HOJA DE METRADOSPROY: "CASO EJE"
CURSO: CONSTRUCCIONES II
REVISADO POR: Ing. CAMARENA HUAYANAY, Max AntonioFecha 9/5/2013
ELABORADO POR: ANCHIRAYCO RIMARI,Christian
PARTIDA DESCRIPCION VECESMETRADO
SUB TOTAL TOTAL UNDLARGO ANCHO ALTOOE.2 ESTRUCTURAS
OE. 2.2 OBRAS DE CONCRETO SIMPLE
OE. 2.2.1 CIMIENTO CORRIDO 1:10 + 30% PG (max 6%) 28.67 m3
Eje H-H, Entre 1-2 1.00 4.63 0.50 0.90 2.08Eje I-I, Entre 1-2 1.00 4.63 0.50 0.90 2.08Eje J´-J´,Entre 1-2 1.00 4.63 0.40 0.90 1.67Eje K´-K´,Entre 1-2 1.00 4.63 0.40 0.90 1.67Eje L-L, Entre 1-2 1.00 4.63 0.50 0.90 2.08Eje 1-1 y 2-2, Entre H-I 2.00 3.00 0.40 0.90 2.16
Eje 1-1 y 2-2, Entre I-J´ 2.00 5.00 0.40 0.90 3.60
Eje 1-1,Entre I-J´, ENSANCHE DE CIMIENTO 1.00 0.50 0.50 0.90 0.23
Eje 2-2,Entre I-J´, ENSANCHE DE CIMIENTO 1.00 0.50 0.60 0.90 0.27
Eje 1-1 y 2-2, Entre J´-K´ 2.00 1.40 0.40 0.90 1.01
Eje 1-1 y 2-2, Entre J´-K´, ENSANCHE DE CIMIENTO 2.00 0.50 0.50 0.90 0.45
Eje 1-1 y 2-2, Entre K´-L 2.00 1.80 0.40 0.90 1.30
Eje I-I y K-K, Entre 2-2´ 2.00 0.95 0.50 0.90 0.86
Eje 2´-2´, Entre I-K 1.00 7.50 0.40 0.90 2.70
Eje 3-3, Entre I-K 1.00 7.50 0.40 0.90 2.70
Eje I-I, Entre 2´-3 1.00 3.03 0.50 0.90 1.36
Eje I´-I´, Entre 2´-3 1.00 3.03 0.40 0.90 1.09
Eje K-K, Entre 2´-3 1.00 3.03 0.50 0.90 1.36
OE. 2.2.4 BASES DE CONCRETO
OE. 2.2.4.1 CONCRETO PARA SUBCIMIENTO 1:12 + 30% PG 0.30 m3
Eje 3-3, Entre I-K 1.00 7.50 0.40 0.10 0.30
OE. 2.2.6 SOBRECIMIENTOS
OE. 2.2.6.1 PARA EL CONCRETO 1:8 + 25% PM (max 4") 4.50 m3
OE. 2.2.6.1.1 ANCHO 0.23 3.20
Eje H-H , I-I y L-L, Entre 1-2 3.00 4.01 0.23 0.40 1.11
Eje 1-1, Entre H-I 1.00 3.25 0.23 0.40 0.30
Eje 1-1, Entre I-J 1.00 3.25 0.23 0.40 0.30
Eje 1-1, Entre J-J´ 1.00 2.25 0.23 0.40 0.21
Eje 1-1, Entre J´-K 1.00 0.85 0.23 0.40 0.08
Eje 1-1, Entre K-K´ 1.00 1.05 0.23 0.40 0.10
Eje 1-1, Entre K´-L 1.00 2.05 0.23 0.40 0.19
Eje 3-3, Entre I-J 1.00 2.05 0.23 0.40 0.19
Eje 3-3, Entre J-K 1.00 3.25 0.23 0.40 0.30
Eje I-I, Entre 2´-3 1.00 1.50 0.23 0.40 0.14
Eje K-K, Entre 2´-3 1.00 3.30 0.23 0.40 0.30
