - 13.86
09.04 VEREDA DE CONCRETO DE 4" 28.35
PARTE FRONTAL 1 8.50 1.50 12.75
1 2.00 2.00 4.00
PARTE POSTERIOR 1 8.50 0.60 5.10
PARTE LATERAL 2 6.50 0.50 6.50
PROYECTO SNIP 107240
COMPONENTE
FORMULA
Lugar : CP. ICHOCA - HUARAZ - ANCASH
Fecha : MAYO DEL 2010
LARGO ANCHO ALTONº DE
VECESMEDIDAS
PARCIAL TOTAL UND.Nº DE LADO
S
PLANILLA DE METRADOS: "MEJORAMIENTO DE LOS SERVICIOS EDUCATIVOS DE LA I.E. 86079 – ICHOCA, DISTRITO DE HUARAZ, PROVINCIA DE HUARAZ - ANCASH"
: "CONSTRUCCIÓN DE AULAS Y SERVICIOS HIGIÉNICOS DE LA I.E. 86079 - ICHOCA"
PARTIDA Nº DESCRIPCION
: CONSTRUCCION DE SERVICIOS HIGIENICOS
09.05 ENCOFRADO Y DESENCOFRADO DE VEREDAS 10.80 m2
2 9.00 0.30 5.40
2 9.00 0.30 5.40
09.06 JUNTAS ASFALTICAS 17.50 m
EN VEREDAS HORIZONTAL 7 0.50 3.50
EN VEREDAS PERPENDICULAR 14 1.00 14.00
10 ZOCALOS Y CONTRAZOCALOS
10.01 CONTRAZOCALO DE CEMENTO S/COLOREAR H = 20 CM PULIDO 34.00 m
2 4.60 9.20
2 3.80 7.60
2 8.60 17.20
10.02 ZOCALO DE MAYOLICA 20X20CM 76.72 m2
EN EL EJE A 1 5.80 1.40 8.12
EN EL EJE B 4 0.80 1.40 4.48
2 1.20 1.40 3.36
EN EL EJE C 4 0.80 1.40 4.48
EJE 1 2 2.50 1.40 7.00
EJE 3 2 2.00 1.40 5.60
16 1.95 1.40 43.68
11 CARPINTERIA METALICA
11.01 PUERTA METALICA INCLUYE COLOCACION 16.55 m2
Puerta P-1 2 1.00 2.80 5.60
Puerta P-2 1 1.10 2.10 2.31
Puerta P-3 8 0.60 1.80 8.64
11.02 VENTANA METALICA, INCLUYE COLOCACION 6.00 m2
Ventana V-1 2 3.00 1.00 6.00
12 VIDRIOS, CRISTALES Y SIMILARES
12.01 VIDRIO SEMIDOBLE INCOLORO CRUDO 99.02 p2
Ventana V-1 2 3.00 - 1.00 64.58
Tragaluz de puertas 4 1.00 - 0.80 34.44
13 PINTURA
13.01 PINTURA LATEX EN MUROS INTERIORES Y EXTERIORES 2 MANOS 157.70 m2
EN EL EJE A 1 6.25 - 2.80 17.50
1 6.25 - 1.80 11.25
EN EL EJE B 1 3.75 - 1.80 6.75
2 3.75 - 3.00 22.50
EN EL EJE C 1 3.75 - 1.80 6.75
2 2.00 - 1.80 7.20
EN EL EJE D 1 6.25 - 2.80 17.50
1 6.25 - 1.80 11.25
EJE 1 2 3.00 - 2.20 13.20
2 3.00 - 1.20 7.20
EJE 3 2 2.00 - 1.50 6.00
PROYECTO SNIP 107240
COMPONENTE
FORMULA
Lugar : CP. ICHOCA - HUARAZ - ANCASH
Fecha : MAYO DEL 2010
LARGO ANCHO ALTONº DE
VECESMEDIDAS
PARCIAL TOTAL UND.Nº DE LADO
S
PLANILLA DE METRADOS: "MEJORAMIENTO DE LOS SERVICIOS EDUCATIVOS DE LA I.E. 86079 – ICHOCA, DISTRITO DE HUARAZ, PROVINCIA DE HUARAZ - ANCASH"
: "CONSTRUCCIÓN DE AULAS Y SERVICIOS HIGIÉNICOS DE LA I.E. 86079 - ICHOCA"
PARTIDA Nº DESCRIPCION
: CONSTRUCCION DE SERVICIOS HIGIENICOS
2 2.00 - 1.80 7.20
16 1.95 - 0.75 23.40
13.02 PINTURA DE CONTRAZOCALO C/ESMALTE 34.00 m
Aulas primer y segundo piso - interior 2 4.60 - - 9.20
Escalera primer piso (Depósito) 2 3.80 - - 7.60
Contrazócalo exterior 2 8.60 17.20
14 INSTALACIONES SANITARIAS
14.01 APARATOS Y ACCESORIOS SANITARIOS
14.01.01 INODORO TANQUE ALTO 8 8.00 8.00 und
14.01.02 LAVADERO CORRIDO C/MAYOLICA 5 4.55 4.55 m
