CAPITULO SUBCAPITULO ACTIVIDAD CODIGO ITEM UNIDAD CANTIDAD VALOR UNITARIO VALOR TOTAL 1.PRELIMINARES 1.1 CAMPAMENTO P. CAMP 01 CAMPAMENTO UN 1 $768,134.30 $768,134.30 1.2 DESCAPOTE P. DESC 01 DESCAPOTE M2 162 $25,610.86 $4,148,959.32 1.3 REPLANTEO 1.3.2 CIMENTACIÓN GENERAL P. REPL 03 CIMENTACION M2 162 $6,207.02 $1,005,537.24 1.3.3 PILOTES P. REPL 03 PILOTES M2 18.85 $6,207.02 $117,002.33 2. EXCAVACIONES 2.1 CIMENTACION 2.2.1 EXCAVACION PILOTES M. CIM 01 PILOTES M3 339.3 $524,740.00 $178,044,282.00 2.2.2 EXCAVACION GENERAL M. CIM 02 CIMENTACION M3 162 $36,611.98 $5,931,140.76 3. ESTRUCTURA 3.1 CIMENTACION 2.3.1 PILOTES E. CIM 01 PILOTES M3 339.3 $524,740.00 $178,044,282.00 2.3.2 DEMOLICION PILOTES E. CIM 02 DEMOLICION PILOTES M3 7.54 $39,882,230.00 $300,712,014.20 2.3.3 PLACA FLOTANTE E. CIM 03 PLACA FLOTANTE M3 64.8 $20,664,901.00 $1,339,085,584.80 3.2 PISOS TIPO 3.2.1 COLUMNAS E.PRIM 01 COLUMNAS M3 25.2 $615,020.54 $15,498,517.61 3.2.2 PLACA ALIGERADA E.PRIM 02 PLACA ALIGERADA M2 972 $129,900.58 $126,263,363.76 3.3 PISOS TIPO 3.3.1 ESCALERAS E. PRIM 04 ESCALERAS M3 5.3 837441.7578 4438441.316 4. CERRAMIENTOS 4.1 PISOS TIPO 4.2.1 MAMPOSTERIA REFORZADA E. PRIM 03 MAMPOSTERIA M2 1108.56 $66,702.03 $73,943,202.38 4.2.2 VENTANERIA E. SEG 10 VENTANERIA UN 54 $120,000.00 $6,480,000.00 5. DIVISIONES 5.1 PISOS TIPO 5.1.1 DIVISIONES E. SEG 05 MUROS M2 1231.2 $79,779.34 $98,224,323.41 6. ACABADOS 6.1 PISOS TIPO 6.2.1 PAREDES E. SEG 09 PAREDES M2 1108.56 $16,863.76 $18,694,489.79 6.2.2 MADERA PISO E. SEG 08 PISO M2 972 $59,990.00 $58,310,280.00 6.2.3 PUERTAS BANOS E. SEG 07 PUERTA UN 12 $140,296.00 $1,683,552.00 6.2.4 PUERTAS OFICINAS E. SEG 06 PUERTA UN 30 $168,545.40 $5,056,362.00 7. INSTALACIONES 7.1 DUCTOS 7.1.1 DUCTO VERTICAL E. DUC 01 DUCTO ML 17.3 $86,900.16 $1,503,372.77 TOTAL $2,417,952,841.97

Transcript of 5. presupuesto general

Page 1: 5. presupuesto general

CAPITULO SUBCAPITULO ACTIVIDAD CODIGO ITEM UNIDAD CANTIDAD VALOR  UNITARIO VALOR  TOTAL1.PRELIMINARES 1.1  CAMPAMENTO P.  CAMP  01 CAMPAMENTO UN 1 $768,134.30 $768,134.30

1.2  DESCAPOTE P.  DESC  01 DESCAPOTE M2 162 $25,610.86 $4,148,959.32

1.3  REPLANTEO 1.3.2  CIMENTACIÓN  GENERAL P.  REPL  03 CIMENTACION M2 162 $6,207.02 $1,005,537.241.3.3  PILOTES P.  REPL  03 PILOTES M2 18.85 $6,207.02 $117,002.33

2.  EXCAVACIONES 2.1  CIMENTACION 2.2.1  EXCAVACION  PILOTES M.  CIM  01 PILOTES M3 339.3 $524,740.00 $178,044,282.002.2.2  EXCAVACION  GENERAL M.  CIM  02 CIMENTACION M3 162 $36,611.98 $5,931,140.76

3.  ESTRUCTURA 3.1  CIMENTACION 2.3.1  PILOTES   E.  CIM  01 PILOTES M3 339.3 $524,740.00 $178,044,282.002.3.2  DEMOLICION  PILOTES   E.  CIM  02 DEMOLICION  PILOTES M3 7.54 $39,882,230.00 $300,712,014.202.3.3  PLACA  FLOTANTE   E.  CIM  03 PLACA  FLOTANTE M3 64.8 $20,664,901.00 $1,339,085,584.80

3.2  PISOS  TIPO 3.2.1  COLUMNAS   E.PRIM  01 COLUMNAS M3 25.2 $615,020.54 $15,498,517.613.2.2  PLACA  ALIGERADA   E.PRIM  02 PLACA  ALIGERADA M2 972 $129,900.58 $126,263,363.76

3.3  PISOS  TIPO   3.3.1  ESCALERAS   E.  PRIM  04 ESCALERAS   M3   5.3 837441.7578 4438441.316

4.  CERRAMIENTOS 4.1  PISOS  TIPO 4.2.1  MAMPOSTERIA  REFORZADA   E.  PRIM  03 MAMPOSTERIA M2 1108.56 $66,702.03 $73,943,202.384.2.2  VENTANERIA   E.  SEG  10 VENTANERIA   UN 54 $120,000.00 $6,480,000.00

5.  DIVISIONES 5.1  PISOS  TIPO 5.1.1  DIVISIONES E.  SEG  05 MUROS   M2 1231.2 $79,779.34 $98,224,323.41

6.  ACABADOS 6.1  PISOS  TIPO 6.2.1  PAREDES E.  SEG  09 PAREDES M2 1108.56 $16,863.76 $18,694,489.796.2.2  MADERA  PISO   E.  SEG  08 PISO M2 972 $59,990.00 $58,310,280.006.2.3  PUERTAS  BANOS   E.  SEG  07 PUERTA   UN 12 $140,296.00 $1,683,552.006.2.4  PUERTAS  OFICINAS   E.  SEG  06 PUERTA   UN 30 $168,545.40 $5,056,362.00

7.  INSTALACIONES 7.1  DUCTOS 7.1.1  DUCTO  VERTICAL   E.  DUC  01 DUCTO   ML 17.3 $86,900.16 $1,503,372.77

TOTAL $2,417,952,841.97