OE. 2.2.6.1.2 ANCHO 0.13 1.29
Eje J´-J´y K´-K´, Entre 1-2 2.00 4.01 0.13 0.40 0.42
Eje 2-2, Entre H-I 1.00 2.05 0.13 0.40 0.11
Eje 2-2, Entre I-J 1.00 3.25 0.13 0.40 0.17
Eje 2-2, Entre J-J´ 1.00 1.05 0.13 0.40 0.05
Eje 2-2, Entre K-K´ 1.00 1.05 0.13 0.40 0.05
Eje 2-2, Entre K´-L 1.00 1.20 0.13 0.40 0.06
Eje 2´-2´, Entre I-J, J-K 2.00 3.25 0.13 0.40 0.34
Eje I´-I´, Entre 2´-3 1.00 1.71 0.13 0.40 0.09
OE. 2.2.6.2 PARA EL ENCOFRADO Y DESENCOFRADO 28.06 m2
Eje 1-1, Entre H-I y I-J 2.00 3.25 0.40 2.60
Eje 1-1, Entre J-J´ 1.00 2.25 0.40 0.90
Eje 1-1, Entre J´-K 1.00 0.85 0.40 0.34
Eje 1-1, Entre K-K´ 1.00 1.05 0.40 0.42
Eje 1-1, Entre K´-L 1.00 2.05 0.40 0.82
Eje 2-2, Entre H-J 1.00 2.05 0.40 0.82
Eje 2-2, Entre I-J 1.00 3.25 0.40 1.30
Eje 2-2, Entre J-J´ 1.00 1.05 0.40 0.42
Eje 2-2, Entre K-K´ 1.00 1.05 0.40 0.42
PARTIDA DESCRIPCION VECESMETRADO
SUB TOTAL TOTAL UNDLARGO ANCHO ALTO
Eje 2-2, Entre K´-L 1.00 1.20 0.40 0.48
PARTIDA DESCRIPCION VECESMETRADO
SUB TOTAL TOTAL UNDLARGO ANCHO ALTO
Eje H-H, I-I y L-L,Entre 1-2 3.00 4.01 0.40 4.81
Eje J´-J´ y K´-K´,Entre 1-2 2.00 4.01 0.40 3.21
Eje 2´-2´, Entre H-J y J-K 2.00 3.25 0.40 2.60
Eje 3-3, Entre H-J 2.00 0.53 0.40 0.42
Eje 3-3, Entre H-J 1.00 0.84 0.40 0.34
Eje 3-3, Entre J-K 1.00 3.25 0.40 1.30
Eje I-I ,Entre 1-2 1.00 0.60 0.40 0.24
Eje I-I ,Entre 1-2 1.00 0.90 0.40 0.36
Eje I´-I´ ,Entre 1-2 1.00 0.58 0.40 0.23
Eje I´-I´ ,Entre 1-2 1.00 1.13 0.40 0.45
Eje K-K,Entre 1-2 1.00 3.30 0.40 1.32
Tapas donde culmina sobrecimientos de 15 cm 4.00 0.15 0.40 0.24
Tapas donde culmina sobrecimientos de 25 cm 4.00 0.25 0.40 0.40
Tapas para columna de 15 cm 17.00 0.15 0.40 1.02
Tapas para columna de 25 cm 26.00 0.25 0.40 2.60
OE 2.2.9 FALSO PISO 86.23 m2
ALMACEN GENERAL - PEQUEÑO 1.00 3.25 4.11 13.36
sumar 1.00 1.20 0.15 0.18
ALMACEN GENERAL - GRANDE 1.00 5.75 4.11 23.63
restar -1.00 0.25 0.10 -0.03
sumar 1.00 1.20 0.15 0.18
S.H.D 1.00 2.15 4.11 8.84
restar -1.00 0.25 0.10 -0.03
sumar 1.00 0.85 0.15 0.13
S.H.V 1.00 2.05 4.11 8.43
sumar 1.00 0.85 0.15 0.13