14.01.03 URINARIO CORRIDO C/MAYOLICA 2 1.98 1.98 m
14.02 TUBERIAS Y ACCESORIOS
14.02.01 SALIDA DE DESAGUE EN PVC SAL DE 2" 5 5.00 5.00 pto
14.02.02 SALIDA DE DESAGUE EN PVC SAL DE Ø4" 8 8.00 8.00 m
14.02.03 TUBERIA PVC SAL DE Ø2" 40 40.00 40.00 m
14.02.04 TUBERIA PVC SAL DE Ø4" 80 80.00 80.00 m
14.02.05 SUMIDERO DE 2" 2 2.00 2.00 und
14.02.06 REGISTRO DE BRONCE,2" 2 2.00 2.00 und
14.02.07 REGISTRO DE BRONCE, 4" 8 8.00 8.00 und
14.02.08 SALIDA DE VENTILACION 2 2.00 2.00 pto
14.02.09 CAJA DE REGISTRO DE DESAGUE 12"X24" C/TAPA DE CONCRETO1 1.00 1.00 und
14.02.10 YEE PVC SAL 4" 8 8.00 8.00 und
14.02.11 YEE PVC SAL 2" 8 8.00 8.00 und
14.03 SISTEMA DE AGUA FRIA
14.03.01 SALIDA DE AGUA FRIA 16 16.00 16.00 pto
14.03.02 VALVULA COMPUERTA DE BRONCE DE UNION ROSCADA DE Ø1/2"5 5.00 5.00 und
14.03.03 VALVULA COMPUERTA DE BRONCE DE UNION ROSCADA DE Ø3/4"1 1.00 1.00 und
14.03.04 TUBERIA PVC SAP Ø3/4" 20 20.00 20.00 ml
14.03.05 TUBERIA PVC SAP Ø1/2" 60 60.00 60.00 ml
14.03.06 GRIFO 1/2" 4 4.00 4.00 und
14.03.07 CODO PVC SAP Ø1/2" 60 60.00 60.00 und
14.03.08 CODO GALVANIZADO Ø1/2" 16 16.00 16.00 und
14.03.09 REDUCCION PVC DE Ø3/4" A Ø1/2" 5 5.00 5.00 und
14.03.10 CRUZ 3/4" 1 1.00 1.00 und
14.03.11 TEE 1/2" 14 14.00 14.00 und
14.03.12 TEE 3/4" 1 1.00 1.00 und
14.04 SISTEMA DE AGUA DE LLUVIA
14.04.01 CANALETA DE FºGº 6" 17 16.80 16.80 m
14.04.02 TUBERIA DE BAJADA PVC SAP 3" 11 11.20 11.20 m
14.04.03 CODO PVC SAP 3" 6 6.00 6.00 und
14.04.04 CANAL DE CONCRETO F`C=175KG/CM2 1 34.72 34.72 34.72 m3
14.04.05 REJILLA DE PLATINA 3/4" P/CANAL 1 34.72 34.72 34.72 m
PROYECTO SNIP 107240
COMPONENTE
FORMULA
Lugar : CP. ICHOCA - HUARAZ - ANCASH
Fecha : MAYO DEL 2010
LARGO ANCHO ALTONº DE
VECESMEDIDAS
PARCIAL TOTAL UND.Nº DE LADO
S
PLANILLA DE METRADOS: "MEJORAMIENTO DE LOS SERVICIOS EDUCATIVOS DE LA I.E. 86079 – ICHOCA, DISTRITO DE HUARAZ, PROVINCIA DE HUARAZ - ANCASH"
: "CONSTRUCCIÓN DE AULAS Y SERVICIOS HIGIÉNICOS DE LA I.E. 86079 - ICHOCA"
PARTIDA Nº DESCRIPCION
: CONSTRUCCION DE SERVICIOS HIGIENICOS
15 INSTALACIONES ELECTRICAS
15.01 TUBERIAS Y ACCESORIOS
15.01.01 SALIDA DE PARED C/CABLE AWG TW 2.5 MM(14)+PVC SEL 20MM(3/4) 2 2.00 2.00 pto
15.01.02 SALIDA DE TECHO C/CABLE AWG TW 2.5MM(14) + PVC SEL 20MM(3/4)6 6.00 6.00 pto
15.02 TABLEROS DE DISTRIBUCION Y ACCESORIOS
15.02.01 TABLERO DE DISTRIBUCION ELECTRICA DE 1 CIRCUITO1 1.00 1.00 und
15.02.02 INTERRUPTOR TERMOMAGNETICO 2X15AMP1 1.00 1.00 und
15.03 CONDUCTORES Y/O CABLES
15.03.01 CABLE ELECTRICO 2.5 mm2 THW, #14 1 100.00 100.00 100.00 m
15.04 INSTALACION DE LUMINARIAS Y ACCESORIOS
15.04.01 ARTEFACTOS FLUORESCENTES 2/20W + LAMPARAS4 4.00 4.00 und
15.04.02 ARTEFACTOS FLUORESCENTES 2/40W + LAMPARAS2 2.00 2.00 und
16 FLETES
16.01 FLETE 1 1.00 1.00 glb