CAMARA FRIGORIFICA 1.00 4.34 3.30 14.32
sumar 1.00 1.20 0.15 0.18
VESTIBULO 1.00 2.26 3.30 7.46
sumar 1.00 1.20 0.25 0.30
sumar 1.00 1.80 0.25 0.45
PASADIZO 1.00 7.25 1.20 8.70
HOJA DE METRADOSPROY: "CASO EJE"
CURSO: CONSTRUCCIONES II
REVISADO POR: Ing. CAMARENA HUAYANAY, Max AntonioFecha 9/5/2013
ELABORADO POR: ANCHIRAYCO RIMARI,Christian
PARTIDA DESCRIPCION VECESMETRADO
SUB TOTAL TOTAL UNDLARGO ANCHO ALTOOE.2 ESTRUCTURAS
OE. 2.2 OBRAS DE CONCRETO SIMPLE
OE. 2.2.1 CIMIENTO CORRIDO 1:10 + 30% PG (max 6%) 28.67 m3
Eje H-H, Entre 1-2 1.00 4.63 0.50 0.90 2.08Eje I-I, Entre 1-2 1.00 4.63 0.50 0.90 2.08Eje J´-J´,Entre 1-2 1.00 4.63 0.40 0.90 1.67Eje K´-K´,Entre 1-2 1.00 4.63 0.40 0.90 1.67Eje L-L, Entre 1-2 1.00 4.63 0.50 0.90 2.08Eje 1-1 y 2-2, Entre H-I 2.00 3.00 0.40 0.90 2.16
Eje 1-1 y 2-2, Entre I-J´ 2.00 5.00 0.40 0.90 3.60
Eje 1-1,Entre I-J´, ENSANCHE DE CIMIENTO 1.00 0.50 0.50 0.90 0.23
Eje 2-2,Entre I-J´, ENSANCHE DE CIMIENTO 1.00 0.50 0.60 0.90 0.27
Eje 1-1 y 2-2, Entre J´-K´ 2.00 1.40 0.40 0.90 1.01
Eje 1-1 y 2-2, Entre J´-K´, ENSANCHE DE CIMIENTO 2.00 0.50 0.50 0.90 0.45
Eje 1-1 y 2-2, Entre K´-L 2.00 1.80 0.40 0.90 1.30
Eje I-I y K-K, Entre 2-2´ 2.00 0.95 0.50 0.90 0.86
Eje 2´-2´, Entre I-K 1.00 7.50 0.40 0.90 2.70
Eje 3-3, Entre I-K 1.00 7.50 0.40 0.90 2.70
Eje I-I, Entre 2´-3 1.00 3.03 0.50 0.90 1.36
Eje I´-I´, Entre 2´-3 1.00 3.03 0.40 0.90 1.09
Eje K-K, Entre 2´-3 1.00 3.03 0.50 0.90 1.36
OE. 2.2.4 BASES DE CONCRETO
OE. 2.2.4.1 CONCRETO PARA SUBCIMIENTO 1:12 + 30% PG 0.30 m3
Eje 3-3, Entre I-K 1.00 7.50 0.40 0.10 0.30
OE. 2.2.6 SOBRECIMIENTOS
OE. 2.2.6.1 PARA EL CONCRETO 1:8 + 25% PM (max 4") 4.97 m3
OE. 2.2.6.1.1 ANCHO 0.25 3.48
Eje H-H , I-I y L-L, Entre 1-2 3.00 4.01 0.25 0.40 1.20
Eje 1-1, Entre H-I 1.00 3.25 0.25 0.40 0.33
Eje 1-1, Entre I-J 1.00 3.25 0.25 0.40 0.33
Eje 1-1, Entre J-J´ 1.00 2.25 0.25 0.40 0.23
Eje 1-1, Entre J´-K 1.00 0.85 0.25 0.40 0.09
Eje 1-1, Entre K-K´ 1.00 1.05 0.25 0.40 0.11
Eje 1-1, Entre K´-L 1.00 2.05 0.25 0.40 0.21
Eje 3-3, Entre I-J 1.00 2.05 0.25 0.40 0.21
Eje 3-3, Entre J-K 1.00 3.25 0.25 0.40 0.33
Eje I-I, Entre 2´-3 1.00 1.50 0.25 0.40 0.15
Eje K-K, Entre 2´-3 1.00 3.30 0.25 0.40 0.33
OE. 2.2.6.1.2 ANCHO 0.15 1.49
Eje J´-J´y K´-K´, Entre 1-2 2.00 4.01 0.15 0.40 0.48
Eje 2-2, Entre H-I 1.00 2.05 0.15 0.40 0.12
Eje 2-2, Entre I-J 1.00 3.25 0.15 0.40 0.20
Eje 2-2, Entre J-J´ 1.00 1.05 0.15 0.40 0.06
Eje 2-2, Entre K-K´ 1.00 1.05 0.15 0.40 0.06
Eje 2-2, Entre K´-L 1.00 1.20 0.15 0.40 0.07
Eje 2´-2´, Entre I-J, J-K 2.00 3.25 0.15 0.40 0.39
Eje I´-I´, Entre 2´-3 1.00 1.71 0.15 0.40 0.10
OE. 2.2.6.2 PARA EL ENCOFRADO Y DESENCOFRADO 24.18 m2
Eje H-H , I-I y L-L, Entre 1-2 3.00 4.01 0.40 4.81
Eje J´-J´y K´-K´, Entre 1-2 2.00 4.01 0.40 3.21
Eje 1-1, Entre H-I 1.00 3.25 0.40 1.30
Eje 1-1, Entre I-J 1.00 3.25 0.40 1.30
Eje 1-1, Entre J-J´ 1.00 2.25 0.40 0.90
Eje 1-1, Entre J´-K 1.00 0.85 0.40 0.34
Eje 1-1, Entre K-K´ 1.00 1.05 0.40 0.42
Eje 1-1, Entre K´-L 1.00 2.05 0.40 0.82
Eje 2-2, Entre H-I 1.00 2.05 0.40 0.82
PARTIDA DESCRIPCION VECESMETRADO
SUB TOTAL TOTAL UNDLARGO ANCHO ALTO
Eje 2-2, Entre H-I Tapa Frontal 1.00 0.15 0.40 0.06
PARTIDA DESCRIPCION VECESMETRADO
SUB TOTAL TOTAL UNDLARGO ANCHO ALTO
Eje 2-2, Entre I-J 1.00 3.25 0.40 1.30
Eje 2-2, Entre J-J´ 1.00 1.05 0.40 0.42
Eje 2-2, Entre J-J´ Tapa Frontal 1.00 0.15 0.40 0.06
Eje 2-2, Entre K-K´ 1.00 1.05 0.40 0.42
Eje 2-2, Entre K´-L 1.00 1.20 0.40 0.48
Eje 2-2, Entre K´-L Tapa Frontal 1.00 0.15 0.40 0.06
Eje 2´-2´, Entre I-J, J-K 2.00 3.25 0.40 2.60
Eje 3-3, Entre I-J 2.00 0.53 0.40 0.42
Eje 3-3, Entre I-J 1.00 0.84 0.40 0.34
Eje 3-3, Entre I-J Tapa Frontal 1.00 0.25 0.40 0.10
Eje 3-3, Entre J-K 1.00 3.25 0.40 1.30
Eje I-I, Entre 2´-3 1.00 1.50 0.40 0.60
Eje I-I, Entre 2´-3 Tapa Frontal 1.00 0.25 0.40 0.10
Eje I´-I´, Entre 2´-3 1.00 1.71 0.40 0.68
Eje K-K, Entre 2´-3 1.00 3.30 0.40 1.32
OE 2.2.9 FALSO PISO 86.23 m2
ALMACEN GENERAL - PEQUEÑO 1.00 3.25 4.11 13.36
sumar 1.00 1.20 0.15 0.18
ALMACEN GENERAL - GRANDE 1.00 5.75 4.11 23.63
restar -1.00 0.25 0.10 -0.03
sumar 1.00 1.20 0.15 0.18
S.H.D 1.00 2.15 4.11 8.84
restar -1.00 0.25 0.10 -0.03
sumar 1.00 0.85 0.15 0.13
S.H.V 1.00 2.05 4.11 8.43
sumar 1.00 0.85 0.15 0.13
CAMARA FRIGORIFICA 1.00 4.34 3.30 14.32
sumar 1.00 1.20 0.15 0.18
VESTIBULO 1.00 2.26 3.30 7.46
sumar 1.00 1.20 0.25 0.30
sumar 1.00 1.80 0.25 0.45
PASADIZO 1.00 7.25 1.20 8.70
REQUERIMIENTO PARA CIMIENTOS CORRIDOS REQUERIMIENTO PARA SOBRECIMIENTOS
Dosificación: Para: Dosificación: Para:
1:10 + 30% PM CONCRETO 1:8 + 25% PM CONCRETO
METRADO: 28.67 METRADO: 4.97
Materiales unid. Dosificacion Requerimiento Materiales unid. Dosificacion Requerimiento
Cemento bls 2.9 83.13 87.29 Cemento bls 3.7 18.40 19.32
Hormigon m3 0.83 23.79 24.98 Hormigon m3 0.85 4.23 4.44
Piedra Mediana m3 0.48 13.76 14.45 Piedra Mediana m3 0.4 1.99 2.09
Agua m3 0.1 2.87 3.01 Agua m3 0.13 0.65 0.68
EL REQUERIMIENTO SERA DE : EL REQUERIMIENTO SERA DE :
Materiales Dosificacion unid. Materiales Dosificacion unid.
Cemento 88 bls Cemento 20 bls
Hormigon 25 m3 Hormigon 5 m3
Piedra Mediana 15 m3 Piedra Mediana 3 m3
Agua 4 m3 Agua 1 m3
Desperdicios (5%)
Desperdicios (5%)
DATOS: PROPORCIONPIEDRA 25 % 1:8 + 25% P.MRELACION 1 : 8A/C 0.8CEMENTO 42.5
PROCEDIMIENTO DE CALCULOCALCULO PREVIO DE PESOS SECOS
Cemento: 1 p3 = 42.5 kgHormigon: 8 p3 x 1800 kg/m3 / 35.315 p3 = 407.8 kgAgua: 42.5 kg x 0.8 = 34 kg
DENDIMIENTO DE LAMEZCLA (VOLUMENES ABSOLUTOS)Cemento: 42.5 kg / 3150 kg/m3 = 0.0135 m3Hormigon: 407.8 kg / 2700 kg/m3 = 0.1510 m3Agua: 34 kg / 1000 kg/m3 = 0.0340 m3
TOTAL = 0.1985 m3
V(1 m3)= 1 - 0.25 -0.01 = 0.74 m3factor cemento 0.74 / 0.1985 = 3.73 bolsas
CANTIDAD DE MATERIALCemento: = 3.73 = 3.70Hormigon: = 0.845 m3 = 0.85Agua: = 126.82 lt 0.127 = 0.13piedra: = 0.3971 m3 = 0.40
DATOS: PROPORCIONPIEDRA 30 % 1:10 + 30% P.MRELACION 1 : 10A/C 0.8CEMENTO 42.5
PROCEDIMIENTO DE CALCULOCALCULO PREVIO DE PESOS SECOS
Cemento: 1 p3 = 42.5 kgHormigon: 10 p3 x 1800 kg/m3 / 35.315 p3 = 509.7 kgAgua: 42.5 kg x 0.8 = 34 kg
DENDIMIENTO DE LAMEZCLA (VOLUMENES ABSOLUTOS)Cemento: 42.5 kg / 3150 kg/m3 = 0.0135 m3Hormigon: 509.7 kg / 2700 kg/m3 = 0.1888 m3Agua: 34 kg / 1000 kg/m3 = 0.0340 m3
TOTAL = 0.2363 m3
V(1 m3)= 1 - 0.3 -0.01 = 0.69 m3factor cemento 0.69 / 0.2363 = 2.92 bolsas
CANTIDAD DE MATERIALCemento: = 2.92 = 2.90Hormigon: = 0.827 m3 = 0.83Agua: = 99.28 lt 0.099 = 0.10piedra: = 0.4765 m3 = 0.48
DATOS: PROPORCIONPIEDRA 30 % 1:12 + 30% P.MRELACION 1 : 12A/C 0.8CEMENTO 42.5
PROCEDIMIENTO DE CALCULOCALCULO PREVIO DE PESOS SECOS
Cemento: 1 p3 = 42.5 kgHormigon: 12 p3 x 1800 kg/m3 / 35.315 p3 = 611.6 kgAgua: 42.5 kg x 0.8 = 34 kg
DENDIMIENTO DE LAMEZCLA (VOLUMENES ABSOLUTOS)Cemento: 42.5 kg / 3150 kg/m3 = 0.0135 m3Hormigon: 611.6 kg / 2700 kg/m3 = 0.2265 m3Agua: 34 kg / 1000 kg/m3 = 0.0340 m3
TOTAL = 0.2740 m3
V(1 m3)= 1 - 0.3 -0.01 = 0.69 m3factor cemento 0.69 / 0.2740 = 2.52 bolsas
CANTIDAD DE MATERIALCemento: = 2.52 = 2.50Hormigon: = 0.856 m3 = 0.86Agua: = 85.68 lt 0.086 = 0.09piedra: = 0.4765 m3 = 0.48
REQUERIMIENTO PARA CIMIENTOS CORRIDOSDOSIFICACION 1:10 + 30% PMPara Concreto
METRADO= 28.67 PAG.77PAG84
Und. Dosificacion Desperdicios (5%)Cemento bls 2.9 83.13 87.29Hormigon m3 0.83 23.79 24.98Piedra Mediana m3 0.48 13.76 14.45Agua m3 0.1 2.87 3.01
EL REQUERIMIENTO SERA DE :
Und.
Cemento 88.00 blsHormigon 25.00 m3Piedra Mediana 15.00 m3Agua 4.00 m3
REQUERIMIENTO PARA CIMIENTOS CORRIDOSDOSIFICACION 1:10 + 30% PMPara Concreto
METRADO= 4.97 PAG.77PAG84
Und. Dosificacion Desperdicios (5%)Cemento bls 2.9 83.13 87.29Hormigon m3 0.83 23.79 24.98Piedra Mediana m3 0.48 13.76 14.45Agua m3 0.1 2.87 3.01
EL REQUERIMIENTO SERA DE :
Und.
Cemento 88.00 blsHormigon 25.00 m3Piedra Mediana 15.00 m3Agua 4.00 m3
REQUERIMIENTO PARA SOBRECIMIENTOSDOSIFICACION 1:8 + 25% PMPara Concreto
METRADO= 4.97
unid. Dosificacion Desperdicios (5%)Cemento bls 3.7 18.40 19.32Hormigon m3 0.85 4.23 4.44Piedra Mediana m3 0.4 1.99 2.09Agua m3 0.13 0.65 0.68
EL REQUERIMIENTO SERA DE :
Cemento 20.00 blsHormigon 5.00 m3Piedra Mediana 3.00 m3Agua 1.00 m3